This is a Questions and Answers document related to the Space weather Observations at L1 to Advance Readiness Project (SOLAR) X-Ray Irradiance Sensor (XRIS) acquisition. The document addresses a single question regarding CREME96 modeling requirements specified in Attachment B – SPEC, XRIS-200, subsection 4.4 Instrument Data Availability. The answer clarifies that a detailed CREME96 analysis is not required at the time of proposal submission. Instead, offerors must demonstrate understanding of the requirements and capability to complete the analysis during future design reviews. Acceptable methods of demonstrating this understanding include providing the analytical approach or submitting a preliminary analysis. The document notes that in the event of any discrepancy between this Q&A and the Final Request for Proposal, the RFP provisions and contract terms will take precedence.

View the file

Other files

File Type Posted
Update 02_Questions and Answers.pdf PDF
Amendment 01_XRIS RFP 80GSFC26R0006 (duly executed).pdf PDF
4) Attachment A - SOLAR XRIS SOW.pdf PDF
10) Attachment G - SOLAR XRIS GFP.pdf PDF
11) Attachment J - Requirements Statements List.pdf PDF
17) Attachment N - 3. DRD CPIC.pdf PDF
18) Attachment N - 3a. DRD CPIC Template for IT Portfolio PPM Data Collection.pdf PDF
5) Attachment B - SOLAR XRIS SPEC.pdf PDF
7) Attachment D - SOLAR XRIS MAR.pdf PDF
12) Attachment K - Small Business Subcontracting Plan.pdf PDF
15) Attachment N - 1. Non-Technical Contract Data Requirements List.pdf PDF
20) Attachment N - 4a. DRD CITAR Report Template.pdf PDF
22) Attachment P - Contractor Proposed Enhancements.pdf PDF
27) Exhibits 1 - 3.pdf PDF
2) 80GSFC26R0006 XRIS SF33.pdf PDF
6) Attachment C - SOLAR XRIS CDRL.pdf PDF
8) Attachment E - SOLAR XRIS RHARD.pdf PDF
13) Attachment L - Time-and-Materials Rates.pdf PDF
14) Attachment M - Performance Based Milestone Payment.pdf PDF
21) Attachment O - Organizational Conflicts of Interest (OCI) Plan.pdf PDF
25) Enclosure 2 - Financial Capability Disclosure.pdf PDF
1) XRIS Final RFP 80GSFC26R0006 Cover Letter.pdf PDF
3) XRIS RFP 80GSFC26R0006.pdf PDF
9) Attachment F - Funding Profile.pdf PDF
16) Attachment N - 2. DRD-2 Security Requirements for Unclassified IT Resources.pdf PDF
19) Attachment N - 4. DRD CITAR.pdf PDF
23) Attachment Q - Quality Assurance Plan.pdf PDF
24) Enclosure 1 - Past Performance Questionnaire.pdf PDF
26) Enclosure 3 - Quality Assurance Surveillance Plan.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Below are questions related to the Space weather Observations at L1 to Advance Readiness Project (SOLAR) X-Ray Irradiance Sensor (XRIS) acquisition. In the event of any discrepancy, the Final Request for Proposal provisions and contract terms will take precedence.

Question 1:

Attachment B – SPEC, XRIS-200 in subsection 4.4 Instrument Data Availability:

Is the CREME96 modeling something that is required at the time of submission or is this something that will be required at the time of future design reviews? If needed at submission what is the scope of this requirement at the time of submission - every component or a general model?

Answer 1:

No, a detailed analysis is not required with the proposal. The offeror shall demonstrate that they understand the requirements and can accomplish the work to complete the analysis. Providing the approach to the analysis or a preliminary analysis are ways to demonstrate that understanding.