10-25-728 Article 11 ContractChanges.pdf
PDF 142 KB Posted
- Solicitation number
- 2025-728
- Issued by
- King County, Washington
About this file
This document is an Article 11 contract management procedure guide applicable to Washington state construction projects, specifically detailing the contract change management protocols for the Bellevue College Parking Garage Update project administered through a General Contractor/Construction Manager (GC/CM) delivery method. The article outlines the procedures for modifying contracts through four primary mechanisms: Change Order Proposals (COPs), Field Authorizations (FAs), Change Orders (COs), and Team Change Memos (TCMs). COPs are used when fixed costs are determined prior to work execution and require written authorization from the state's contracting officer before work commences. FAs allow immediate work commencement with estimated not-to-exceed pricing in emergency situations or when project schedule delays would result, requiring verbal or written approval from the Project Manager, DES Assistant Program Manager, or FPS Program Manager for amounts exceeding $50,000. All changes must be documented within a master change log maintained by the GC/CM throughout the project lifecycle, and the state is obligated to issue change orders within 30 days of written agreement, with interest accruing at one percent per month if this timeline is not met.
The Maximum Allowable Construction Cost (MACC) serves as the baseline for distinguishing change types, with changes exceeding the MACC paid from Owner contingency funds and changes within the MACC funded through risk contingency or bid package savings. COPs and FAs of $50,000 or more require approval from the FPS Program Manager or DES Assistant Program Manager, while TCMs up to $50,000 require only the project manager's authorization with amounts exceeding this threshold requiring Assistant Program Manager or Program Manager approval. The GC/CM bears responsibility for ensuring all FA and COP work items are converted to change orders before inclusion in payment applications, and all changes must be reviewed at weekly project team meetings. The contract guarantees that the original scope of work will not exceed the MACC and that all work necessary to produce a complete, fully functional facility within the original scope, including work required to conform to published codes and state/federal/local laws, will be covered by the MACC.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Article 11: Contract Changes 4-22
ARTICLE 11: CONTRACT CHANGES
11.1 Types of Contract Changes
Modifications to the contract occur when a signed, fully executed change order from the Owner to the GC/CM changes the Total Contract Cost (TCC). Only in an emergency situation can the DES Project Manager give verbal authorization for a change. Written documentation must be confirmed in writing within 48 hours.
A Change Order Proposal (COP), or a Field Authorization (FA) changes the project scope and can change the contract sum and the contract time. When all terms have been agreed to and signed by the GC/CM, Consultant and Owner; the COP or FA will be converted into a Change Order. A Team Change Memo (TCM) authorizes changes to the work within the MACC. This section describes how FAs, COPs, Change Orders, and TCMs are issued, monitored, and incorporated into the GC/CM's contract.
If the Owner and the GC/CM agree, in writing, on a price for additional work, the Owner must issue a change order within 30 days of the written agreement. If the public body does not issue a change order within the 30 days, interest shall accrue on the dollar amount of the additional work satisfactorily completed until a change order is issued. The Owner shall pay this interest at a rate of one percent per month.
The original scope of work is guaranteed by the GC/CM not to exceed the MACC. The MACC will cover all work necessary to produce a complete, fully functional facility within the original scope of work. The GC/CM is responsible for building the facility and supporting infrastructure within the MACC at the scope defined at the time the MACC is established.
The GC/CM will accomplish this objective within the MACC by using savings from bid packages and GC/CM contingencies to cover these types of changes. Work necessary to conform to published code and state/federal/local laws will be covered by the MACC. The MACC and/or the schedule may be changed due to latent site conditions or to a change in the scope of work by the owner.
11.2 Changes to the MACC and/or Schedule
Changes to the MACC shall be paid out of the Owner contingency. The Owner contingency shall be used to pay for changes such as latent conditions, and changes in the Owner's design. A COP is used to initiate a change where the fixed costs are determined and agreed to prior to the work being executed. An FA allows change work to commence with an estimated not to exceed price before the final scope or costs can be established. No COP or FA shall be issued as a change order without defining the exact cost for the work supported by appropriate backup documentation.
Changes involving the scope of work that results in a change of the cost of the work or the schedule, must be authorized in writing on the COP by the state's contracting officer prior to the change work starting. The GC/CM shall receive a fully executed copy of the Change Order authorization to proceed prior to beginning work.
An FA may be initiated with a not-to-exceed cost limit when an exact price cannot initially be determined. In this case, the FA should include a statement of how the cost will be determined, i.e., cost of materials, plus exact hourly rates, plus profit/overhead if any.
The team Contract Specialist shall incorporate FAs and COPs that include completed cost breakdowns and appropriate backup into change orders as they are received in the project manager’s office. No COP shall be acted upon until documentation is received and approved and a change order issued. Failure of the GC/CM to adhere to this requirement exempts the state from any obligation for such work and may make the GC/CM liable for claims resulting from unauthorized work.
The GC/CM, Consultant, Owner and DES project manager shall sign each original COP and FA. The State’s contracting officer shall supply copies of the executed change order to the GC/CM, A/E, and Owner. The contracting officer shall have final approval on any exception to this procedure. Upon execution of a change order, the GC/CM will modify the project budget sheet to reflect the change to the MACC.
Master Change Log
The GC/CM shall maintain a master change log which shall list all FAs, COPs, TCMs and their executed COs. The master change log is a comprehensive listing of all changes and modifications considered and executed for the project. The log incorporates a running summation of all executed COs, FAs or COPs not yet converted to COs. The project team can, at any time, ascertain the value of existing executed changes, changes implemented but not yet formally executed, FAs, and those COPs awaiting consideration.
Once a FA or COP is issued in the field, the work item is given the next FA or COP number in the master log.
Upon receipt of an FA, COP or TCM, the GC/CM shall enter the appropriate information on the master change log. All COPs, FAs and TCMs shall remain on the log for the duration of the project even if they are ultimately rejected. The project team shall review all FAs and COPs pending and executed within the past week at the team weekly progress meeting.
Should the work item be rejected, the FA or COP is marked "void" with a brief explanation and remains on the master log. A complete and chronological history is maintained of all contemplated changes or modifications.
Change Order Proposal (COP)
The COP is a request to change in scope that changes the contract sum (MACC) or time or both. The Owner, project manager, Consultant, or GC/CM may request a COP. The Consultant will write the COP after it receives a sequential COP number from the master change log from the GC/CM. When a COP number is issued, the item is entered into the log, and remains there throughout the life of the project providing a continuous history of all changes that have been considered.
COPs are sent to the Consultant for design and/or specifications as necessary. A copy is kept in a central file at the job site. The GC/CM will deliver a complete package, with applicable cost information to the Consultant with copies to the Owner and Project Manager. The project team will review and the team will either accept the change as proposed, reject the change, or will direct the Consultant or GC/CM to make modifications to the documentation. The latter process may occur on an iterative basis until the COP is accepted or rejected. Once approved and signed, a change order will be issued within 30 days. If a change order is not issued for an approved, signed COP within 30 days, interest in the amount of one percent per month shall accrue on the dollar amount of the additional work completed.
COPs of $ 50,000.00 or more require approval from the FPS Program Manager or DES Assistant Program Manager.
COPs are executed with the original going to the DES contract file and signed copies going to the GC/CM, Consultant, DES project manager, and the Owner.
Field Authorization (FA)
An FA is an authorization to commence the work immediately for an estimated maximum not to exceed amount. FAs are issued if there is an immediate threat to life or safety, or if delaying the work will affect the overall project schedule. Otherwise, the change will be initiated as a COP. No FA shall be authorized without an estimated not to exceed cost for the change.
FAs $50,000.00 and over must be approved by FPS Program Manager or Assistant Program Manager. FAs for this amount may be issued for the same reasons as above.
Verbal approval may be given by the PM or designee. Written confirmation of the verbal authorization must be attached to the FA and transmitted to the authorizing official within three (3) days of the FAs execution. In the absence of the contracting officer or designee, the DES public works administrator can provide verbal authorization of the FA.
FAs are originated by the project manager, the A/E, or the Owner. Every FA is assigned a sequential FA number that is obtained from the GC/CM or designee. Once an FA number is issued, it is entered into the master change log and remains there throughout the life of the project providing a continuous history of all changes that have been considered.
The original FA shall be retained by the GC/CM until the work is completed and receipt and approval of cost data backup. After the project team reviews and approves the costs, it is forwarded to the Contract Specialist by the project manager to be incorporated into a CO within 30 days. Copies are distributed to the GC/CM, project manager, Consultant, and Owner.
Changes involving a change to the MACC will be accomplished using the above process.
Payment applications shall include only fully executed change orders. Consequently, the GC/CM is charged with responsibility of ensuring that all FA and COP work items are converted to change orders.
11.3 Changes Within the MACC
Team Change Memo
Changes within the MACC shall be paid out of the risk contingency or from any remaining buyout savings. The risk contingency shall be used to pay for items that are not included in plans and specifications but are required to complete the project to achieve a fully functional facility. The approval of the DES project manager is necessary before the GC/CM can authorize any change within the MACC. Changes within the MACC are authorized by a Team Change Memo (TCM).
A TCM may be initiated by a FA or COP in the same manner as in the change order process. The process described above for FAs and COPs shall be followed. A TCM will be issued rather than a CO whenever the change does not involve a latent condition or a change in the scope of work by the Owner or Owner’s representative. TCMs may also be initiated without an FA or COP for changes within the MACC. The project manager has signature authority for TCMs up to $50,000. TCMs at $50,000 and above require prior approval by the Assistant Program Manager or Program Manager.
An accounting of changes within the MACC is reported by the GC/CM on a monthly basis in the Cost Accounting Report. Copies of TCMs authorizing changes within the MACC shall be forwarded by the GC/CM to the project manager, A/E, and Owner immediately.
The TCM log shall be available for review at weekly construction progress meetings.