7) Attachment D - SOLAR XRIS MAR.pdf

PDF 522 KB Posted

Attached to
Space weather Observations at L1 to Advance Readiness (SOLAR) Series X-ray Irradiance Sensor (XRIS)
Solicitation number
80GSFC26R0006
Issued by

About this file

This document is a Mission Assurance Requirements (MAR) specification for the X-Ray Irradiance Sensor (XRIS) instrument, part of the Space Weather Next (SW Next) Program under the Space weather Observations at L1 to Advance Readiness (SOLAR) Project. The MAR is effective March 13, 2026, through March 13, 2031, and applies to the development of a Class C free flyer payload being developed jointly by the U.S. Department of Commerce (NOAA/NESDIS) and NASA (GSFC).

The document establishes risk-based safety and mission assurance requirements across twelve disciplinary areas: General SMA Requirements, Quality Management System, System Safety, Reliability, Software Assurance, Workmanship, EEE Parts, Materials and Processes, Contamination Control, Metrology and Calibration, GIDEP Alerts and Problem Advisories, and End Item Acceptance Data Package. Key requirements include: implementing a comprehensive safety and mission assurance program with an independent assurance manager; establishing quality management systems compliant with SAE AS9100; performing failure modes and effects criticality analyses (FMECA) and fault tree analyses; ensuring three independent inhibits for catastrophic hazards and two for critical hazards; developing system safety plans and instrument safety assessment reports; implementing EEE parts control at Level 3 per GSFC standards; and maintaining detailed tracking logs for hazard verification and anomaly resolution. The developer must flow down requirements to all suppliers, establish Material Review Boards and Anomaly Review Boards for major nonconformances, provide quarterly quality metrics to NASA, participate in GIDEP programs, and submit multiple contract data requirements list deliverables throughout the project lifecycle. The specification includes detailed technical standards references for workmanship, PCB design, software assurance, radiation effects mitigation, and lifting device safety, with NASA maintaining surveillance and inspection rights including Government Mandatory Inspection Points for firm fixed price work.

View the file

Other files

File Type Posted
Update 02_Questions and Answers.pdf PDF
Amendment 01_XRIS RFP 80GSFC26R0006 (duly executed).pdf PDF
Update 01_Question and Answer.pdf PDF
5) Attachment B - SOLAR XRIS SPEC.pdf PDF
12) Attachment K - Small Business Subcontracting Plan.pdf PDF
15) Attachment N - 1. Non-Technical Contract Data Requirements List.pdf PDF
20) Attachment N - 4a. DRD CITAR Report Template.pdf PDF
22) Attachment P - Contractor Proposed Enhancements.pdf PDF
27) Exhibits 1 - 3.pdf PDF
2) 80GSFC26R0006 XRIS SF33.pdf PDF
6) Attachment C - SOLAR XRIS CDRL.pdf PDF
8) Attachment E - SOLAR XRIS RHARD.pdf PDF
13) Attachment L - Time-and-Materials Rates.pdf PDF
14) Attachment M - Performance Based Milestone Payment.pdf PDF
21) Attachment O - Organizational Conflicts of Interest (OCI) Plan.pdf PDF
25) Enclosure 2 - Financial Capability Disclosure.pdf PDF
1) XRIS Final RFP 80GSFC26R0006 Cover Letter.pdf PDF
3) XRIS RFP 80GSFC26R0006.pdf PDF
9) Attachment F - Funding Profile.pdf PDF
16) Attachment N - 2. DRD-2 Security Requirements for Unclassified IT Resources.pdf PDF
19) Attachment N - 4. DRD CITAR.pdf PDF
23) Attachment Q - Quality Assurance Plan.pdf PDF
24) Enclosure 1 - Past Performance Questionnaire.pdf PDF
26) Enclosure 3 - Quality Assurance Surveillance Plan.pdf PDF
4) Attachment A - SOLAR XRIS SOW.pdf PDF
10) Attachment G - SOLAR XRIS GFP.pdf PDF
11) Attachment J - Requirements Statements List.pdf PDF
17) Attachment N - 3. DRD CPIC.pdf PDF
18) Attachment N - 3a. DRD CPIC Template for IT Portfolio PPM Data Collection.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective Date: March 13, 2026

Expiration Date: March 13, 2031

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

SOLAR-XRIS-REQ-0032, Revision B

Space Weather Next (SW Next) Program

Space weather Observations at L1 to Advance Readiness Project

Code 493

SOLAR

X-Ray Irradiance Sensor (XRIS)

Mission Assurance Requirements (MAR)

U.S. Department of Commerce (DOC)

National Oceanic and Atmospheric Administration (NOAA)

National Environmental Satellite, Data, and Information Service (NESDIS)

National Aeronautics and Space Administration (NASA)

GSFC SOLAR CMO

03/13/2026

Released

SOLAR XRIS MAR SOLAR-XRIS-REQ-0032, Revision B ii

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

SOLAR X-Ray Irradiance Sensor (XRIS) Mission Assurance

Requirements (MAR) Signature/Approval Page

Prepared by:

Paul Markie

Reviewed by:

Charles (Hudson) DeLee

Stephen Husty

Brennan Nowak

John Vollmer

Yaireska Collado Vega

John Panek

Edward Glanfield

Shiva Anand

Thomas Haas

Approved by:

James (Jim) Morrissey iii

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Preface

This document is under Space weather Observations at L1 to Advance Readiness (SOLAR) configuration management (CM)-controlled document. Changes to this document require prior approval and shall be submitted in the SOLAR project Technical Data Management System

(TDMS) via a Configuration Control Request (CCR) or Signature Control Request (SCoRe), along with supportive material justifying the proposed change. Changes to this document will be made via complete revision.

All of the requirements within this document assume the use of the work “shall” unless otherwise stated.

Questions or comments concerning this document should be addressed to:

SOLAR Project Configuration Management Office

Goddard Space Flight Center

Code 493

Greenbelt, MD 20771 iv

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Change History Log

Revision Effective Date Description of Changes

(Reference the CCR & CCB/ERB Approval Date)

Revision RFI 05/31/2024 Baseline release for RFI released following the approval of

SOLAR-CCR-0081

Revision - 04/09/2025 Baseline release following the approval of SOLAR-CCR-

Revision A 09/15/2025 Update following the approval of SOLAR-CCR-0143

Revision B 03/13/2026 Update following the approval of SOLAR-CCR-0184 v

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Table of Contents

1 GENERAL

1.1 Systems Safety and Mission Assurance Program

1.2 Management

1.3 Requirements Flow down

1.4 Identification of Project-Level Critical Items (PCIs)

1.5 Suspension of Work Activities

1.6 Surveillance

1.7 Government Mandatory Inspection Points (GMIPs)

1.8 List of Suppliers

1.9 Use of Inherited Products/Items

1.10 Protection of Flight Hardware

1.11 Risk Management

2 QUALITY MANAGEMENT SYSTEM

2.1 General

2.2 Supplemental Quality Management System Requirements

2.2.1 Control of Nonconforming Product

2.2.2 Material Review Board (MRB)

2.2.3 Anomaly Reporting and Disposition

2.3 Orbital Debris Assessment Report (ODAR) and End of Mission Plan (EOMP)

3 SYSTEM SAFETY

3.1 General

3.2 Mission Related Safety Requirements Documentation

3.3 System Safety Deliverables

3.3.1 System Safety Plan

3.3.2 Safety Requirements Compliance Checklist

3.3.3 Instrument Safety Assessment Report (ISAR)

3.3.4 Hazard Analyses

3.3.4.1 Preliminary Hazard Analysis

3.3.4.2 Operations Hazard Analysis (OHA) and Hazard Verification Tracking Log

(HVTL)

3.3.4.3 Operating and Support Hazard Analysis

3.3.5 Verification Tracking Log (VTL)

3.3.6 Hazardous Procedures for Payload I&T and Pre-launch Processing

3.3.7 Lifting Device Safety Requirements

3.3.8 Mishap Reporting and Investigation

3.3.9 NASA ELV Payload Safety Program Forms

4 RELIABILITY

4.1 Reliability Program

4.2 Analysis of Design

4.2.1 FMECA and Critical Items List (CIL)

4.2.2 Fault Tree Analysis (FTA)

4.2.3 Reliability Calculations

4.3 Limited Life Analysis

vi

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

4.4 Parts Stress Analysis

4.5 Worst-Case Analysis

5 SOFTWARE ASSURANCE

5.1 Software Assurance Program

5.2 Surveillance of Software Development, Maintenance, and Assurance Activities

6 WORKMANSHIP

6.1 General

6.2 Electrostatic Discharge Control (ESD)

6.3 Printed Circuit Boards (PCB)

6.4 Lead-Free Control Measures

7 EEE PARTS

7.1 General

7.2 Parts Control Board

7.3 Re-use of EEE Parts

7.4 Master EEE Parts List

7.5 Radiation Effects Mitigation

8 MATERIALS AND PROCESSES

8.1 M&P Selection, Control, and Implementation Plan (MPCIP)

8.2 Materials Identification and Usage List (MIUL)

8.3 Life Test Plan for Lubricated Mechanisms

8.4 Additive Manufacturing Control Plan (AMCP)

9 CONTAMINATION CONTROL

9.1 Contamination Control Plan

9.2 Material Outgassing

9.3 Foreign Object Debris Program

10 METROLOGY AND CALIBRATION

10.1 Metrology and Calibration Program

10.2 Use of Calibrated and Non-Calibrated Instruments

11 GIDEP ALERTS AND PROBLEM ADVISORIES

11.1 Government-Industry Data Exchange Program (GIDEP)

11.2 Alert Disposition

11.3 GIDEP Reporting

11.4 Review Reporting

12 END ITEM ACCEPTANCE DATA PACKAGE

Appendix A Acronym List

List of Tables

Table 4.1 Severity Categories Table 4.2 Likelihood Rankings Table 4.3 Consequence Rankings vii

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Document Organization and Conventions

This document establishes a risk-based application of mission assurance requirements for a Class

C free flyer payload. It is organized around the following Safety and Mission Assurance (SMA) disciplines or focus areas, each with its own section:

• Section 1 – General SMA Requirements • Section 7 - EEE Parts

• Section 2 – Quality Management System • Section 8 – Materials and Processes

• Section 3 – System Safety • Section 9 – Contamination Control

• Section 4 – Reliability • Section 10 – Metrology and Calibration

• Section 5 – Software Assurance • Section 11 – GIDEP Alerts and Problem

Advisories

• Section 6 - Workmanship • Section 12 – End Item Acceptance Data

Package

Each discipline or focus area is further decomposed into subsections associated with its individual SMA activities or deliverables, e.g., within Section 2.2, “Quality Management

System”, subsection 2.2.2 flows down the specific requirements for operating a “Material

Review Board.” In instances where the risk classification does not warrant the flow down of specific SMA process/product standards, that section or subsection has been identified as “not applicable,” and the developer is expected to apply their internal standards, without government oversight.

In this document, a specific requirement is denoted by “shall,” a good practice by “should,” permission by “may,” and an expectation by “will.”

The requirements in this document use the following identification convention:

SMA Discipline–Numeric Identifier

Ex. QMS_01

The key to the requirement identification is as follows:

SMA

Discipline

One of the following 3-character mnemonics associated with the corresponding SMA

Discipline/Focus Area:

• GEN – General SMA Requirements • EEE – EEE Parts

• QMS – Quality Management System • MAP – Materials and Processes

• SAF – System Safety • CON – Contamination Control

• REL – Reliability • MAC – Metrology and Calibration

• SWA – Software Assurance • GID – GIDEP Alerts and Problem Advisories

• WOR – Workmanship • EIA – End Item Acceptance Data Package

Numeric

Identifier A unique, sequential 2-digit number assigned to each requirement in the discipline/focus area viii

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Note: The contents of this Mission Assurance Requirements (MAR) document are the result of tailoring from a master set of requirements. Consequently, there may be instances where jumps or gaps occur in the numbering sequence of requirement IDs and DIDs. Due to the tailoring, there may also be sections that are not applicable, and have thus been marked “RESERVED.”

This is done intentionally to preserve the organization of the document and to facilitate tracking of data from implementation of requirements.

Requirements that have an associated Contract Data Requirements List (CDRL) item are denoted with the CDRL item number of MA x-y, where MA indicates a Mission Assurance CDRL item, x is the section referenced in this MAR document, and y is a sequential item number.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

1 GENERAL

1.1 Systems Safety and Mission Assurance Program

GEN_01: The developer shall implement a safety and mission assurance program that is consistent with contractual requirements. The mission assurance program shall cover:

• Flight hardware and software that is designed, built, or provided by the developer and its subcontractors or furnished by the government, from project initiation through launch and mission operations

• The ground support equipment that interfaces with flight items to the extent necessary to assure the integrity and safety of flight items

GEN_02: The developer shall submit a compliance matrix that identifies variance and acceptance rationale for processes, procedures, and standards that are proposed as alternatives to those specified by the contract (CDRL MA 1-1). This includes identification of requirements for which relief is requested via the Inherited Item Risk Assessment process (see Section 1.9 “Use of

Inherited Products/Items”).

1.2 Management

GEN_03: The developer shall designate a manager for all assurance activities. The assurance manager shall not be responsible for project costs and schedules other than those pertaining to assurance activities.

GEN_04: The developer shall ensure that the assurance manager has direct access to upper management that is independent of project management, with functional freedom and authority to interact with all elements of the project.

1.3 Requirements Flow down

GEN_05: The Developer shall ensure flow down of SMA requirements to all suppliers based on the work to be performed and establish a process to verify compliance, with the exception of those approved for relief via the Inherited Item Risk Assessment process (see Section 1.9 “Use of

Inherited Products/Items”).

GEN_06: The Developer’s contract review and purchasing processes shall indicate the method for documenting, communicating, and reviewing requirements with sub-tier suppliers to ensure requirements are met and information on discrepancy reports is communicated.

GEN_07: The Developer shall ensure that quality plans, processes, procedures, hardware, and software submitted by the Developer’s sub-tier suppliers are compliant with the requirements in this MAR and adequately communicated, as applicable.

1.4 Identification of Project-Level Critical Items (PCIs)

GEN_08: The Developer shall identify its critical items for incorporation into the Project-Level

Critical Items (PCIs) developed in accordance with NPR 8735.2, Section 4.1.4 “Critical Items and Processes Determination”.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

GEN_10: Identification of critical items and processes should include the results of system safety and reliability analyses.

1.5 Suspension of Work Activities

GEN_11: The developer shall direct the suspension of any work activity that presents an unsafe work condition to personnel or imminent danger to property.

1.6 Surveillance

GEN_12: The developer shall provide access to quality management system documentation, information systems and work products or artifacts to National Aeronautics and Space

Administration (NASA) representatives.

GEN_13: The work activities, operations, and documentation performed by the Contractor and sub-tier contractors or suppliers shall be subject to evaluation, review, audit, inspection, and survey by NASA representatives at various points over the program or project development lifecycle.

GEN_14: In accordance with Federal Acquisition Regulations (FAR) 46.103, 46.104, 46.202-2, 46.4, and 46.5, the developer shall grant physical or remote access to NASA representatives to conduct an on-site and/or remote audit, assessment, or inspection upon notice. A 30-day notice will be provided to the supplier or developer prior to the start of an audit or assessment. The supplier or developer shall supply personnel, documents, records, equipment, and an acceptable work area within the developer’s facilities to assist with the audit, assessments, or inspections.

GEN_15: The developer shall report the status of facility operations and quality metrics to

NASA on a quarterly basis. This should include the following data for 1st tier and 2nd tier suppliers of project-defined critical items:

• Quality escapes - Any product released by an internal or external supplier that is subsequently determined to be nonconforming to contract and/or product specification requirements.

• First Pass Yield - A measure of quality in a process that reflects the percentage of product made correctly without any rework or corrective activity.

• Supplier Defect Rate - The supplier defeat rate measures the percentage of materials or product received from suppliers that do not meet required or compliance specifications.

• Internal Audit results

1.7 Government Mandatory Inspection Points (GMIPs)

GEN_16: For firm fixed price projects, the developer shall provide a proposed GMIP plan, which will be used by the government in determining the final GMIPs that will be conducted.

NASA Procedural Requirements (NPR) 8735.2 “Hardware Quality Assurance Program

Requirements for Programs and Projects” may be used as a guide.

Typical GMIPs include:

a. Inspect Circuit Card Assemblies (CCAs), harnesses, connectors, etc. prior to staking/conformal coating process (solder, crimps, handling, and overall workmanship).

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

b. Inspect CCAs for proper staking and conformal coating.

c. Pre-Cap inspection of Hybrid Components

d. Perform a pre-closure inspection of flight components (e.g., box, subsystem, structure) prior to the start of acceptance testing for configuration verifications and general mechanical and electrical workmanship.

e. Inspect flight harnesses for compliance to NASA-STD-8739.4

f. Review of purchase orders and statements of work on components/subsystem elements for proper requirements flow-down

g. Packaging, packing, shipping, and storage of flight products pre-shipment, and receiving of Government Furnished Equipment (GFE).

h. Witness and verify fastener torquing involving flight hardware.

i. Witness and inspect mates and de-mates of all flight connectors.

j. Verify test setups.

k. Witness and inspect any additional items or processes identified by the Government as areas of concern due to perceived risk.

GEN_19: Prior to the start of manufacturing, the developer shall provide work instructions, procedures, drawings, etc. that are required for performing the planned inspections.

1.8 List of Suppliers

GEN_20: The developer shall track suppliers used for product produced under this contract.

1.9 Use of Inherited Products/Items

GEN_21: For Inherited Products/Items, defined as those that will be build-to-print (BTP), or rebuilt with modification, or are available as commercial-off-the-shelf (COTS), or were previously developed and exist (e.g., spares), the developer may propose to follow the processes documented in GPR 8730.5 “Safety and Mission Assurance Acceptance of Inherited and Build-to-Print Products”.

Use of this process does not relieve the developer from meeting contractual performance and functional requirements for the Inherited Product.

1.10 Protection of Flight Hardware

GEN_22: The Developer shall evaluate the potential for Ground Support Equipment (GSE) to damage flight hardware and use appropriate means to prevent such damage from occurring.

GEN_23: The approach to obviate GSE damage to flight hardware shall be presented prior to the start of testing and at subsequent review milestones.

GEN_24: Prior to performing work on flight hardware, the performing organization shall identify a list of items, if any, that are sensitive to normal handling environments, such as presence of light, presence of metal objects (magnets), or presence of humidity outside of normal cleanroom and workmanship limits.

GEN_25: The Developer shall hold a meeting on the day work is to be performed, prior to the start of each shift, that includes a discussion of the list of items from GEN_24.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

1.11 Risk Management

GEN_26: SMA activities should be tightly linked with the project’s Risk Management processes. For example, risks that evolve from reliability analyses that affect overall mission objectives should be managed in the project’s risk database when not eliminated or mitigated to noncredible likelihood levels.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

2 QUALITY MANAGEMENT SYSTEM

2.1 General

QMS_01: The developer shall have a quality management system that is compliant with the requirements of Society of Automotive Engineers (SAE) AS9100 Quality Systems – Aerospace

– Model for Quality Assurance in Design, Development, Production, Installation and Servicing.

2.2 Supplemental Quality Management System Requirements

2.2.1 Control of Nonconforming Product

QMS_04: The developer shall have a documented closed loop system for identifying, reporting, and correcting product nonconformances that shall include sub-tier supplier discrepancy reports.

The system shall ensure that the adequacy of corrective action is determined by audit, inspection, or test, that objective evidence is collected, and that preventive action is implemented to preclude recurrence.

2.2.2 Material Review Board (MRB)

QMS_06: The Developer shall have a documented process(es) for the establishment and operation of an MRB to process major non-conformances, which are those that affect form, fit, function, require a software change, involve the presence of Foreign Object Debris (FOD), affect the reliability, or safety of the end item, where a contractual requirement is violated, or those that the Government or developer determines involve elevated risk.

QMS_07: The Developer shall appoint a MRB chairperson who is responsible for implementing the MRB process and for appointing Developer representatives as MRB members.

QMS_09: The MRB process shall include a government representative as a participating member on MRB actions involving major nonconformances.

QMS_11: The government shall be provided notice and applicable documentation 24 hours in advance of scheduled MRB meetings.

QMS_12: The Developer shall inform the Government of MRB actions (CDRL MA 2-2).

QMS_13: The MRB shall use the following disposition actions:

• Scrap — the product is not usable

• Re-work/Re-test — the product will be re-worked/re-tested to conform to requirements

(sometimes referred to as “return to print”)

• Return to supplier — the product will be returned to the supplier

• Repair — the product will be repaired

• Use as is — the product will be used as is

2.2.3 Anomaly Reporting and Disposition

QMS_14: The developer shall have a documented process for the establishment and operation of an anomaly review board (ARB) to process (report and disposition) major anomalies, which are those that have resulted in hardware or software test failures and damage or potential damage to

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

hardware, require a software change, affect safety or where there is a violation of a Government requirement.

QMS_16: Reporting of major anomalies shall begin with the first application of power at the component or board level, flight software acceptance testing and when interfacing with flight hardware, and the first mechanical operation.

QMS_19: The ARB (or equivalent function) shall permit a government representative to be a participating member.

QMS_20: The government shall be provided notice of major anomalies and applicable documentation in advance of scheduled ARB meetings.

QMS_21: Failures that cannot be duplicated, have unknown root cause, or cannot be verified shall be assessed for residual risk, declared as red flag problem failure records (PFRs), and brought to the project risk board for disposition.

2.3 Orbital Debris Assessment Report (ODAR) and End of Mission Plan (EOMP)

QMS_22: The developer shall provide the information necessary for the development of the

ODAR and the EOMP deliveries per the content defined in NASA-STD 8719.14 Process for

Limiting Orbital Debris (CDRL MA 2-1).

Note: This is input to the Observatory ODAR and EOMP, and not the report and plan themselves which the Project will provide.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

3 SYSTEM SAFETY

3.1 General

SAF_01: The developer shall document and implement a system safety program, support the

Expendable Launch Vehicle (ELV) Safety Review Process as defined in Chapter 3 of NPR

8715.7 Payload Safety Program, comply with launch service provider requirements, and comply with launch range safety requirements.

SAF_02: The developer shall include the following specific safety requirements in the system safety program:

• The developer shall ensure three independent inhibits in the design (dual failure tolerant) if a system failure may lead to a catastrophic hazard. A prelaunch catastrophic hazard is a payload-related hazard, condition, or event occurring prior to launch that could result in a fatal injury to personnel or loss of a ground facility. A post-launch catastrophic hazard is a payload-related hazard, condition, or event occurring after launch and up to payload separation that could result in a fatal injury or loss of flight termination system.

• The developer shall ensure two independent inhibits in the design (single failure tolerant) if a system failure may lead to a critical hazard. A critical hazard is defined as a hazard, condition or event that may cause severe injury or occupational illness or major property damage to facilities.

• The developer shall adhere to specific detailed safety requirements, including compliance verification that must be met for design elements with hazards that cannot be controlled by failure tolerance. The process by which safety is incorporated into these design elements (e.g., structures and pressure vessels) is called "Design for Minimum Risk."

3.2 Mission Related Safety Requirements Documentation

SAF_03: The developer shall implement the launch range safety requirements that are applicable to the selected launch site. The developer shall implement the most stringent safety requirement in the event there are conflicting requirements. The sections below include the applicable requirements documents for the likely launch range (Requirements to be provided if another range is selected):

SAF_04: ELV Eastern Test Range (ETR) or Western Test Range (WTR) Missions:

• NASA-STD 8719.24 (with Annex) NASA Expendable Launch Vehicle Payload

Safety Requirements

• KNPR 8715.3 KSC Safety Practices Procedural Requirements (applicable at KSC property, KSC-controlled property, and offsite facility areas where KSC has operational responsibility)

• NPR 8715.7 Expendable Launch Vehicle Payload Safety Program

• Launch Site Facility-specific Safety Requirements, as applicable (e.g., Astrotech)

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

3.3 System Safety Deliverables

3.3.1 System Safety Plan

SAF_10: The developer shall prepare a System Safety Plan (SSP) that describes the tasks and activities of system safety management and engineering required to identify, evaluate, and eliminate or control hazards to the hardware, software, and system design by reducing the associated risk to an acceptable level throughout the system life cycle, including launch range safety requirements (CDRL MA 3-1).

3.3.2 Safety Requirements Compliance Checklist

SAF_11: The developer shall document and implement a Safety Requirements Compliance

Checklist to demonstrate that the payload complies with NASA and range safety requirements

(CDRL MA 3-2).

3.3.3 Instrument Safety Assessment Report (ISAR)

SAF_22: The developer shall generate an ISAR to document the comprehensive evaluation of the risk being assumed prior to the testing or operation of an instrument (CDRL MA 3-4). The spacecraft developer will use the ISAR as an input to the Safety Data Package (SDP).

3.3.4 Hazard Analyses

3.3.4.1 Preliminary Hazard Analysis

SAF_15: The developer shall perform a Preliminary Hazard Analysis (PHA) to obtain an initial risk assessment and to identify safety critical areas of a concept or system. The PHA is based on the best available data, including mishap data from similar systems and other lessons learned.

SAF_16: The developer shall evaluate hazards associated with the proposed design or function for severity, control approach (fault tolerance or design for minimum risk), and operational constraints. The developer shall identify safety provisions and alternatives that are needed to eliminate hazards or reduce their associated risk to an acceptable level.

SAF_17: The developer shall deliver the PHA with a Preliminary ISAR (CDRL MA 3-4).

3.3.4.2 Operations Hazard Analysis (OHA) and Hazard Verification Tracking Log (HVTL)

SAF_18: The developer shall perform hazard analysis to ensure that hardware operations, test equipment operations, and integration and test (I&T) activities comply with the safety requirements of the facilities where the activities will be performed and that hazards associated with those activities are mitigated to an acceptable level of risk.

SAF_19: The developer shall update and maintain the Hazard Verification Tracking Log during

I&T activities to track open issues.

3.3.4.3 Operating and Support Hazard Analysis

SAF_20: The developer shall perform an Operating and Support Hazard Analysis (O&SHA) to evaluate activities for hazards introduced during testing, transportation, storage, integration, and prelaunch operations at the launch site. The primary purpose is to evaluate the adequacy of procedures used to eliminate, control, or mitigate identified hazards so as to ensure

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

implementation of safety requirements for personnel, procedures, and equipment during activities at the launch site.

SAF_21: The developer shall submit the results of the O&SHA as a part of the Intermediate &

Final ISARs (DID 3-4).

3.3.5 Verification Tracking Log (VTL)

SAF_22: The developer shall document and implement a VTL that documents a Hazard Control and Verification Tracking process as a closed-loop system that ensures safety compliance has been satisfied per applicable launch range safety requirements.

SAF_23: The developer shall document in the VTL the process of verifying the control of hazards by test, analysis, inspection, similarity to previously qualified hardware, or any combination of these activities.

SAF_24: The developer shall ensure that verifications listed on the hazard reports refer to specific test, analysis, or inspection reports with a summary of the pertinent results.

SAF_25: The developer shall make the results of the tests, analyses, and inspections from

SAF_24 available for government review.

SAF_26: The VTL shall identify hazard controls that are not verified as closed and shall be delivered with the final ISAR (CDRL MA 3-4).

SAF_27: The developer shall provide regular electronic updates of the VTL until all hazard controls are verified as closed.

3.3.6 Hazardous Procedures for Payload I&T and Pre-launch Processing

SAF_28: The developer shall document the hazardous procedures that will be implemented when integration and test activities and pre-launch activities are performed at processing facilities and the launch site.

SAF_29: The developer shall ensure that the hazardous procedures comply with applicable facility safety requirements.

SAF_30: The developer shall provide safety support for the implementation of hazardous procedures.

3.3.7 Lifting Device Safety Requirements

A Critical Lift is defined as a lift during which failure/loss of control presents an elevated risk of serious injury, loss of life, or loss of one-of-a-kind articles, or high dollar items, whose loss would have serious programmatic or institutional impact.

SAF_31: The developer shall implement the following safety requirements for Lifting Devices and Equipment (LDE) when performing NASA work at non-NASA facilities:

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

• Overhead cranes, winches, and wire rope hoists shall have a dual hoist braking system installed per the NASA STD 8719.9 (Lifting Standard), Sections 5.4 and 7.4.

Chain hoists typically do not have dual brakes as standard equipment unless included in the manufacturer’s design when specifically requested by the user. A single hoist motor holding brake in combination with a Variable Frequency Drive (VFD) dynamic braking system is an acceptable dual braking system.

• Label and tag LDE per the NASA STD 8719.9B, Section 4.9 requirements with no more than its Working Load Limit (WLL) as determined by the original equipment manufacturer (OEM) or its current certified WLL if that value is lower than the OEM rated WLL.

• Perform an initial one-time proof load test per the following NASA STD 8719.9B, Section 4.5 requirements:

• 1.25X WLL for overhead cranes.

• 1.25X WLL for mobile aerial platforms that will be used near critical hardware.

• 1X WLL for mobile cranes and derricks (.95X to 1X is acceptable).

• 1.25X WLL for Below-The-Hook (BTH) lifting devices.

• Slings (i.e., wire rope, synthetics, chain, etc.,) should only be proof load tested beyond its WLL with OEM approval.

• 2X WLL for rigging hardware items used for critical lifts (i.e., shackles. hoist rings. turnbuckles, etc.).

• Perform a 1X WLL load test every four years after the initial proof test on all LDE.

• In addition to visual inspection, perform a post load test NDT inspection (e.g., radiographic, ultra-sonic, magnetic particle, dye penetrant, etc.) on crane hooks and critical welds. A critical weld is one in which a failure would result in a failure of the hardware. The inspections will be performed by an American Society of Non-destructive Testing (ASNT) or equivalently trained inspector."

3.3.8 Mishap Reporting and Investigation

SAF_32: The developer shall have a plan that describes appropriate mishap and close call notification, reporting, recording, and investigation procedures.

SAF_33: The developer shall report accidents, test failures, or other mishaps and close calls promptly (within 24 hours) to NASA.

SAF_34: The developer shall promptly investigate test failures, or other mishaps and close calls to determine the root cause of the mishap/close call.

3.3.9 NASA ELV Payload Safety Program Forms

SAF_35: The developer shall prepare NASA Expendable Launch Vehicle Payload Safety

Forms. The forms are available at URL https://kscsma.ksc.nasa.gov/PayloadSafety/forms.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

4 RELIABILITY

4.1 Reliability Program

REL_05: The developer should perform reliability analyses concurrent with design so that identified problem areas are addressed, and corrective action taken in a timely manner.

4.2 Analysis of Design

4.2.1 FMECA and Critical Items List (CIL)

REL_11: The developer shall perform and maintain Failure Modes and Effects Criticality

Analyses (FMECA) that address flight hardware and software and ground support equipment that interfaces with flight systems that are being designed, built, or provided from project initiation through launch and mission operations. The developer shall include likelihood, cause, detection and mitigation, and the effects of each failure mode at the local, subsystem, and system or mission levels. Components and systems designated as inherited items shall be analyzed at the interface level. All others shall be analyzed at the box or functional level. (CDRL MA 4‑2).

REL_12: The developer shall prepare and maintain a Critical Items List for items with failure-mode severity categories 1SC (Safety Critical), 1, 1R (Redundant), 1S (Safety), and 2 per Table

4.1.

Table 4.1 Severity Categories

C ri ti ca li ty

Category Description

S P

F s

C ri ti ca l

1SC

Failure modes that could cause a catastrophic event such as the loss of life, permanently disabling injury to personnel, or facility loss/destruction.

Failure modes that could result in mission loss or minimum mission success criteria not being achievable.

1S Failure modes that could prevent detection of or operations during a hazardous condition resulting in 1SC conditions, eliminate a hazard inhibit, or cause severe injury, occupational illness, or major property damage.

1R Failure modes of identical or equivalent redundant hardware items that, if all failed, could result in category 1/1SC effects.

Failure modes that could result in loss of one or more mission objectives, including the significant loss of data, functionality, or a significant reduction in life of the mission. Minimum mission success criteria are still achievable.

S ig n if ic an t

2R Failure modes of identical or equivalent redundant hardware items that could result in Category 2 effects if all failed.

Significant failure modes that could cause degradation to full mission objectives and still meet minimum mission.

M in o r

Minor Failure modes that could result in insignificant or no loss to mission objectives.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

REL_13: The developer shall prepare and maintain a Single Point Failure (SPF) list for modes resulting in category 1 and 1SC severities per table 4.1 and document applicable failure causes, mitigations, and retention rationale.

REL_14: The developer shall identify and assess any known common cause failure modes and their causes for category 1R and 2R items. This shall be included and maintained in CDRL MA

4-2.

REL_15: The developer shall estimate the likelihood score for each failure mode from 1-5 using the appropriate criteria from GPR 7120.4 (shown in Table 4.2) or another scale approved by GSFC Reliability. Each likelihood estimation can be based on qualitative assessment and/or failure rate data from other analyses (e.g., system calculations) in order to score each failure mode for the mission duration. This should be included and maintained in CDRL MA 4-2.

Table 4.2 Likelihood Rankings

REL_16: The developer shall identify the consequence for each failure mode using the appropriate criteria from GPR 7120.4 (shown in Table 4.3). This should be included and maintained in CDRL MA 4-2).

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

Table 4.3 Consequence Rankings

4.2.2 Fault Tree Analysis (FTA)

REL_17: The developer shall perform qualitative fault tree analyses (FTA), as deemed necessary by the contractor.

REL_18: Fault trees shall address both hardware and software contributions at a level necessary to identify risks, verify mitigations, and assist in the development of fault management.

REL_19: In the event the developer or the project identifies a major mission risk contributor in the FMECA or FTA, the developer shall quantify (and if necessary, expand) the appropriate FTA or the portions of the FTA necessary for detailed risk assessment, as deemed necessary by the

CSO and the MSE.

REL_20: FTA should also be considered for use to check the FMECAs for completeness.

4.2.3 Reliability Calculations

REL_21: The developer shall perform and maintain reliability and availability calculations using

Fault Tree Analyses (FTA), reliability block diagrams, and/or Probabilistic Risk Assessment

(PRA) to identify design weaknesses, support design trades, and demonstrate the impact of critical items, as deemed necessary by the contractor.

4.3 Limited Life Analysis

REL_22: The developer shall perform and maintain Limited Life Item Analysis (LLA) that includes expected life, required life, and an assessment of life margin (including servicing and maintenance); provides retention rationale for items with an expected life of less than 2x the required life and fosters a plan to manage limited life items (CDRL MA 4-5).

REL_25: The risk assessment and mitigations plans shall be included in the LLA for items not meeting the 2X life requirement and shall factor in wear caused by atomic oxygen, solar and

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

trapped radiation, shelf-life, extreme temperatures, thermal cycling, write/erase cycles and mechanical wear or fatigue, and include refurbishment and maintenance plans.

4.4 Parts Stress Analysis

REL_26: The developer shall perform parts stress and derating analyses for electrical, electronic, and electromechanical (EEE) parts in accordance with GSFC EEE-INST-002

Instruction for EEE Parts Selection, Screening, Qualification, and Derating (CDRL MA 4-6) or the developer’s own established standard, unless specifically relieved of this requirement by the

GSFC Inherited Items Risk Assessment process (See Section 1.9).

REL_28: If alternate derating guidelines are requested to be used, they shall be submitted to the

Parts Control Board and GSFC Reliability Engineering for approval.

4.5 Worst-Case Analysis

REL_30: The developer shall perform Worst-Case Analyses (WCA) for circuit designs that are new or significantly modified or are being used in an environment not covered by the existing analysis and identified as critical through analysis of the design (See Section 4.2) (CDRL MA 4-

7).

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

5 SOFTWARE ASSURANCE

5.1 Software Assurance Program

SWA_01: The developer shall establish a software assurance program consisting of a planned and systematic set of activities and disciplines that ensures that software conforms to organizational and project-specific requirements and standards throughout the project lifecycle, where software is defined as:

• Computer programs, procedures, and possibly associated documentation and data pertaining to the operation of a computer system

• All or a part of the programs, procedures, rules, and associated documentation of an information processing system

• Program or set of programs used to run a computer

• All or part of the programs which process or support the processing of digital information

• Part of a product that is the computer program or the set of computer programs.

Note: The software definition applies to software developed by NASA, software developed for

NASA, software maintained by or for NASA, COTS, GOTS, MOTS, OSS, reused software components, auto-generated code, embedded software, software used on ground support equipment, the software executed on processors embedded in programmable logic devices, legacy, heritage, applications, freeware, shareware, trial or demonstration software, and open-source software components.

SWA_03: The developer shall ensure the independence of software assurance from software engineering.

SWA_04: The developer shall document and implement a Software Assurance Plan and schedule compliant to NASA-STD-8739.8B, NASA Software Assurance and Software Safety

Standard (CDRL MA 5-1).

The plan includes the software assurance processes, procedures, tools, and techniques to be used commensurate with the software classification and safety criticality assessment, with additional tailoring in accordance with guidance provided by NASA-STD-8739.8B for each category of software (new, reused, Off-the-shelf, auto-generated code, etc..).

The plan addresses both Software Assurance and Software Safety disciplines. This includes the necessary collaboration with relevant SMA and Engineering stakeholders (i.e., system safety, system reliability, hardware quality, system security, and software engineering), and the process by which traceability is established to their respective analyses and/or requirements.

5.2 Surveillance of Software Development, Maintenance, and Assurance Activities

SWA_08: Consistent with the general requirement for support of government surveillance (see

Section 1.6 "Surveillance"), the developer shall provide on-request access to following:

• Software problem reports

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

• Software documentation (i.e., management plans, assurance plans, configuration management plans, requirements specifications, design documents, test plans, test cases, test procedures, test results, software review results, software engineering and assurance schedule, and maintenance plans)

• Source code

• Findings and corrective actions from software process and product audits and assessments

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

6 WORKMANSHIP

6.1 General

WOR_02: The developer shall implement a workmanship program to assure that electronic packaging technologies, processes, and workmanship meet mission objectives for quality and reliability per the requirements of the following standards:

• NASA-STD-8739.6 Implementation Requirements for NASA Workmanship Standards, excluding sections 8.1, 9.1, and 10.1

• J-STD-001, Requirements for Soldered Electrical and Electronic Assemblies

• GSFC-STD-6001 Ceramic Column Grid Array Design and Manufacturing Rules for

Flight Hardware

• IPC-2225 Sectional Design Standard for Organic Multichip Modules (MCM-L) and

MCM-L Assemblies

• IPC-6015 Qualification and Performance Specification for Organic Multichip Module

(MCM-L) Mounting and Interconnecting Structures

WOR_04: The developer shall comply with one of the following standards for electrical cables and harnesses:

• NASA-STD-8739.4 Crimping, Interconnecting Cables, Harnesses, and Wiring

• IPC/WHMA-A-620 Requirements and Acceptance for Cable and Wire Harness

Assemblies

6.2 Electrostatic Discharge Control (ESD)

WOR_06: The developer shall prepare and implement an ESD control plan that conforms to the requirements of ANSI/ESD S20.20 "Protection of Electrical and Electronic Parts, Assemblies and Equipment (Excluding Electrically Initiated Explosive Devices)" or contractor equivalent.

6.3 Printed Circuit Boards (PCB)

WOR_08: The developer shall comply with one of the following standards for rigid printed circuit boards:

• IPC-6012 Qualification and Performance Specification for Rigid Printed Boards, Class 3

(the latest revision preferred, but older revisions acceptable based on inherited designs or developer standard practices)

• MIL-PRF-55110H Performance Specification: Printed Wiring Board, Rigid, General

Specification For

• ECSS-Q-ST-70-10 Qualification of Printed Circuit Boards

WOR_09: In cases in which high-density interconnect (HDI) components (e.g., reconfigurable

FPGAs, high-density SRAMs, etc.) or board population are present, the developer should consult with the GSFC Project and GSFC MPCB CRAE for a specification strategy to avoid extensive rebuilds or the incorporation of risky features solely in order to meet the spec. This consultation may result in deviations from the specifications above with no waiver required.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

WOR_12: For non-conforming coupons, the evaluation report shall be delivered to the GSFC

MPCB CRAE for a risk assessment. If the CRAE's risk assessment determines that there is no elevated risk, no waiver is required and the CSO will determine the disposition of the board.

6.4 Lead-Free Control Measures

WOR_17: The developers shall submit uses of lead-free solder or surface finishes to the NASA project office for approval before use.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

7 EEE PARTS

7.1 General

EEE_02: The developer shall document and implement a Parts Control Plan (PCP) per Level 3 instructions of GSFC EEE-INST-002 Instruction for EEE Parts Selection, Screening, Qualification, and De-rating (CDRL MA 7-1).

Note: The developer may use as is Class V, S, Q, B, M compliant microcircuits; JANS, JANTXV, and JANTX semiconductors without any further approval.

Note: The developer may use as is automotive or hi-rel commercial off the shelf (COTS) parts, compliant to level 3 per NASA-STD-8739.10 without any additional screening or qualification tests without any further approval.

7.2 Parts Control Board

EEE_07: The developer shall establish a Parts Control Board (PCB) that is responsible for the planning, management, and coordination of the selection, application, and procurement requirements of EEE parts.

EEE_10: The developer shall identify the person responsible for directing and managing the

EEE parts program and interfacing with government assurance personnel.

EEE_13: The developer shall include the GSFC Parts Engineer and the Parts and Radiation

Assurance Engineer (PRAE) as participating members of the PCB.

7.3 Re-use of EEE Parts

EEE_15: The developer shall require approval of the PCB to re-use EEE parts that have been installed.

7.4 Master EEE Parts List

EEE_16: The developer shall develop and deliver a Master EEE Parts List in accordance with

CDRL MA 7-2 and maintain it for the duration of the project.

7.5 Radiation Effects Mitigation

EEE_19: The developer shall provide a plan, for approval, for how radiation will be addressed

(CDRL MA 7-3).

EEE_20: The developer shall provide a radiation and shielding analysis to ensure that all instrument parts will be compatible with the expected space radiation environment for the required mission life and to determine whether the instrument radiation shielding is adequate to protect the instrument electrical and optical parts from excessive degradation due to radiation

(CDRL MA 7-4).

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

8 MATERIALS AND PROCESSES

8.1 M&P Selection, Control, and Implementation Plan (MPCIP)

MAP_01: The developer shall implement a Materials and Processes (M&P) Selection, Control, and Implementation Plan (MPCIP). NASA-STD-6016 shall be used as a baseline, with developer standard practices acceptable if associated command media are shared with NASA.

8.2 Materials Identification and Usage List (MIUL)

MAP_04: The developer shall prepare a materials identification and usage list (CDRL MA 8-3).

8.3 Life Test Plan for Lubricated Mechanisms

MAP_05: The developer shall implement a life test plan for lubricated mechanisms.

8.4 Additive Manufacturing Control Plan (AMCP)

MAP_06: The developer shall implement an Additive Manufacturing Control Plan (AMCP) for the design and manufacture of Additively Manufactured (AM) if AM parts will be used.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

9 CONTAMINATION CONTROL

9.1 Contamination Control Plan

CON_01: The developer shall implement a contamination control program.

9.2 Material Outgassing

CON_03: The developer shall include in CDRL MA 8-3 (MIUL) information regarding material outgassing.

CON_04: If an alternate standard to NASA-STD-6016 "STANDARD MATERIALS AND

PROCESSES REQUIREMENTS FOR SPACECRAFT " is implemented, materials shall meet requirements of < 1% total mass loss (TML) and < 0.1% collected volatile condensable material

(CVCM) at 125C under vacuum for twenty-four hours when tested to ASTM E595 Standard Test

Methods for Total Mass Loss and Collected Volatile Condensable Materials from Outgassing in a Vacuum Environment.

9.3 Foreign Object Debris Program

CON_05: The developer shall implement a foreign object debris program.

Check the SOLAR CM tool Server at https://ipdtdms.gsfc.nasa.gov/frontmenu dsp.cfm to verify that this is the correct version prior to use.

10 METROLOGY AND CALIBRATION

10.1 Metrology and Calibration Program

MAC_01: For measurement and test equipment that has documented requirements for metrological accuracy and traceability, the developer shall comply with NASA-STD-8739.12

"Metrology and Calibration", or verify equipment against calibrated instruments or intrinsic standards, using a documented procedure.

Note: The developer may verify torque wrenches against a calibrated torque tester prior to use.

10.2 Use of Calibrated and Non-Calibrated Instruments

MAC_02: The developer shall record the measurements that require accuracy in applicable project build documents (e.g., Work Order Authorizations (WOAs), job orders, task sheets or test plans), including the article of calibrated equipment used to take the measurement and its calibration end…