Vol1_Specifications_Final_Construction_Documents_May_2021_0002.pdf
PDF 5 MB Posted
- Attached to
- GRCA - 229035 Phantom Ranch Wastewater Treatment P Federal contract opportunity
- Solicitation number
- 140P2021R0127
About this file
This document outlines specifications for construction work at the Phantom Ranch Wastewater Treatment Plant in Grand Canyon National Park. The project involves interim improvements including installation of a new influent screen, equalization tank mixer, integrated fixed film activated sludge system, blower modifications, final clarifier tube settlers, automatic backwash filter, digester modifications, and control panel and electrical upgrades. The contractor must coordinate work sequences to maintain continuous plant operations, with shutdowns of individual processes requiring advanced planning and approval. The contractor is responsible for permitting, environmental protection, quality control, and commissioning. The National Park Service is the contracting agency, with a preconstruction conference and regular progress meetings required over the course of the project.
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FINAL
Construction Documents
Volume 1 Specifications
May 2021
Prepared for the
National Park Service
Phantom Ranch Wastewater Treatment Plant
Short Term Improvements
Volume 1 Specifications
Prepared for the
National Park Service
Phantom Ranch Wastewater Treatment Plant
Short Term Improvements
PPS0323210011CVO
FINAL
Construction Documents
May 2021
NATIONAL PARK SERVICE
GRAND CANYON NATIONAL PARK
BIDDING REQUIREMENTS
AND
CONTRACT DOCUMENTS
for the construction of the
PHANTOM RANCH WASTEWATER TREATMENT PLANT
SHORT TERM IMPROVEMENTS
Contract No. GRCA-229035
Final Construction Documents
SPECIFICATIONS
CH2M
Phoenix, Arizona
May 2021
Project No. D3167624 Copy No.
GRCA – 229035 00 01 07 - 1
MAY 2021 SEALS PAGE
SECTION 00 01 07
SEALS PAGE
SPECIFICATIONS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00, 01 26 01, 01 27 00, 01 31 00, 01 32 16, 01 32 33, 01 33 23, 01 35 13.22, 01 35 23, 01 35 91, 01 40 00, 01 42 00, 01 43 00, 01 50 00, 01 57 19.11, 01 57 19.12, 01 57 23, 01 67 00, 01 73 29, 01 73 40, 01 74 19, 01 77 00, 01 78 23, 01 79 00, 01 81 13, 01 91 14
Digitally Signed on
May 21, 2021
Jennifer Phillips
GRCA – 229035 00 01 07 - 2
DIVISION 01 – GENERAL REQUIREMENTS
01 88 15
DIVISION 03 – CONCRETE
DIVISION 05 – METALS
Liao Yang
GRCA – 229035 00 01 07 - 3
SPECIFICATIONS
DIVISION 02 – EXISTING CONDITIONS
DIVISION 40 – PROCESS INTERCONNECTIONS
DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION
AND STORAGE EQUIPMENT
DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT
DIVISION 46 – WATER AND WASTEWATER EQUIPMENT
Digitally Signed on
Kristen Griebel
GRCA – 229035 00 01 07 - 4
DIVISION 09 – FINISHES
Craig VanHorn
GRCA – 229035 00 01 07 - 5
DIVISION 26 – ELECTRICAL
Jim Landman
GRCA – 229035 00 01 07 - 5
SPECIFICATIONS
DIVISION 26 – ELECTRICAL
Digitally Signed on
James Landman
GRCA - 229035 00 01 10 - 1
MAY 2021 TABLE OF CONTENTS
TABLE OF CONTENTS
Pages
VOLUME 1
SPECIFICATIONS
DIVISION 01—GENERAL REQUIREMENTS
01 11 00 Summary of Work .................................................................... 1- 6 Supplements:
Inner Canyon Code of Conduct Bunkhouses ........................... 1- 2 Inner Canyon Bunkhouse Checklist ......................................... 1- 3 01 26 01 Contract Modification Procedures ........................................... 1- 6 01 27 00 Definition of Contract Line Items ............................................ 1- 1 Supplement:
Contract Price Schedule Template ........................................... 1- 1 01 31 00 Project Management and Coordination ................................... 1- 15 01 32 16 Construction Schedule ............................................................. 1- 10 01 32 33 Photo Documentation for Historic Preservation Projects ........ 1- 2 01 33 23 Submittal Procedures ............................................................... 1- 9 Supplement:
Submittal List ........................................................................... 1- 11 01 35 13.22 Archeological Protection ......................................................... 1- 3 01 35 23 Safety Requirements ................................................................ 1- 4 01 35 91 Historic Preservation Treatment Procedures ........................... 1- 7 01 40 00 Quality Requirements .............................................................. 1- 9 Supplements:
Fabricator’s Certificate of Compliance .................................... 1- 1 Statement of Structural Tests and Special Inspections ............ 1- 8 01 42 00 Reference Standards................................................................. 1- 11 01 43 33 Manufacturers’ Field Services ................................................. 1- 4 Supplement:
Manufacturer’s Certificate of Proper Installation .................... 1- 1 01 50 00 Temporary Facilities and Controls ........................................... 1- 8 01 57 19.11 Indoor Air Quality Management .............................................. 1- 6 01 57 19.12 Noise & Acoustics Management ............................................. 1- 2 01 57 23 Temporary Storm Water Pollution Prevention ........................ 1- 9 01 65 50 Product Delivery, Storage, and Handling ................................ 1- 5 01 67 00 Product Requirements .............................................................. 1- 8 01 73 29 Cutting and Patching ................................................................ 1- 4 01 73 40 Execution ................................................................................. 1- 8 01 74 19 Construction Waste Management and Disposal ...................... 1- 9 Supplements:
Appendix A: Project Waste Management Plan Worksheet ..... 1- 1 Appendix B: Standard Solid Waste Conversions .................... 1- 5
Pages
GRCA - 229035 00 01 10 - 2
01 77 00 Closeout Procedures................................................................. 1- 5 Supplement:
Closeout and Operation & Maintenance Requirements........... 1- 2 01 78 23 Operation and Maintenance Data ............................................. 1- 9 01 79 00 Demonstration and Training .................................................... 1- 4 01 81 13 Sustainable Design Requirements for Non LEEDTM Projects . 1- 4 01 88 15 Anchorage and Bracing ............................................................ 1- 6 01 91 14 Equipment Testing and Facility Startup .................................. 1- 6 Supplements:
Unit Process Startup Form ....................................................... 1- 1 Facility Performance Demonstration/Certification Form ........ 1- 1
DIVISION 02—EXISTING CONDITIONS
02 41 00 Demolition ............................................................................... 1- 4
DIVISION 03—CONCRETE
03 30 10 Structural Reinforced Concrete ................................................ 1- 23 Supplements:
Concrete Mix Design, Class 5000F3S1P2C2 .......................... 1- 2 Concrete Mix Design, Class 4500F1S1P0C1 .......................... 1- 2 03 62 00 Grouting ................................................................................... 1- 9 Supplement:
24-hour Evaluation of Nonshrink Grout Test Forms and Grout Testing Procedures ..................................................... 1- 3
DIVISION 04—NOT USED
DIVISION 05—METALS
05 05 19 Post-Installed Anchors ............................................................. 1- 7 05 50 00 Metal Fabrications ................................................................... 1- 11 05 53 00 Metal Gratings ......................................................................... 1- 5
DIVISIONS 06 THROUGH 08—NOT USED
DIVISION 09—FINISHES
09 90 00 Painting and Coating ................................................................ 1- 18 Supplements:
Paint System Data Sheet (PSDS) ............................................. 1- 1 Paint Product Data Sheet (PPDS) ............................................ 1- 1
GRCA - 229035 00 01 10 - 3
09 96 35 Chemical-Resistant Coatings ................................................... 1- 9 Supplements:
Chemical-Resistant Coating Data Sheet (CRCDS) ................. 1- 1 Chemical-Resistant Coating Product Data Sheet (CRCPDS) .. 1- 1
DIVISIONS 10 THROUGH 25—NOT USED
DIVISION 26—ELECTRICAL
26 05 02 Basic Electrical Requirements ................................................. 1- 6 Supplement:
Panelboard “P” Imbalance ....................................................... 1- 1 26 05 04 Basic Electrical Materials and Methods .................................. 1- 11 26 05 05 Conductors ............................................................................... 1- 9 26 05 26 Grounding and Bonding for Electrical Systems ...................... 1- 4 26 05 33 Raceway and Boxes ................................................................. 1- 14 26 05 70 Electrical Systems Analysis ..................................................... 1- 7 Supplement:
Figure 1: Example Arc Flash Label ......................................... 1- 1 26 08 00 Commissioning of Electrical Systems ..................................... 1- 13 26 20 00 Low-Voltage AC Induction Motors ......................................... 1- 4 26 24 16 Panelboards .............................................................................. 1- 6 26 24 19 Low-Voltage Motor Control .................................................... 1- 7 26 27 26 Wiring Devices ........................................................................ 1- 7 26 29 23 Low-Voltage Adjustable Frequency Drive System ................. 1- 9
DIVISIONS 27 THROUGH 30—NOT USED
DIVISION 31—EARTHWORK
31 10 00 Site Clearing............................................................................. 1- 2 31 23 16 Excavation................................................................................ 1- 3 31 23 23 Fill and Backfill ....................................................................... 1- 5 31 23 23.15 Trench Backfill ........................................................................ 1- 9
DIVISION 32—NOT USED
DIVISION 33—UTILITIES
33 05 01 Conveyance Piping—General .................................................. 1- 7 33 05 01.12.03 Polyvinyl Chloride (PVC)—Gravity Sanitary Sewer Data Sheet ............................................................................. 1- 1 33 05 13 Manholes .................................................................................. 1- 9
DIVISIONS 34 THROUGH 39—NOT USED
GRCA - 229035 00 01 10 - 4
DIVISION 40—PROCESS INTERCONNECTIONS
40 05 15 Piping Support Systems ........................................................... 1- 10 Supplements:
Table 1: Nonchemical Areas .................................................... 1- 1 Table 2: Chemical Areas .......................................................... 1- 1 40 05 33 Pipe Heat Tracing .................................................................... 1- 5 40 27 00 Process Piping—General ......................................................... 1- 17 Supplement:
Piping Schedule ....................................................................... 1- 2 40 27 00.07 Galvanized Steel Pipe and Malleable Iron Fittings Data Sheet ............................................................................. 1- 3 40 27 00.08 Stainless Steel Pipe and Fittings—General Service Data Sheet ............................................................................. 1- 2 40 27 00.10 Polyvinyl Chloride (PVC) Pipe and Fittings Data Sheet ......... 1- 2 40 27 01 Process Piping Specialties........................................................ 1- 9 40 27 02 Process Valves and Operators .................................................. 1- 8 Supplement:
Self-Regulated Valve Schedule ............................................... 1- 1 40 80 01 Process Piping Leakage Testing .............................................. 1- 6 40 90 01 Instrumentation and Control for Process Systems ................... 1- 19 Supplements:
Component Specifications ....................................................... 1- 10 Instrument List ......................................................................... 1- 1 Control Descriptions ................................................................ 1- 5 PLC Input/Output List ............................................................. 1- 8 Preparation for Testing and Functional Test Forms ................ 1- 4 Performance Acceptance Test Sheet ........................................ 1- 2
DIVISIONS 41 AND 42—NOT USED
DIVISION 43—PROCESS GAS AND LIQUID HANDLING, PURIFICATION,
AND STORAGE EQUIPMENT
43 22 56.01 Submersible Mixers ................................................................. 1- 4
DIVISION 44—POLLUTION AND WASTE CONTROL EQUIPMENT
44 42 56.04 Submersible Pump ................................................................... 1- 5 Supplement:
Screen Washwater Pump Data Sheet ....................................... 1- 2 44 42 56.10 Horizontal End Suction Centrifugal Pumps ............................. 1- 5 Supplements:
Filter Feed Pump 1 and 2 Data Sheet....................................... 1- 2 Filter Effluent Pump Data Sheet .............................................. 1- 2 Final Effluent Pump Data Sheet .............................................. 1- 2
GRCA - 229035 00 01 10 - 5
44 42 56.16 Peristaltic Hose Pump .............................................................. 1- 5 Supplement:
Peristaltic Hose Pump Data Sheet ............................................ 1- 3 44 43 15 Automatic Backwash Filter Equipment ................................... 1- 6 44 44 57 Tube Settler System ................................................................. 1- 8 44 45 16.01 Coarse Bubble Air Diffuser System ........................................ 1- 10 44 53 16 Screw Screen ............................................................................ 1- 9
DIVISION 45—NOT USED
DIVISION 46—WATER AND WASTEWATER EQUIPMENT
46 53 36 Integrated Fixed-Film Activated Sludge Equipment ............... 1- 7
DIVISIONS 47 THROUGH 49—NOT USED
VOLUME 2
DRAWINGS
END OF SECTION
GRCA - 229035 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location:
1. Grand Canyon National Park
Phantom Ranch Wastewater Treatment Plant Grand Canyon, Arizona
2. The Phantom Ranch Wastewater Treatment Plant is located at the base of the Grand Canyon, near the confluence of Bright Angel Creek with the Colorado River. The plant serves Phantom Ranch, which provides campgrounds, dormitories and cabins for hikers and mule riders. The hike to Phantom Ranch is approximately 7.5 miles down the South Kaibab Trail or 10 miles on the Bright Angel Trail.
B. The Work consists of the following:
1. The Work includes interim improvements to the Phantom Ranch Wastewater Treatment Plant, which supports all visitor and support services for Phantom Ranch and Bright Angel Campground. The plant is rated for a maximum month wastewater flow of 7,000 gallons per day and a maximum day of 12,000 gallons per day. The completed Work will provide improvements for enhanced performance and include the following:
a. New influent screen. Construction of a new influent screen with integral washer and compacter and headworks structure. Backwash pump will convey water from the Effluent Storage (Chlorine Contact) Tank.
b. Equalization tank mixer replacement. Construction of a new submersible mixer in the existing equalization tank.
c. Aeration tank retrofit with integrated fixed film activated sludge (IFAS) technology.
Retrofit of the existing aeration tank with an IFAS technology for carbon, nitrogen and solids removal.
d. Blower modifications. Construction of new adjustable frequency drives for the three existing blowers and ancillary piping and valves.
GRCA - 229035 01 11 00 - 2
e. Final clarifier tube settler replacement. Retrofit of the existing final clarifier with new tuber settlers for enhanced settling performance.
f. Tertiary filter replacement. Construction of a new tertiary filter with chemical addition and automatic backwashing to replace the existing, retired filter.
g. Digester modifications. Construction of coarse bubble diffusers to provide mixing and process air for digestion.
h. Instrumentation and control and main control panel upgrades.
i. Electrical upgrades.
j. Demolition.
k. Temporary facilities and controls.
C. Continuous operation of the Phantom Ranch Wastewater Treatment Plant is of critical importance.
Schedule and conduct activities to enable existing facilities to operate continuously, unless otherwise specified. Contractor shall perform work as required to maintain compliance with the facility Aquifer Protection Permit and facility operating requirements.
D. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Phantom Ranch Wastewater Treatment Plant Effluent Disposal Improvements: A separate contract will be awarded for construction of a new percolation basin to discharge treated effluent from the WWTP.
2. Grand Canyon National Park SCADA System Upgrade: A separate contract will be awarded for the configuration and programming of a new SCADA system at the Grand Canyon National Park sites. This contractor will be responsible for programming, field testing and commissioning services for the SCADA system for the Phantom Ranch Wastewater Treatment Plant Short Term Improvements.
C. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Final Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.
1. Phantom Ranch Water and Wastewater Treatment Plants: Separate contracts will be awarded for construction of a new Water Treatment Plant and a new Wastewater Treatment Plant on the Delta, adjacent to the existing Phantom Ranch Wastewater Treatment Plant.
GRCA - 229035 01 11 00 - 3
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the WWTP building and as noted on the drawings.
2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
B. Storage of Materials: Confine storage of materials to areas located on the Drawings.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. Trenching and construction equipment transported to the site from outside of the Park shall be pressure washed to minimize the potential to import invasive plant seeds and material to the site.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: The Contractor will be allowed to use one of the two bedrooms in the Phantom Ranch Trail Crew Bunk House during construction. The bedroom has three bunk beds that will accommodate up to 6 Contractor crew members. The bunk house has a full kitchen that will be shared with personnel who may be using the other half of the sleeping quarters. If the Contractor requires housing for more than 6 personnel at a time, Contractor can provide tent camping facilities in the volleyball court area adjacent to the bunk house. The Contractor shall provide a site plan and proposed tent enclosures for approval by the Contracting Officer prior to the beginning of construction. All personnel will be allowed to use the kitchen and bath facilities of the bunk house.
GRCA - 229035 01 11 00 - 4
Contractor will only use the designated campsite area for overflow crew members that cannot be accommodated in the bunk house.
1. Clean and organize lodging facilities daily to mitigate exposure to rodents. Place trash into an NPS approved, Contractor-provided trash receptacle daily. The Contractor will use a helicopter to backhaul trash from the project site. The Contractor will not use any Park-provided dumpster or trash cans for personal trash or other project trash. Any food or trash stored outdoors must be kept in a hard-sided, rodent-proof container at all times.
2. Return the lodging and camping area facilities to pre-project condition at the completion of work. Any damage to lodging and camping area facilities will be repaired or replaced a no additional cost to the NPS, including, but not limited to: structures, deck, finishes, furniture, fixtures, and appliances.
3. The use of TV in the canyon is not allowed unless otherwise approved by the Contracting Officer.
4. No telephone is available for Contractor use. See Section 01 73 40, Execution for requirements on phone installation, should Contractor require phone service.
5. Contractor to arrange a pre-move in and post-move out inspection of the bunkhouse with the Contracting Officer.
6. Contractor will be allowed the use of one of the two refrigerators in the kitchen area and approximately one-half of the freezer space designated for bunk house occupants.
7. Comply with the NPS Code of Conduct for Bunkhouses and Bunkhouse_Checklist_contractor. Copies of these documents are provided as supplements to this Section, 01 11 00, Summary of Work.
8. Comply with NPS Backcountry Rules and Regulations for Grand Canyon National Park, which can be found at Backcountry Rules and Regulations - Grand Canyon National Park (U.S. National Park Service) (nps.gov). A backcountry permit will not be required for personnel using the bunkhouse and campsite area in accordance with this specification.
9. Contractor will provide advance notification to the Contracting Officer of planned occupancy levels for the bunkhouse and campsite area. Provide notification at least one week in advance for each week while using the bunkhouse and campsite area.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Building closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum of 8 hours.
1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Full Government Occupancy: Government will occupy buildings that will be under construction during the entire contract period. Cooperate with Government during
GRCA - 229035 01 11 00 - 5
construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
1.7 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during working hours of 6:00 a.m. to 6:00 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: 8:00 am to 5:00 pm.
2. Early Morning or Night Hours: Upon approval only.
3. Hours for outdoor activities: 8:00 am to 5:00 pm.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than ten days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
GRCA - 229035 01 11 00 - 6
3. Hours for Utility Shutdowns: Between 12 am and 4 am for 4 hours.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
1.10 SOILS INVESTIGATION REPORT
A. A soils investigation was not conducted for this project.
B. It is the responsibility of the Contractor to assess the conditions during the mandatory site visit.
1.11 SUPPLEMENTS
A. The supplements listed below, following "End of Section 01 11 00" are a part of this specification:
1. Inner Canyon Bunkhouse Code of Conduct.
2. Inner Canyon Bunkhouse Checklist.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
GRCA - 229035 01 11 00 SUPPLEMENT - 1
Grand Canyon National Park Inner Canyon Bunkhouse Code of Conduct
Work The primary purpose for Inner Canyon bunkhouse use is to facilitate the completion of NPS work projects. These are NOT party trips and events. We expect all workers and participants to be fully engaged and actively participate in all required duties for the duration of each trip. This includes shared activities: loading and unloading, cooking, doing dishes, keeping facilities clean, and completing final facility cleaning prior to departure.
Cooperation Bunkhouse users often consist of employees from different divisions, NPS contractors, and volunteers.
Rangers are expected to walk through the bunkhouse to check fire and safety equipment, look for emergent issues (broken pipes, running water, fire hazards, etc.) and check security. Establishing good working relationships is essential in shared quarters and requires full cooperation from everyone. Do your part to keep the bunkhouse clean. People may be working difference work schedules, so maintaining quiet hours and respect for the sleep of others is mandatory!
Quiet Hours There are park visitors camping nearby and other residents in close proximity. At these locations, voices and noise carries and echoes, and we do not want to impact the experience of others. Many campers are exhausted and go to sleep at dark. Quiet hours must be observed at these facilities from 8pm to 6am.
However, noise can be unreasonable at any time of day, when other people are disturbed through inconsiderate or reckless behavior. If there is any non-adherence to these rules, you may be contacted by a Law Enforcement Ranger.
Especially at Indian Garden, sound travels directly from the bunkhouse to the campground. At night, conversation and laughter outside the bunkhouse (or inside, with the windows open) is disruptive to campers trying to sleep. If you want to socialize after dark, do so inside the IG bunkhouse with the windows closed, or hike out toward Plateau Point.
Professionalism, Rules, Alcohol and Drug Policy NPS rules and regulations will be adhered to at all times. The use of alcohol in the Inner Canyon Bunkhouses, campgrounds and overflow areas is prohibited during or after work hours. Likewise, transport of alcohol by NPS on-duty staff or livestock is prohibited. Illegal drugs are against the law and will not be tolerated. Federal drug laws apply. We expect everyone to be professionals at all times.
Noncompliance with rules or regulations may result in the offender being expelled from temporary backcountry quarters and/or revocation of privileges to use bunkhouses by the offending program/division.
Dark Skies Grand Canyon National Park is conserving our Dark Skies. Please do your part by closing the blinds on all bunkhouse windows after dark.
Rodents All of the Inner Canyon Bunkhouses are prone to mouse infestations. Please keep the door closed except when walking in or out of the bunkhouse. Maintain good housekeeping measures…sweep floors and wipe counters after each and every meal preparation. Store food properly (rodent proof containers) when not in use (no leftover sandwiches and trail mix in your backpack on the floor overnight, etc.) If you see
GRCA - 229035 01 11 00 SUPPLEMENT - 2
mice (or mouse sign) in the bunkhouse, please follow the Integrated Pest Management notification procedure.
Positive Attitude Maintain a positive attitude, be flexible, patient, and open to learning from others. The way you interact with others and with the group as a whole has an impact on the work and the reputation of your particular crew, so please be positive and professional.
Inner Canyon Bunkhouse
During your project work, you have been allowed to stay at one of the NPS bunkhouses. Please make sure you meet with your NPS project manager prior to heading into the canyon to ensure you have a key for the facility.
The bunkhouses are shared quarters and there may be other users while you are there.
Each bunkhouse has bunkbeds, full kitchen, sitting area, bathrooms with showers, and access to laundry facilities. There are some linens, blankets, and towels. Many guests opt to bring their own.
There may be other concerns that may influence your stay including requirements during public health emergencies or infrastructure concerns.
As of April 2021, the park is still taking COVID-19 precautions. Masks are required when inside buildings and in outdoor areas where distancing is not possible. Up to date information can be found at https://www.nps.gov/grca/planyourvisit/conditions.htm. Please coordinate use of the kitchen and bathrooms with other users. Remember to wash your hands and wipe down surfaces.
The Phantom Waste Water Treatment plant has been overtaxed by the amount of waste.
Please be very conscientious with any waste water going down the drain. The NPS has significantly reduced the use of the backcountry campground and the Phantom Ranch guests to reduce the load. Please take short showers and limit the amount of laundry.
Please help us take care of the park and these facilities.
Cleaning Checklist It is the responsibility of everyone who occupies a bunkhouse to ensure that it is kept clean.
Prior to vacating, the facility must be cleaned to the standards supplied below.
If supplies or repairs are needed please notify your NPS project manager. They will submit the appropriate requests.
Should be stocked at all times: Toilet Paper, Dish Soap, Laundry Soap, Simple Green, Mops, Brooms, Vacuum, Linens, Pillows, Blankets, Cookware, Flatware, Dishes and Mouse traps.
GRCA - 229035 01 11 00 SUPPLEMENT - 1
SUMMARY OF WORK
https://www.nps.gov/grca/planyourvisit/conditions.htm
Etiquette
- Share facilities with patience and professionalism
- Observe quiet hours (10pm-6am) and be mindful of other employee’s work hours
- Smoking and alcohol are not allowed within the bunkhouses, including porches
- Answer the phone professionally and pass on messages
Kitchens
❏ Remove all food items from the refrigerator/freezer
❏ If you are a long-term user please label your food with your name and the date. Only use one refrigerator if your crew is leaving for a weekend.
❏ Please dispose of all consumable food items once your work project is over.
❏ Wipe up any spills and crumbs on shelves in refrigerator/freezer
❏ Wash all dirty dishes and dry and put away
❏ Wipe down counters and any surfaces that may have grease or food splatter
❏ Scrub sink
❏ Sweep and mop floor
❏ Wash any dish towels or pot holders that you’ve used
❏ Double check that the stove range and oven are off
Bathrooms
❏ Scrub down shower/bathtub. Ensure all hair/debris is removed from the tub and hair traps
❏ Clean toilet
❏ Sweep and mop floor
❏ Check toilet paper stock and put in a work order if it is low
Laundry Facilities
❏ Ensure that the dryer is not left on while you are away or after your departure
❏ Do empty the lint trap and leave the wash machine door open/ajar to prevent mold
Bedrooms and Common Areas
GRCA - 229035 01 11 00 SUPPLEMENT - 2
❏ Remove all bedding from the beds
❏ Wash, dry, fold, and put away all bedding and towels (Do not leave dryer running after departure)
❏ Dust furniture surfaces
❏ Sweep and mop floors
❏ Draw shades in all rooms and turn off exterior lights
❏ Take out all trash and recycling
❏ Do not leave mouse-traps baited and set upon departure
❏ Make sure that all doors and windows are closed and secure
Trash and Recycling
You are responsible for flying your trash out with your gear.
GRCA - 229035 01 11 00 SUPPLEMENT - 3
GRCA - 229035 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
GRCA - 229035 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Trash removal, dumpsters
5. Barricades
6. Small tools
7. Safety supplies
8. Scaffolding
9. Daily cleaning
10. Traffic control
11. Temporary signage
12. Temporary power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
GRCA - 229035 01 26 01 - 3
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
GRCA - 229035 01 26 01 - 4
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
GRCA - 229035 01 26 01 - 5
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit……………………10%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
GRCA - 229035 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 26 01
GRCA - 229035 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 0001 Phantom Ranch WWTP Short Term Improvements.
1. This item consists of all components necessary to demolish, prepare, install, operate and maintain the new equipment at the WWTP, including a new influent screen, equalization tank mixer, integrated fixed film activated sludge (IFAS) system, blower modifications, final clarifier tube settlers, automatic backwash filter, digester coarse bubble diffusers, main control panel upgrades, ancillary equipment, instrumentation and electrical gear. The work includes civil, structural, mechanical, instrumentation and control and electrical elements.
2. Measurement for payment will be in accordance for the Schedule of Values.
3. Payment will be made at the contract lump sum price in accordance with the percentage of work completed.
3.2 SUPPLEMENT
A. The supplement listed below, following “End of Section,” is part of this specification.
1. Contract Price Schedule Template.
END OF SECTION 01 27 00
Contract Price Schedule Template National Park Service (NPS) - Denver Service Center (DSC) | 3-13-18
Solicitation Number:
PARK - PMIS: GRCA - 229035
(Project Management Information System)
Developed Area:
Project Title: Phantom Ranch Wastewater Treatment Plant Short Term Improvements
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line Item Number
(CLIN)
Contract Line Item (CLI) Title…