3-25-728 Article 03 ModificationsToWashingtonStateGeneralConditions.pdf
PDF 214 KB Posted
- Solicitation number
- 2025-728
- Issued by
- King County, Washington
About this file
This document is Article 03 of the General Conditions modifications for Washington State Facilities Construction applicable to the GC/CM (General Contractor/Construction Manager) contract for the Bellevue College Parking Garage Update project. The modifications establish the operational framework for the GC/CM delivery method, defining the roles and responsibilities of the General Contractor/Construction Manager, the Architect/Engineer, and the Owner/Department of Enterprise Services (DES). The GC/CM shall manage trade contractor bidding, maintain cooperative relationships with the design team, and provide monthly cost-accounting reports throughout the project duration. Trade contractors must be competitively bid through public bid openings, with the GC/CM prohibited from bidding on subcontract work except under specific conditions outlined in RCW 39.10.380, and the GC/CM's self-performed work cannot exceed thirty percent of the negotiated maximum allowable construction cost.
The contract establishes a Maximum Allowable Construction Cost (MACC) structure with a Risk Contingency not to exceed five percent, with buyout savings accruing to the Owner upon project completion. The GC/CM must provide a 100% payment and performance bond using AIA A312 forms and maintain General Liability and Builder's All Risk insurance for the duration of construction. Trade contractors bidding work exceeding $300,000 must post bid bonds and performance bonds; those under $300,000 must provide performance and payment bonds if required by the GC/CM. The GC/CM receives no markup on trade contractor work except for bonds, insurance, and the firm's fee, and the Owner may compensate the GC/CM for increased bond and insurance costs on an actual cost basis if the Total Contract Cost increases through change orders or MACC negotiations. All project savings accrue to the Owner, and the GC/CM must maintain detailed accounting records satisfactory to the Owner.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Article 03: Modifications to the General Conditions for WA State Facilities Construction for GC/CM 4-22
ARTICLE 03: MODIFICATIONS TO THE GENERAL CONDITIONS FOR
WASHINGTON STATE FACILITIES CONSTRUCTION
The Instructions to Bidders and General Conditions for Washington State Facilities Construction apply to the GC/CM Contract as modified by the GC/CM Manual:
3.1 Part 1, 1.01 Definitions
“Contract Documents” shall include, in addition to the documents mentioned, The GCCM’s response to the RFQ/RFP and the GC/CM manual for this project. The Manual consists of the RFQ/RFP and all its Articles and Attachments.
Where “contractor” or “contractor’s” is used, substitute “GC/CM” or “GC/CM’s”. Wherever “sub-contractor” is used, substitute “trade contractor” or “trade partner”. Wherever “Owner” is used, substitute Owner/DES.
3.2 Part 1, 1.03 Execution and Intent: add paragraphs below
5. The Owner has a separate agreement with the Architect/Engineer (A/E) to design the facility and to provide the limited construction observation services necessary to ensure that the construction conforms to the drawings and specifications but does not absolve the GC/CM of its role as Construction Manager or General Contractor to assure performance.
Both the GC/CM and the A/E shall be given direction by the owner, normally by the DES project manager or designated representative. The relationship between the GC/CM and the A/E is intended to be cooperative and proactive, both participating on the same team with the Owner. Meeting minutes during construction will be taken by the GC/CM and distributed to all parties within five calendar days. The A/E will provide attachments addressing design issues when appropriate.
3.3 GC/CM Provisions
A. If the A/E's estimate and the GC/CM's estimate on a bid package are not in agreement, then the A/E, the GC/CM, and the owner shall make whatever efforts necessary to come to agreement and make any necessary changes prior to advertising the bid package.
This should take place within seven calendar days of receipt of the estimate. Efforts shall include but not be limited to program revisions, architectural/ engineering revisions, and construction adjustments, etc.
B. Bidding on subcontract work by the GC/CM or its subsidiaries is prohibited, except as provided for under RCW 39.10.380. In the event that no bids are received, or the bids received are over the budgeted amount for the trade contract specialty or the trade contractor fails to perform, then, with the prior approval of the owner, the GC/CM may:
• Negotiate with the low responsive responsible bidder in accordance with RCW
39.10.380 or
• Provide written explanation to reject all bids and rebid the bid package.
In preparing trade contract bid packages, the GC/CM must not require the trade contractor to violate or waive terms of a collective bargaining agreement.
C. The GC/CM shall use the Instructions to Bidders and General Conditions for Washington
State Facilities Construction in all trade contracts. GC/CM trade contract form and other conditions specific to the project are allowed to the extent that the GC/CM's documents do not conflict with the State documents. The documents shall be provided to the Owner https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10.380 https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10.380 for review and approval at least 60 days prior to bidding.
D. For GC/CM bid packages, Instructions to Bidders, Section 0.09 Subcontractor Listings, and R CW 39.30.060 does not apply.
E. The MACC should include sufficient allowance and contingencies to accomplish the work. The Risk Contingency amount will be agreed upon at the time the MACC is negotiated and will not exceed 5%.
F. Potential buy-out savings, within this article, shall be defined as the difference between the bid package MACC and the bid amount plus Team Change Memos (TCMs). There is no potential buy-out savings if the total amounts awarded plus TCMs exceeds the total of the bid package estimates which are identified within the negotiated MACC.
1. During the period of time between the bidding of the first bid package and until 80% of all work has been awarded, the full amount of the negotiated MACC is available to the GC/CM for awarding bid packages and for writing TCMs.
2. The GC/CM shall be allowed to carry a maximum 5% of buyout savings after 80% of the work has been awarded to trade contractors. An evaluation will be performed by the Owner to determine the exact amount allowed. This allowance is in addition to any contingencies or other allowances within the negotiated MACC. The GC/CM shall carry this amount for six months after which the buyout savings goes to zero.
The MACC will be adjusted to reflect buyout savings by change order.
3. GC/CM Fee percentage, the negotiated Specified General Conditions and original scope of work will remain unchanged.
G. The GC/CM shall provide timely notification to the owner and A/E in writing of items missing or incomplete in the drawings and specifications. The GC/CM shall carry sufficient contingency and/or allowances within the negotiated MACC to correct such deficiencies. The GC/CM shall use the Risk Contingency or allowances noted above only upon the prior written authorization of the owner.
H. The Owner may negotiate with the GC/CM to add scope to the MACC within the legislative intent and the scope in the advertisement for the GC/CM’s services. The percent fee will be applied to any change of scope. Revision to the percent fee shall be negotiated if the MACC changes by more than 15%. The GC/CM will provide a bond for the revised TCC.
I. All project savings accrue to the owner upon completion of the project.
3.4 Accounting Records
The GC/CM shall keep full and detailed accounts and exercise such controls as may be necessary for proper financial management under this contract. The accounting and control systems shall be satisfactory to the owner.
During the period from the date when bids are opened on the first bid package until completion of the project, the GC/CM shall provide, on a monthly basis, a complete and comprehensive cost-accounting to the Owner of the status of all actual and budgeted costs within the MACC.
Accounting shall be provided in accordance with Article 9 of the GC/CM Contract Provisions.
3.5 Payment and Performance Bonds and Insurance
A payment and performance bond for 100% of the Total Contract Cost (TCC) and Washington State sales tax shall be furnished by the GC/CM. The GC/CM shall include within their Final Proposal (bid) the cost for providing a payment and performance bond and insurance in the full amount of the Total Contract Cost, including Washington State sales tax.
Note: AIA Payment Bond and Performance Bond forms (A312) are required. These forms will not be provided by the Owner.
Should the TCC be increased by change order, the Owner shall compensate the GC/CM for the increase, if required, for performance and payment bond on an actual cost basis. The GC/CM shall include within their proposal the cost for providing a payment & performance bond in the full amount of the Total Contract Cost, including Washington State sales tax.
General Liability Insurance: For the duration of the construction, the GC/CM shall carry liability coverage in accordance with the General Conditions.
Builder's All Risk Insurance: The GC/CM shall carry Builder's all-risk insurance, covering perils such as fire, flood, earthquake, and other natural disaster. The coverage shall be accordance with the General Conditions. Should the TCC be increased during the MACC negotiations or by change order the Owner shall compensate the GC/CM for the increase on an actual cost basis for associated bonds and insurance.
All Trade contractors who bid work over $300,000 shall post a bid bond and the awarded trade contractor shall provide a performance and payment bond for their contract amount plus Washington State sales tax. All other subcontracts under $300,000 shall provide payment and performance bonds, if required by GC/CM.
3.6 Changes in the Contract Sum
The GC/CM shall not be entitled to any markup on trade contractor work, except for payment and performance bond, builders risk insurance, general liability insurance and the GC/CM firm’s fee. The GC/CM may be eligible for mark-ups on changes per Part 7 of the General
Conditions on work where the GC/CM is self-performing as a trade contractor. Refer to Part
7 of the Washington State General Conditions for terms and conditions for changes in the work and for markups at the subcontract level.
3.7 Predetermination of Trade Contractor Eligibility
When determination of trade contractor eligibility prior to seeking bids is in the best interest of the project and critical to the successful completion of a subcontract bid package, the Owner and GC/CM may evaluate and determine bidder eligibility. The process shall adhere to the requirements of RCW 39.10.400 including public notification and public hearing of intent to evaluate and determine bidder eligibility with opportunity for written and verbal comments on the justification for conducting bidder eligibility, the evaluation criteria, and weights for each criteria and sub criteria.
A written final determination shall be issued to all interested parties. Any potential bidder determined not to meet eligibility criteria has one opportunity to establish its eligibility by providing additional information and meeting with the Owner and GC/CM within three business days of the final determination.
The criteria used to determine eligibility may include:
A. Adequate financial resources or the ability to secure such resources.
https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10.400
B. History of successful completion of a contract of similar type and scope.
C. Project management and project supervision personnel with experience on similar projects and the availability of such personnel for the project.
D. Current and projected workload and the impact the project will have on the trade contractor’s current and projected workload.
E. Ability to accurately estimate the trade contractor bid package shop drawing and other coordination procedures.
F. Eligibility to receive an award under applicable laws and regulations G. Ability to meet subcontract bid package scheduling requirements.
When trade contractor eligibility was not determined before bidding, the subcontract bid packages must include the specific objective criteria that will be used to evaluate bidder responsibility. Bidder responsibility must be determined in accordance with criteria listed in the bid documents per RCW 39.04.350.
3.08 GC/CM Alternative Selection of Major Trade Contractors
The GC/CM must competitively bid all subcontract work with public bid openings. The GC/CM firm may bid on subcontract work subject to limitations defined in RCW 39.10. The exception to this is the alternative selection of trade contractors using a similar process to the selection of the GC/CM in accordance with RCW 39.10.385. Department of Enterprise Services must approve the use of this alternate selection of trade contractors. This process may only be used when the anticipated value of the subcontract will exceed $3,000,000. Should the total value of the sum of the competitively bid subcontracts plus owner approved change orders be less than the negotiated trade package MACC, then the difference (defined as the "buyout savings") accrues to the Owner. If the construction is completed for more than the MACC, the additional costs are the responsibility of the SC/CM.
3.09 Self-Performance
The GC/CM, or its subsidiaries, may bid on subcontract work if A. The work within the subcontract bid package is customarily performed by the
GC/CM;
B. The bid opening is managed by the public body and is in compliance with
RCW 39.10.380 ; and C. Notification of the GC/CM’s intention to bid is included in the public solicitation of bids for the bid package.
In no event may the value of subcontract work performed and equipment and materials supplied by the GC/CM exceed thirty (30) percent of the negotiated maximum allowable construction cost.
3.10 Information for Capital Project Advisory Review Board
The GC/CM and its trade contractors shall be obligated to provide and submit project information to Enterprise Services, Engineering and Architecture Services as required by the board in RCW 39.10.
https://apps.leg.wa.gov/RCW/default.aspx?cite=39.04.350 https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10 https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10.385 https://apps.leg.wa.gov/RCW/default.aspx?cite=39.10