This document is Article 12 of the Schedule Management requirements for the GC/CM Bellevue College Parking Garage Update project in Washington. The General Contractor/Construction Manager is responsible for developing and managing comprehensive schedules that accommodate the Owner's operational requirements while maintaining facility operations. A Critical Path Method (CPM) schedule must be prepared to coordinate all work activities in accordance with the project's General Conditions, with updates submitted at minimum on a monthly basis.

The GC/CM must submit a four-week look-ahead schedule at each weekly construction meeting, detailing the previous week's planned versus actual work performed and forecasting activities for the subsequent three weeks. The schedule must identify critical path tasks and note any activities that may disrupt facility operations, including scheduled outages. This rolling forecast approach enables proactive management of construction sequencing while maintaining transparency regarding project progress and potential operational impacts.

View the file

Other files

File Type Posted
30-25-728 Attachment 17 FinalAcceptanceChecklistForm.pdf PDF
24-25-728 Attachment 11 RetainageBondForm.pdf PDF
19-25-728 Attachment 05 CostResponsibilityMatrix.pdf PDF
25-25-728 Attachment 12 ChangeOrderProposalForm.pdf PDF
20-25-728 Attachment 07 ApprenticeUtilizationPlanForm.pdf PDF
27-25-728 Attachment 14 TeamChangeMemo.pdf PDF
1-25-728 Article 00 InstructionsToProposers.pdf PDF
13-25-728 Article 14 Definitions.pdf PDF
17-25-728 Attachment 03 FinalProposalForm.pdf PDF
7-25-728 Article 08 QualityControlAssurance.pdf PDF
3-25-728 Article 03 ModificationsToWashingtonStateGeneralConditions.pdf PDF
6-25-728 Article 07 ApprenticeshipRequirements.pdf PDF
12-25-728 Article 13 SubstantialCompletion-ProjectCloseout.pdf PDF
28-25-728 Attachment 15 WageTheftForm.pdf PDF
23-25-728 Attachment 10 RCWsRelevantToGCCM.pdf PDF
26-25-728 Attachment 13 FieldAuthorizationForm.pdf PDF
22-25-728 Attachment 09 Ph2ProtestProcedures.pdf PDF
5-25-728 Article 06 ElementsOfTotalContractCost.pdf PDF
10-25-728 Article 11 ContractChanges.pdf PDF
4-25-728 Article 05 PreconstructionServices.pdf PDF
14-25-728 Attachment 00 ProposerContactForm.pdf PDF
8-25-728 Article 09 CoordinationAndMeetings.pdf PDF
21-25-728 Attachment 08 Ph1ProtestProcedures.pdf PDF
9-25-728 Article 10 Budget.pdf PDF
16-25-728 Attachment 02 RequestForFinalProposal.pdf PDF
15-25-728 Attachment 01 AdvertisementForGCCM.pdf PDF
18-25-728 Attachment 04 PerformanceEvaluationQuestionnaire(GCCM).pdf PDF
2-25-728 Article 01 GeneralConditions.pdf PDF
29-25-728 Attachment 16 CertificateOfSubstantialCompletion.pdf PDF
31-25-728 RFQ-RFP.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Article 12: Schedule Management 4-22

ARTICLE 12: SCHEDULE MANAGEMENT

12.1 Long-Range Project Management Schedule

The GC/CM shall be responsible to develop and manage schedules that reflect the requirements of the project. The schedule shall reflect the Owners need for maintaining operation.

A Critical Path Method (CPM) schedule shall be prepared by the GC/CM to coordinate the work in accordance with Part 3, Section 3.02 B. of the General Conditions. This schedule shall be updated as needed but not less than once a month.

12.2 Short Term Look-Ahead Schedules

A four week look-ahead schedule shall be submitted at each weekly meeting during construction. The schedule shall show the prior week planned vs. actual work performed and forecasted activities for the next three weeks. Activities such as scheduled outages or any activity that may disrupt facility operations shall be noted. Critical path tasks shall be identified.