This is a Facility Professional Services Final Completion & Acceptance Checklist form effective June 1, 2025, for use by the Washington Department of Enterprise Services (DES) and client agencies managing construction and facility projects. The checklist establishes a standardized process for documenting project completion and final acceptance, applicable to projects exceeding $35,000 that require Notice of Completion (NOC) filing with the Department of Labor & Industries (LNI). The document outlines sequential verification steps required from the contractor, Architect/Engineer (A/E), Project Manager (PM), and Client Agency throughout two distinct phases: Final Completion Process (steps 1-12) and Final Acceptance Process (steps 13-27), with a 45-day lien period following contract closure.

The checklist requires contractors to submit written notice of punch list completion, provide LNI-approved affidavits of wages paid for all subcontractors, and confirm all work compliance with contract specifications. The A/E must conduct final on-site inspections, approve as-built documentation, verify LEED compliance, resolve Field Authorizations (FAs) and Change Orders, and confirm post-commissioning activities. The PM must verify claims resolution, complete contractor invoicing including retainage processing, confirm apprentice participation percentages against the 15% goal or calculate penalties, verify diversity compliance audits through DES B2Gnow, and ensure all agency releases from LNI, Department of Revenue (DOR), and Employment Security Department (ESD) are received. The PM issues the NOC within LNI, coordinates contract closure with the Contract Specialist (CS), and completes final documentation retention verification after the 45-day lien period expires.

View the file

Other files

File Type Posted
24-25-728 Attachment 11 RetainageBondForm.pdf PDF
19-25-728 Attachment 05 CostResponsibilityMatrix.pdf PDF
25-25-728 Attachment 12 ChangeOrderProposalForm.pdf PDF
20-25-728 Attachment 07 ApprenticeUtilizationPlanForm.pdf PDF
27-25-728 Attachment 14 TeamChangeMemo.pdf PDF
1-25-728 Article 00 InstructionsToProposers.pdf PDF
13-25-728 Article 14 Definitions.pdf PDF
17-25-728 Attachment 03 FinalProposalForm.pdf PDF
7-25-728 Article 08 QualityControlAssurance.pdf PDF
11-25-728 Article 12 ScheduleManagement.pdf PDF
3-25-728 Article 03 ModificationsToWashingtonStateGeneralConditions.pdf PDF
6-25-728 Article 07 ApprenticeshipRequirements.pdf PDF
12-25-728 Article 13 SubstantialCompletion-ProjectCloseout.pdf PDF
28-25-728 Attachment 15 WageTheftForm.pdf PDF
23-25-728 Attachment 10 RCWsRelevantToGCCM.pdf PDF
26-25-728 Attachment 13 FieldAuthorizationForm.pdf PDF
22-25-728 Attachment 09 Ph2ProtestProcedures.pdf PDF
5-25-728 Article 06 ElementsOfTotalContractCost.pdf PDF
10-25-728 Article 11 ContractChanges.pdf PDF
4-25-728 Article 05 PreconstructionServices.pdf PDF
14-25-728 Attachment 00 ProposerContactForm.pdf PDF
8-25-728 Article 09 CoordinationAndMeetings.pdf PDF
21-25-728 Attachment 08 Ph1ProtestProcedures.pdf PDF
9-25-728 Article 10 Budget.pdf PDF
16-25-728 Attachment 02 RequestForFinalProposal.pdf PDF
15-25-728 Attachment 01 AdvertisementForGCCM.pdf PDF
18-25-728 Attachment 04 PerformanceEvaluationQuestionnaire(GCCM).pdf PDF
2-25-728 Article 01 GeneralConditions.pdf PDF
29-25-728 Attachment 16 CertificateOfSubstantialCompletion.pdf PDF
31-25-728 RFQ-RFP.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FACILITY PROFESSIONAL SERVICES

FINAL COMPLETION & ACCEPTANCE

CHECKLIST

Effective: 6/1/2025

Project Title: Project/JOC/Work Order No.:

Project Manager: Client Agency:

Contractor: Architect/Engineer:

Actions Reference Info.

Verified

By (initials) Date

Final Completion Process

1. Contractor: Submit written notice that all incidental corrective work (punch list) is completed. GC 6.09; per

Spec.

2. Contractor: Confirms affidavit of wages paid, approved by LNI, for the contractor and all tiers of subcontractors that performed work on the project. GC 5.04C

3.

Contractor: All work done per contract

Print Name: Signature: Date:

4. A/E: In consultation with FPS PM and Owner, conduct a final on-site inspection of punch list to confirm completion. GC 6.09; per Spec.

5. A/E: Confirms review and approval and acceptance of final "As-Built" Record Documents from contractor. GC 4.02

6. A/E: Confirms all LEED documentation complete and submitted to US Green Building Council.

7. A/E: Verify all FAs and COPs resolved, approved, and all Change Orders processed. GC 6.09

8. A/E: Verifies all post- commissioning fine-tuning is complete, and issues resolved. GC 6.09; per Spec.

9. PM: Submit Commissioning Final Report (except seasonal testing). GC 6.09; per Spec.

10.

A/E Recommendation of Acceptance (All work acceptable per Contract)

Print Name: Signature: Date:

11.

Client Agency Recommendation of Acceptance

Print Name: Signature: Date:

12.

PM Determination of Date of Final Completion Final Completion Date:

Print Name: Signature:

Final Acceptance Process

13. PM: Verify any and all claims and/or disputes resolved. GC 6.09

14. PM: Verify final contractor invoicing complete (100% & retainage as applicable*).

*Retainage invoice cannot be paid until after LNI, DOR & ESD Reviews

GC 6.09; per Spec.

15. PM: Uses the LNI portal to verify all affidavits and certified payroll, including lower tier subcontractors, submitted to LNI. GC 5.04 RCW 39.12.040

16.

PM: Uses the LNI portal and approved affidavits to verify apprentice participation is ________%. Processes incentive payments for meeting the 15% apprentice goal. If the goal wasn’t achieved, forwards the good faith effort to the APM or calculates the penalty to be $___________.

GC 10.12;

per Spec.

17. PM: Verify that audits are up to date through the Final Completion Date (except retainage) within DES Diversity Compliance program (B2Gnow).

18.

PROGRAM MANAGER OR APM Approves Closing the Contract

Print Name: Signature: Date:

19.

PM: Issues the Notice of Completion (NOC) for projects above $35,000 within LNI. For DOC and DSHS projects, Fiscal issues NOC.

*Notifies CS that NOC has been issued

20. PM: Verify that all documents are retained as per DES policy.

21.

CS: Closes the contract and advertises the Final Acceptance date. 45-day lien period begins. Notifies the PM, A/E, Client Agency, and Contractor that the contract has been accepted.

Final Acceptance Date:

Print Name:

22. PM: Verifies that all B2Gnow audits are marked final and notifies CS to close the contract.

23. PM: Verifies that the contract in the DES Diversity Compliance program (B2Gnow) has been closed by the CS.

45 Day Lien Period Expires & Notice of Completion has been accepted by LNI. (Steps 24-27 are completed after 45 Day Lien Period.)

24. PM: Verifies all agency releases are received (LNI, DOR, ESD) and sent to the CS.

25. PM: Verifies that the Client Agency has released the retainage for projects that don’t have a retainage bond.

FACILITY PROFESSIONAL SERVICES

FINAL COMPLETION & ACCEPTANCE

CHECKLIST

Effective: 6/1/2025

26. PM: Verifies with the CS that the Project Master in PTS is closed.

27. PM: Sends completed Final Acceptance Checklist to CS to be saved in the project file.

Notes:

1. References provided are for information. Contractor shall refer to the Contract Documents to fulfill all contract requirements.

2. If there are consultants for the project, the FPS PM will reconcile and issue a consultant completion request.

3. If there are no consultants for the project, the FPS PM will mark “NA” for all A/E related line items.

Notes:

Project Title:
ProjectJOCWork Order No:
Project Manager:
Client Agency:
Contractor:
ArchitectEngineer:
Notes:
1:
GC 609:
Date:
2:
GC 504:
Date:
10:
Date:
AE Print Name:
AE Signature:
11:
Client Agency Print Name:
Client Agency Signature:
Date:
3:
Date:
Contractor Print Name:
Contractor Signature:
4:
GC 609:
Date:
5:
GC 402:
Date:
6:
AE Confirms:
Date:
7:
GC 609:
Date:
8:
GC 609:
Date:
9:
Date:
GC 609:
12:
DES PM Signature:
DES PM Print Name:
Date:
13:
GC 609:
Date:
14:
GC 609:
Date:
15:
GC 504:
Date:
16:
Apprentice %:
Apprentice Penalty:
Date:
GC 1012:
17:
Audit Verification:
Date:
18:
DES APM Signature:
Date:
DES APM Print Name:
19:
NOC:
NOC Issued:
20:
Docs Retained:
Docs Retained Date:
21:
Date:
DES CS Name:
22:
B2G Audits:
B2G Audits Date:
23:
B2G Closed:
B2G Closed Date:
24:
Releases Rec'd:
Releases Rec'd Date:
25:
CA Released Retainage:
CA Released Retainage Date:
26:
PTS Closed:
PTS Closed Date:
27:
Checklist to CS:
Checklist to CS Date: