19-25-728 Attachment 05 CostResponsibilityMatrix.pdf
PDF 211 KB Posted
- Solicitation number
- 2025-728
- Issued by
- King County, Washington
About this file
This is a Cost Responsibility Matrix attachment for the Bellevue College Parking Garage Update project, a GC/CM (General Contractor/Construction Manager) delivery method contract with the Washington state institution. The matrix is designed to guide GC/CM proposers in developing cost proposals by delineating which fee proposal sections should include identified costs across five cost categories: Cost of the Work (COW), Negotiated Support Services (NSS), Specified General Conditions (SGC), Fee, and Preconstruction Services (PCS). The matrix identifies approximately 90 line items spanning materials, labor, equipment, permits, insurance, site management, administrative functions, and project closeout responsibilities, with each item assigned to one or more cost categories to establish the basis for the estimated Maximum Allowable Construction Cost (MACC).
The Cost Responsibility Matrix establishes clear cost allocation expectations for proposers, including direct cost responsibilities such as subcontractor and material costs, equipment, permits, warranties, site security, and temporary work under COW; reimbursable support services without markup under NSS; temporary work and staffing under SGC; overhead and profit under Fee; and design phase services including estimating, constructability reviews, and value engineering under PCS. The document emphasizes that in cases of conflict or omitted items, the GC/CM Agreement and General Conditions Document shall govern, and proposers must reference the RFFP, Instructions to Bidders, GC/CM Agreement, and all addenda to ensure compliance with total project scope requirements.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 05: Cost Responsibility Matrix
R6/14/22
Cost Responsibility Matrix
2025-728 Bellevue College Parking Garage Update
(To be attached to Agreement at contract execution)
In order to assist the GC/CM finalist in developing its cost associated with the different segments of the fee proposal process, DES is providing the following Cost Responsibility Matrix ("Matrix"). The checked box indicates in what section of the fee proposal DES expects GC/CM proposers to apply the identified cost.
• COW refers to Cost of the Work to be awarded via subcontracts.
• NSS refers to Negotiated Support Services
• SGC refers to Specified General Conditions
• PCS refers to Preconstruction Services
Proposers should refer to the RFFP, Instruction to Bidders, GC/CM Agreement and General Conditions documents including all addenda, to ascertain all the project scope requirements. In the event there is a conflict or omitted items contained in the Matrix, the GC/CM Agreement and the General Conditions Document shall govern.
This Matrix establishes the basis for the estimated MACC used in the RFP.
Item COW NSS SGC Fee PCS Owner
Sub-contractor and material costs X
Equipment and supplies related to the work X
Meet regulatory requirements X
Permits other than building permit X
Warranties X
Refuse collection, clean-up, removal and disposal from the site—unless included in sub bids
X
Dust control—unless included in sub bids X
Primary surveying and control X
Temporary signs fences and barricades X
Site security including lighting and 24-hour camera and recording of project site (2 camera locations).
X
Flaggers and traffic control X
Erosion control X
Cranes and hoisting X
Item COW NSS SGC Fee PCS Owner
Scaffolds and shoring X
Elevator operations X
Weather protection X
Temporary site conditions and modifications X
Selective demolition X
Mock-ups X
Temporary project fire protection X
Temporary heat, power, and water (consumption) X
Final cleaning X
Project signs X
Project manager(s) on site during construction X
Superintendent(s) during construction X
Project engineers during construction X
Administrative staffing on site during construction X
Funding support documentation X
Estimating during construction X
Meeting minutes and administration during construction
X
Schedule development and updating during construction
X
Sub-contract administration and coordination X
Contractor accounting and cost accounting X
Project cash flow analysis X
Administration of the project safety program X
Item COW NSS SGC Fee PCS Owner
Administration of the environmental program, including waste management program. Campus protocol as environmental campus, LEED/sustainability requirements, State of Washington construction waste protocol
X
Applications for payments X
Change order preparation and procedures X
Communications and coordination X
Managing regulatory requirements X
Review and processing of submittals, shop drawings and samples
X
Maintaining and updating BIM models and/or CAD drawings during construction
X
Contractor quality control X
Coordination of testing laboratory X
Administration and coordination of the commissioning program
X
Equipment, phones, and supplies related to management
X
Company-owned vehicles assigned to field staff (company trucks)
X
Travel, gas, oil, (maintenance for company-owned vehicles assigned to field staff)
X
Coordination of other Owner contractors X
Contract close-out X
Punch-list preparation and administration X
All site safety work X
All GC/CM insurance, payment and performance bonds (not including Builders Risk)
X
Builders Risk insurance as stated in the agreement X
GC/CM profit (or loss) X
GC/CM taxes except sales taxes X
Item COW NSS SGC Fee PCS Owner
Liquidated damages X
Legal expenses X
Wages & salaries of Office personnel X
Fee proposal preparation, site walk, interview process, invitation to bid, GC/CM Agreement and General Conditions
X
GC/CM corporate overhead, office expenses X
Travel expenses X
Design participation through GMACC X
Estimating through GMACC X
Meeting minutes-through GMACC X
Pre-construction schedules X
Sub-contractor and supplier analysis of market conditions prior to bidding
X
Review and recommendations of possible product substitutions
X
Review of Value Engineering studies for additional recommendations
X
Provide pre-bid Constructability Reviews X
Assembling and updating BIM models as assigned X
Other technical or administrative tasks as assigned during the design phase
X
Development of GMACC or interim Contract Amendments
X
Sub-contractor bid packaging and development X
Diverse Business Outreach X
Advertise project for bids X
Pre-bid conferences and marketing X
Item COW NSS SGC Fee PCS Owner
Sub-contractor and supplier bid analysis and award recommendation including possible alternative subcontracting opportunities
X
Review and analysis of subcontractor qualifications per RCW 39.10
X
Coordination and finalization of subcontracting for labor, material and equipment, including reviews/finalization of scopes of work and buyouts
X
Construction office and facilities X
Temporary sanitation X
Permanent Utility hook-up, X
Architectural and engineering services X
Sub-contractor bid document reproduction X
Washington State Sales Tax on GC/CM billings X
General Building permit and Site work Building permit
X
Testing laboratory and testing services per the Contract Documents (Code related)
X
Project management consultant X
Negotiated Support Services (NSS) Items a general contractor would normally manage or perform on a construction project including, but not limited to,
• surveying,
• hoisting,
• safety enforcement, Items provided by the GC/CM as reimbursable cost within the MACC on a direct cost basis without markup; these items are not a biddable part of the work.
Cost of the Work (COW)
Sub-contractor costs which include change orders. Includes all GCCM self-performed work.
Specified General Conditions (SGC) Temporary work, staff, and/or fees performed by or paid by the GC/CM to accomplish the project scope of work as detailed in the Request for Proposal.
Pre-construction Services (PCS) Throughout the design period the GC/CM will provide services to include, but not limited to, the following:
• Attend and participate in design meetings.
• Value Engineering.
• Scheduling.
• Design Cost Estimating.
• Constructability Review and Analysis.
• Interdisciplinary Coordination,
• Project Management Services.
• Alternative Construction Options for Cost Savings.
• Planning for Sequencing of the work.
• Utility investigation/potholing as required per Architect/Engineer.
Pre-construction Services Fee The Lump Sum fee amount for the GC/CM proposer to provide the Pre-Construction
Services for the Project.
Percent Fee The percentage amount to be earned by the GC/CM as overhead and profit.