Final Attach H.pdf
PDF 77 KB Posted
- Attached to
- Request for Proposal Geostationary Extended Observations (GeoXO) Sounder (GXS) Instrument Implementation
- Solicitation number
- 80GSFC22R0055
About this file
This document contains requirements for a financial management reporting attachment to a federal contract. The contractor must submit NASA Form 533 reports monthly and quarterly containing labor hours and costs by labor category and elements of direct, overhead, and other direct costs. Variances over 10% between estimated and actual labor hours and costs require a narrative explanation. Reports are due to addresses indicated in the contract clause by the 10th day after the monthly period and 15th day before the quarter. Data must include prime and subcontractor direct labor hours by category, direct labor costs by category, overhead expenses, subcontract costs by vendor, material costs, travel costs, and other direct costs. General and administrative expenses, provisionally billed award fees, award fees earned, and total cost-plus-award-fee must also be reported.
The related federal contract opportunity is a request for proposal to implement the Geostationary Extended Observations Sounder instrument for the GeoXO program. The scope includes design, analysis, development, fabrication, integration, calibration, testing, verification, evaluation, launch support, and 10 years of operations and 5 years of on-orbit storage for each flight model. The contract type will be cost-plus-award-fee. A draft RFP is expected in December 2022 with questions due 15 days after, and a final RFP in January-February 2023. The anticipated award date is late August 2023. The NAICS code is 541330 with a size standard of $22.5M.
View the file
Other files
Show 40 more
Latest 50 of 67 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT H
FINANCIAL MANAGEMENT REPORTING
REQUIREMENTS
RFP 80GSFC22R0055
CONTRACT TBD
Contract TBD
Attachment H
(06/2014) 2
FINANCIAL MANAGEMENT REPORTING REQUIREMENTS
Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA
Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial
Management Reporting,” dated May 27, 2011, and additional instructions issued by the
Contracting Officer.
a. Level of Detail
The Contractor’s 533 Reports shall contain a summary of total contract costs, for Work
Breakdown Structure (WBS) Level 1element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in
Section d below.
b. Variance Narrative Reporting
In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the
Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total
Cost amount shown in the current month at the total contract level. (For example, the
Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the
Actual June Total Cost amount shown in column 7a in the June NF 533M.)
Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the
Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.
c. Distribution
The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.
After the initial report, the NF 533M reports shall be distributed not later than the tenth
(10th) working day following the close of the contractors' monthly accounting period.
The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.
d. Reporting Requirements
Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:
(06/2014) 3
1. Prime Direct Labor Hours:
(List applicable labor categories)
Total Prime Direct Labor Hours
2. Subcontractor Direct Labor Hours:
Subcontractor A Direct Labor Hours
Subcontractor B Direct Labor Hours
Subcontractor C Direct Labor Hours
Total Subcontractors Direct Labor Hours
3. Total Prime and Subcontractors Direct Labor Hours
4. Prime Direct Labor Costs:
Total Prime Direct Labor Costs
5. Prime Overhead Expense
6. Other Direct Costs (ODCs):
a. Subcontracts (list separately, Subcontractor A, B, C, etc.)
b. Material
c. Travel
d. Other (specify)
Total ODCs
7. Subtotal (Direct Labor, Overhead & ODCs)
8. G&A Expense
9. Total Estimated Cost
(06/2014) 4
10. Provisionally Billed Award Fee
11. Award Fee Earned
12. Total Cost-Plus-Award-Fee (CPAF)