This document provides details for a forthcoming request for proposal for the implementation of the Geostationary Extended Observations Sounder instrument. The National Aeronautics and Space Administration Goddard Space Flight Center plans to issue an RFP for the design, development, integration, testing, evaluation, launch support, and 15 years of operations and storage for one flight model of the instrument, with options for an additional flight model and a flight spare. Responses to the anticipated December 2022 draft RFP will be due in January 2023, with contract award expected in late August 2023. The North American Industry Classification code is 541330, with a size standard of $22.5 million. The contract type will be cost-plus-award-fee, covering a period of performance that includes 10 years of on-orbit operations and 5 years of on-orbit storage for each flight model.
View the file
Other files
Show 40 more
Latest 50 of 67 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: August 13, 2021 418-XO-GXSUIID-0030 Responsible Organization: GeoXO Flight Project/Code 418 Baseline Version 1.6a
To verify the correct version of this document, please contact the GeoXO Series Configuration Management Office.
Geostationary Extended Observations (GeoXO) Sounder (GXS)
Unique Instrument Interface Document (UIID) Signature page
Prepared by:
Electronically approved by: 04/23/2021
Nicolaas du Toit Date GeoXO Flight Project, Instrument Systems Engineer NASA GSFC, Code 418
Reviewed by:
Electronically approved by: 04/12/2021
Alexander Krimchansky Date GeoXO Flight Project, Mission Systems Engineer NASA GSFC, Code 599
Approved by:
Electronically approved by: 04/20/2021
Jason H. Hair Date GeoXO Flight Project, Project Manager NASA GSFC, Code 418
Effective Date: August 13, 2021 418-XO-GXSUIID-0030
To verify the correct version of this document, please contact the GeoXO Series Configuration Management
Document Change Record (DCR)
CCR GeoXO#:X00012 Rev: Title: 418-XO-GXSUIID-0030: GeoXO Sounder UIID baseline Contract # N/A GeoXO S/C: GeoXO Effectivity: Instruments CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 04/20/2021 Doc Version: 1.0 Contract Mod#: N/A DOORs Version: 1.0 Doc Change Date: April 20, 2021 DOORs ID #: 1.0
CCR GeoXO#:X00018 Rev: Title: GXSUIID: Updates for phase A Contract # N/A GeoXO S/C: GeoXO Effectivity: Instruments CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 08/13/2021 Doc Version: 1.1 Contract Mod#: N/A DOORs Version: 1.1 Doc Change Date: Aug. 13, 2021 DOORs ID #: Modify: GXSUIID41 (1.2.2.0-1), 43 (1.2.3.0-1), 45 (1.2.4.0-1), 58 (1.3.5.0-1), 66 (1.4.1.0-1), 68 (1.4.2.0-1), 86 (1.4.5.0-1), 114 (1.3.5.0-2) Add: GXSUIID115 (1.4.5.0-2)
CCR GeoXO#:X00044 Rev: A Title: GXSUIID: Changes for phase A Contract # N/A GeoXO S/C: GeoXO Effectivity: Instruments CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 11/16/2021 Doc Version: 1.2 Contract Mod#: N/A DOORs Version: 1.2 Doc Change Date: Nov. 16, 2021 DOORs ID #: Modify: GXSUIID27 (3.0-1), 30 (3.1.1.0-1), 35 (3.1.4), 36 (3.1.4.0-1), 39
(3.2.1.0-1), 58 (3.3.5.0-1), 114 (3.3.5.0-2), 63 (3.4), 66 (3.4.1.0-1), 69 (3.4.2.0-2), 71 (3.4.3.0-1), 72 (3.4.3.0-2), 86 (3.4.5.0-1), 88 (3.4.6.0-1), 89 (3.4.6.0-2), 115 (3.4.5.0-2), 103 (6.1.0-1), 104 (6.1.0-2), 105 (6.2), 106 (6.2.0-1), 107 (6.2.0-2), 108 (6.2.0-3), 109 (6.2.0-4), 110 (6.2.0-5), 111 (6.2.0-6), 113 (7.0-1), 115 (3.4.5.0-2), 117 (3.3.6)
Add: GXSUIID118 (1), 119 (1.0-1), 120 (1.0-2), 121 (1.0-3), 122 (1.0-4), 123 (1.0-5), 124 (1.0-6), 125 (1.1), 126 (1.1.0-1), 127 (1.2), 128 (1.2.0-1), 129 (1.2.0-2), 130 (1.2.0-3), 131 (1.2.0-4), 132 (1.2.0-5), 133 (1.2.0-6), 134 (1.2.0-7), 135 (1.2.0-8), 136 (1.2.0-9), 137 (1.2.0-10), 138 (1.2.0-11), 139 (1.2.0-12), 140 (1.3), 141 (1.3.0-1), 142 (2), 143 (2.1), 145 (2.1.0-1), (144 (2.2), 146 (2.2.0-1), 117 (3.3.6), 147 (3.3.6.0-1), 148 (3.3.6.0-2), 116 (3.4.7), 149 (3.4.7.0-1);
Delete: GXSUIID105 (6.2), 106 (6.2.0-1), 107 (6.2.0-2), 108 (6.2.0-3), 109 (6.2.0-4), 110 (5.2.0-5), 111 (6.2.0-6), [replaced original text with “Reserved’; DI retains for potential future use;]
CCR GeoXO#:X00083 Rev: Title: GXSUIID: Instrument Volume and other Contract #: 80GSFC21CA023 80GSFC21CA024 GeoXO S/C: GeoXO Effectivity: None CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 6/13/2022 Doc Version: 1.3 Contract Mod#: 8 DOORs Version: 1.3 Doc Change Date: June 22, 2022 DOORs ID #: Modify: GXSUIID49 (3.3.1.0-1), 54 (3.3.3.0-1), 56 (3.3.4.0-1), 113 (7.0-1), 129 (1.2.0-2), 131 (1.2.0-4), 132 (1.2.0-6), 133 (1.2.0-7), 134 (1.2.0-8), 135 (1.2.0-9), 136 (1.2.0-10), 137 (1.2.0-11), 138 (1.2.0-12), 147 (3.3.6.0-2), 148 (3.3.6.0-2)
Add: Insertion after GXSUIID150 (3.3.3.0-2), 151 (1.0-2), 152 (1.2.0-5)
CMO note: GXS instrument is awarded, contract numbers and contract mod are added in the Contract # and Contract Mod fields.
CCR GeoXO#:X00130 Rev: Title: GXSUIID: Instrument Volume Update Contract #: 80GSFC21CA023 80GSFC21CA024 GeoXO S/C: GeoXO Effectivity: None CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 10/17/2022 Doc Version: 1.4
Effective Date: August 13, 2021 418-XO-GXSUIID-0030
To verify the correct version of this document, please contact the GeoXO Series Configuration Management
Contract Mod#: 12, 13 DOORs Version: 1.4 Doc Change Date: Oct. 28, 2022 DOORs ID #: Modify: GXSUIID54 (3.3.3.0-1), 149 (3.4.7.0-1), 150 (3.3.3.0-2)
CCR GeoXO#:X00144 Rev: Title: GXSUIID: TBR deletions Contract #: GeoXO S/C: GeoXO Effectivity: None CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 12/06/2022 Doc Version: 1.5 Contract Mod#: N/A DOORs Version: 1.5 Doc Change Date: Dec. 06, 2022 DOORs ID #: Modify: GXSUIID49 (3.3.1.0-1), 54 (3.3.3.0-1), 92 (3.6), 94 (3.6.0-1), 150
(3.3.3.0-2)
CM note: bypassed Contract Negotiation due to GXS Implementation Phase B RFP Proposal.
CCR GeoXO#:X00154 Rev: Title: GXSUIID: Deletion of Radiated Emission Contract #: GeoXO S/C: GeoXO Effectivity: None CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 01/25/2023 Doc Version: 1.6 Contract Mod#: N/A DOORs Version: 1.6 Doc Change Date: Jan. 25, 2023 DOORs ID #: Modify: GXSUIID102 (6.1), 103 (6.1.0-1), 104 (6.1.0-2)
CM note: bypassed Contract Negotiation due to GXS Implementation Phase B RFP Proposal.
CCR GeoXO#:X00172 Rev: Title: GXSUIID: Update GIRD reference Contract #: GeoXO S/C: GeoXO Effectivity: None CCB Status: Approved Doc #: 418-XO-GXSUIID-0030 CCB Date: 02/27/2023 Doc Version: 1.6a Contract Mod#: N/A DOORs Version: 1.6a Doc Change Date: Feb. 27, 2023 DOORs ID #: Modify: GXSUIID145 (2.1.0-1)
CM note: CM admin change to correct the reference to the GIRD.