This is a Data Item Description (DID) document that establishes the format and content requirements for a Production Surge Plan deliverable in federal contracts.

The Production Surge Plan (Identification Number DI-MGMT-80969) delineates a contractor's capability to rapidly accelerate and sustain production utilizing existing facilities and equipment in a peacetime acquisition environment without declaring war or mobilization. The plan applies to contracts where production surge capability for select critical items is required. The document is approved for public release with unlimited distribution and is maintained by the Office of Primary Responsibility (OPR) as A/AMOCOM/FD, with AMSC Number A4923.

The Production Surge Plan must include: (1) maximum sustainable production rate with a buildup schedule by month until achievement, including subcontractor and vendor capability assessment and verification of vertical planning; (2) two lists identifying subcontracted and non-subcontracted items/components by nomenclature, part number, leadtime, and production volume of long-leadtime, critical, or pacing items that could adversely impact production; (3) a list of Government contracts at the contractor's facility with production surge provisions, identifying contract numbers, item(s), and Defense Materials System and Defense Priorities System priorities; (4) impact analysis on other Government contracts; (5) all additional skilled labor requirements necessary to support maximum sustainable production; (6) strategic or critical materials and precious metals required with quantities, costs, and rolling inventory needs within six months, plus substitute materials; and (7) production equipment, tooling, and costs needed to increase surge capacity by at least 10 percent or reduce leadtime, with estimated impacts on surge production rate and leadtime.

View the file

Other versions and copies of DI-MGMT-80969

File Revision Posted Attached to
A004_DI-MGMT-80969.pdf Same revision and size as this file Revision not stated SOLICITATION FA811826R0055- Repair of the F-16 Oxygen Monitor NSN 1660-01-473-3548
DI-MGMT-80969 Production Surge Plan.pdf Same revision and size as this file Revision not stated Remanufacture of B-2 Actuator, Electromechanical, Rotary
Production Surge Plan (DI-MGMT-80969).pdf Revision not stated F108 Compressor Inlet Temperature (CIT) Sensor
DI-MGMT-80969 Production Surge Plan.pdf Same revision and size as this file Revision not stated Tear Down, Test & Evaluation/Repair of B-2 Fuel Level Control Valve Bodies
DID_DI-MGMT-80969.pdf Revision not stated REMANUFACTURE OF B-1 YAW TRIM ACTUATOR
A006_DI-MGMT-80969.pdf Same revision and size as this file Revision not stated Solicitaton-FA8118-26-R-0047 REMAN F-15 Fuel Tank Safety Relief Valve
A004_DI-MGMT-80969.pdf Same revision and size as this file Revision not stated FA8118-26-R-0038- Remanufacture and Upgrade of B-52 Wing Flap PDU
DI-MGMT-80969 Production Surge Plan.pdf Revision not stated Overhaul of E-3 Electro-Mechanical Actuator
DI-MGMT-80969.pdf Same revision and size as this file Revision not stated Repair of B-2 Submerged Pump, Fuel Pumping Element & Fuel Pump Unit
DI-MGMT-80969.pdf Same revision and size as this file Revision not stated Amendment-01 FD20302600598_FA811826R0033- Overhaul of B1 Torque tube assembly
DI-MGMT-80969 Production Surge Plan.pdf Same revision and size as this file Revision not stated Remanufacture of B-1 Interlock Assembly, Wing Sweep
DID_DI-MGMT-80969.pdf Revision not stated Overhaul of F-16 Check Valve
DID_DI-MGMT-80969.pdf Revision not stated Overhaul of F-16 Check Valve
DI-MGMT-80969 Production Surge Plan.pdf Same revision and size as this file Revision not stated Remanufacturing of the F-16 Air Heat Exchanger
DI-MGMT-80969 Production Surge Plan.pdf Same revision and size as this file Revision not stated Remanufacture of F-15 Rudder and Nose Gear Steering Cartridge Assembly
Production Surge Plan DI-MGMT-80969.pdf Revision not stated Overhaul of KC-135 and E-3 Horizontal Stabilizer Trim Actuator, NSN 1680-01-497-3293RK, 1680-01-005-8163RK
DiD-DI-MGMT-80969-SURGE.pdf Revision not stated Repair of B-2 Transponder Set (KU Band)
DI_MGMT_80969_Surge.pdf Same revision and size as this file Revision not stated T-38 Electro-Mechanical Actuator, Multiple NSNs, Multiple Award Contract (MAC)
DI-MGMT-80969.pdf Same revision and size as this file Revision not stated Remanufacture of C-5 Dual Boost Fuel Pump; NSN: 2915-00-489-9215RK
DI-MGMT-80969.pdf Same revision and size as this file Revision not stated Solicitation for FD20302501098: Overhaul of Control Column, Airc_NSN: 1680-01-527-8154FG & 1680-01-527-8153FG
Show all 20

Who attaches DI-MGMT-80969

Other files

File Type Posted
A003_DI-MGMT-80441D.pdf PDF
A004_DI-SESS-80776B.pdf PDF
A005_DI-MGMT-80503.pdf PDF
TRNSPDATA_REPORT.pdf PDF
FA811826R0043_Reman C130 Fuel boost pump.pdf PDF
A002_DI-PSSS-81995A.pdf PDF
CDRL1_REPORT.pdf PDF
GFP_Listing.pdf PDF
PKGRQMT_REPORT.pdf PDF
Statement_of_Work.pdf PDF
A001_DI-MGMT-81838.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .