9-25-728 Article 10 Budget.pdf
PDF 166 KB Posted
- Solicitation number
- 2025-728
- Issued by
- King County, Washington
About this file
This is an Article 10 Budget document from the State of Washington Department of Enterprise Services (DES) outlining budgeting and financial management requirements for a General Contractor/Construction Manager (GC/CM) engaged on the Bellevue College Parking Garage Update project. The document establishes comprehensive financial protocols for preconstruction and construction phases, requiring the GC/CM to produce estimates of probable cost at each design phase beginning with the Design Development phase and to provide input on cost efficiencies. The Maximum Allowable Construction Cost (MACC) is negotiated at the 90% construction document completion stage and becomes finalized at Notice to Proceed (NTP) for construction. The GC/CM must invoice monthly using the state A-19 invoice form and submit detailed budget control sheets and monthly cost reports to the DES Project Manager, with all invoices requiring signed architect recommendations before forwarding to the Owner for payment.
The budget control and reporting requirements mandate that the GC/CM track and report monthly on multiple financial categories including the Original MACC, General Conditions charges, negotiated Support Services, buy-out savings, GC/CM fees, current budget status, obligations, expenditures, and remaining balances. Payment is structured into major categories covering GC/CM fees (proportionate to work completed), Negotiated Support Services Work, and Cost of Work based on actual progress documented through subcontractor contracts and schedules of values. The project incorporates state policy requirements including a voluntary 26% Diverse Business participation goal (10% MBE, 6% WBE, 5% Veteran-owned, 5% Washington Small Businesses), with mandatory tracking through the DES Public Works Diversity Tracking & Management System powered by B2GNow. Additionally, for projects estimated at one million dollars or more, a minimum of 15% of labor hours must be performed by apprentices in accordance with RCW 39.04.320, with monthly reporting required to compare actual apprenticeship utilization against the filed Apprenticeship Utilization Plan.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Article 10: Budget 4-22
ARTICLE 10: BUDGET
10.1 Preconstruction
The GC/CM shall review design drawings as previously described and produce an estimate of probable cost at each design phase, starting with the Design Development phase. The GC/CM shall participate and provide input and advice where cost efficiencies can be realized to maintain budget within the desired scope. The estimate at 90% complete construction document will be the basis of establishing a negotiated MACC that is fair, reasonable, and within the available funds.
The GC/CM shall invoice monthly for pre-construction services and for construction in an amount proportionate to the total work completed. All invoices shall be on the state A-19 invoice form which can be found at:
https://des.wa.gov/services/public-works/formsreference-documents
10.2 Construction
Budget Control
The MACC is finalized at Notice to Proceed (NTP) for construction after negotiating the MACC. Once established, the MACC does not change unless an Owner requested change order (CO) is approved.
The GC/CM shall update the current budget on an on-going basis and deliver a formal update monthly to the DES Project Manager. Obligations represent fiscal commitments known to the PM. The current budget reflects modifications to the MACC on an item-for-item basis. Change order summaries shall tie to budget control sheets for each project.
A master budget sheet for each bid package shall identify the status of categories for each line-item entry. The GC/CM shall list, vertically on the sheet, a breakdown of the information by bid package and by identifiable pieces of the project. The breakdown shall include:
Original MACC Specified General Conditions charges Negotiated Support Services Buy-out savings GC/CM Fee Allowances Current budget Obligations Expenditures (paid to date) Remaining balances
GC/CM Cost Accounting
To ensure efficiency and accountability, a regular reporting and back-up system has been created. Through monthly submittals of budget control sheets by the GC/CM, the State Contracting Officer can provide checks and balances of the work.
The GC/CM is required to provide a cost accounting of the MACC on a monthly basis in a format acceptable to Department of Enterprise Services protocol. As a minimum each major element of work shall be tracked (i.e.: seismic repairs; site work, etc.).
https://des.wa.gov/services/public-works/formsreference-documents
Reviewing the GC/CM's monthly cost report and outstanding TCMs will enable the PM to assess actual and potential savings within the MACC.
The GC/CM will provide with the monthly invoice, a monthly report to the Project Manager for review of expenditures, tracking of subcontractors, and contract changes. The report shall, at a minimum, track the following using a spreadsheet format:
Budget - This column shall reflect the amounts agreed to between the PM and the GC/CM. It shall reflect the amount shown on the contract for the MACC.
Bid Packages - This column shall show the amounts encumbered less change orders or team change memos for each bid package.
Contract Change Log:
• Change Order Proposals: Change log shall track all potential COP, pending COP, and executed COP to date. Each entry shall show either an estimated or actual value for each COP entry.
• Field Authorizations: Change log shall track all potential FA’s, pending FA’s, executed FA’s to date. Each entry shall show either an estimated or actual value for each COP entry.
• Team Change Memos – Change log shall track approved and pending team change memo amounts. The log shall show beginning balance for risk contingency and buyout savings as well as the balance in each category after the TCM is approved.
• Change Orders - This column shall reflect the amounts of addition or deletion from the contract amount.
Variance - This column shall show the budget less the sub-contract, change orders, and team change memos
Expended to Date - This column shall show the amounts paid the GC/CM
Paid To Date - This column shall show that amount recorded on the last monthly report shown as "Paid To Date"
Earned To Date - This column shall show the amount "Earned To Date"
Percent of Budget – This column shall show that amount of the negotiated budget expended
Anticipated Additional Needed To Completion - This column shall show that amount the GC/CM feels may be needed to complete the project. The amount should typically account for anticipated team change memos.
Payment Summary
Monthly invoices shall be broken into the following major categories.
Payment of the GC/CM Fee: The GC/CM's fee shall be paid in an amount proportionate to the total work completed.
Negotiated Support Services Work: The PM shall verify that all such billings are appropriate, including work that falls under the category of Specified General Conditions work.
Payment of the Cost of the Work: Payments are made based on actual work in progress. In order to assess the actual work completed, the PM will require copies of all contracts between the sub-contractors. Each bid package shall have a schedule of values as described in the General Conditions for Construction, Section 6.02. The information regarding subcontractor payment shall be in a location accessible to the state, on request, for periodic audit. The GC/CM shall invoice on actual work progress.
Bid package costs shall reflect actual bid schedule of values plus any PM approved change orders or team change memos, based on actual work in place and accepted, or on materials stored on site or in a PM approved facility.
Allowances: The GC/CM may carry allowances for items approved by the PM at the time the MACC is negotiated. The PM shall verify that payments within these categories shall not exceed the agreed upon allowance limit without a PM approved change order. These allowances will be identified in the project budget and are subject to audit at the completion of the project.
All payment requests must have the signed and dated recommendation of the Architect.
The PM determines the appropriateness of the billing and forwards invoice to the Owner for payment.
10.3 Diverse Businesses Reporting
The State of Washington encourages participation in all of its contracts by Diverse Businesses as found in RCW Chapters 39, 43, and WAC 326.
The voluntary Diverse Business goal of 26%, which is an aggregate of:
10% Minority Business Enterprises (MBE) 6% Women Business Enterprises (WBE) 5% Veteran-owned Business 5% Washington Small Businesses self-identified in the Washington Electronic
Business Solution (WEBS) DES reserves the right to adjust these voluntary participation goals.
GC/CM and all subcontractors are encouraged to meet or exceed the project goals in the advertisement by any level of participation, regardless of category. Businesses are encouraged to register in WEBS, as well as registering as a state certified M/WBE/Veteran Business. Please reference Attachment 6 for required Diverse Business inclusion Plan.
For reporting and recording progress in meeting these goals, GC/CM is required to register and create an account in the DES Public Works Diversity Tracking & Management System powered by B2GNow. Every month for the duration of your contract, and while your contract is active in the DES Public Works Diversity Tracking & Management System, submit and accurately maintain the following information:
1. Payments received by the prime contractor from the Agency
2. Payments paid to each first tier subcontractor
3. Payments paid to each first tier supplier
You must also ensure the following information is reported in the DES Public Works Diversity Tracking & Management System by your first tier subcontractors and suppliers for the duration of your contract:
1. Confirmation of payments from the prime contractor to the first tier subcontractor
2. Confirmation of payments from the prime contractor to first tier suppliers
10.4 Apprentice Utilization
In accordance with RCW 39.04.320, for all public works estimated to cost one million dollars or more, the State of Washington requires no less than 15% of the labor hours be performed by apprentices. The GC/CM or any subcontractor may not be required to exceed the 15% requirement. On applicable bid packages, the GC/CM’s bid advertisement and Bid Form for subcontractor bid packages shall establish a minimum required percentage of apprentice labor hours compared to the total labor hours. The GC/CM shall report Apprenticeship Utilization compared to the GC/CM Apprenticeship Utilization Plan on file with each monthly invoice. Please reference Article 7 for additional apprenticeship requirements.
https://apps.leg.wa.gov/RCW/default.aspx?cite=39.04.320