Attachment O GXS WBS dictionary.pdf

PDF 332 KB Posted

Attached to
Request for Proposal Geostationary Extended Observations (GeoXO) Sounder (GXS) Instrument Implementation
Solicitation number
80GSFC22R0055
Issued by

About this file

This document provides the Contractor Work Breakdown Structure (CWBS) and CWBS dictionary for the Geostationary Extended Observations (GeoXO) Flight Project Sounder (GXS) instrument implementation contract. The contract scope includes tasks to design, develop, fabricate, integrate, calibrate, test, verify, evaluate, support launch, and maintain ground support equipment for one flight model GXS instrument and two options for an additional flight model and spare. The anticipated period of performance is 15 years for on-orbit operations and storage for each flight model. The solicitation is expected to be released in late January to early February 2023 as a full and open competition with a Cost-Plus-Award-Fee contract type. The contract award date is anticipated for late August 2023.

View the file

Other files

File Type Posted
GXS RFP Cost Exhibits Amendment 1.pdf PDF
Amendment 1 Attachment D GXSUIID.pdf PDF
Amendment 1 Attachment E IMAR.pdf PDF
Amendment 1 Cover page - SF 30.pdf PDF
Amendment 1 - Continuation pages.pdf PDF
Final RFP 80GSFC22R0055 Questions and Responses 2.23.23.pdf PDF
Final Attach R.pdf PDF
Final GXS RFP Cost Exhibits Feb 2023.pdf PDF
Final Attachment A SOW.pdf PDF
Final Attachment B PORD.pdf PDF
Final Attach K SB plan.pdf PDF
GXS 80GSFC22R0055 Final .pdf PDF
Final Attachment M IT ADL.pdf PDF
Final Attach J.pdf PDF
Final Attachment E IMAR.pdf PDF
Final Attachment G EDM.pdf PDF
Final GXS RFP Cover Letter 1.pdf PDF
Final Attachment W OCI Plan.pdf PDF
Final Attach H.pdf PDF
Final Attach V.pdf PDF
Final RFP SF33 GXS.pdf PDF
Final Encl A ITSMP.pdf PDF
Final Attachment D GXSUIID.pdf PDF
Final Attachment C GIRD.pdf PDF
Final Attachment N QASP.pdf PDF
Final Attachment I OCI DRD.pdf PDF
Final Encl B Perf Eval Plan.pdf PDF
Final Attachment F CDRL.pdf PDF
Final Attachment P.pdf PDF
Final Attachment X DEIA Plan.pdf PDF
Final Attach L.pdf PDF
Final RFP WBS Dic Rev.pdf PDF
Final Attach T DEIA DRD.pdf PDF
Final Attachment S CONOPS.pdf PDF
Final Attachment Q GRDDP.pdf PDF
Final Exhibit 8 PPQ.pdf PDF
Final Attachment U FPGA.pdf PDF
GXS Instrument DRFP Questions and Responses.pdf PDF
Attachment W - OCI Plan.pdf PDF
Enclosure A ITSMP TMPLT.pdf PDF
Attachment S GeoXO_ConOps.pdf PDF
Attachment B GXSPORD.pdf PDF
GXS DRFP 80GSFC22R0055 Final.pdf PDF
Attachment P GXS Rad Upwelling.pdf PDF
Attachment T DEIA Plan DRD.pdf PDF
Attachment R GeoXO REED.pdf PDF
Attachment G EDM.pdf PDF
Attachment V Req Statements List.pdf PDF
Attachment U GeoXO FPGA.pdf PDF
GXS DRFP Cover Letter.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Geostationary eXtended Observations

(GeoXO) Flight Project

Sounder (GXS)

Contractor Work Breakdown Structure

(CWBS)

November 16, 2022

Prepared by:

Heather Matthews

GeoXO Flight Deputy Project Manager/Resources

Approved by:

Candace Carlisle

GeoXO Flight Project Manager

Attachment O: Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary

1. DESCRIPTION / PURPOSE

The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance and provides a basis for uniform planning, reporting status, program visibility, and assignment of responsibilities. Additionally, the CWBS provides a product-oriented logical subdivision of hardware, software, services, facilities, etc., that contribute to and/or make up the total project scope of effort and work. The CWBS dictionary provides a narrative description of the work tasks and effort to be performed in each CWBS element.

2. PREPARATION INFORMATION

Contents:

The CWBS and CWBS dictionary are two distinct project documents used for defining the approved project scope of work. The contents of each document are detailed in the following paragraphs:

CWBS – A logical, hierarchical display of the subdivision of all project work to be completed.

The CWBS shall include the approved element title and element number.

CWBS dictionary – The CWBS dictionary shall briefly describe and document the work content of every CWBS element and relevant efforts associated with each element (e.g., design, development, and manufacturing).

The CWBS levels shall be governed by the Following. The actual letter and number designations can be adapted to meet the needs of the Contractor’s systems

Level 1 - Total contract effort

Level 2 Definitions: Major contract activity as described below

A. Engineering Unit / Non-Recurring Activities – All effort to plan and manage the design of the instrument including detailed design activities, design reviews, risk reduction

(engineering models, etc), software development, GSE development, verification planning, etc.

B. Flight Model (FM) -1 – All effort related to fabrication, assembly, test, launch operations and on-orbit testing of the satellite

C. FM-2

D. FM-3

E. Special Tasks – all un-issued special task funds remain in this level 2 WBS

F. Mission Operations - Long term mission support including any management, business management support, systems engineering etc that is not unique to a particular mission

Level 3 Definitions (Note: X denotes the Level 2 Contract Activity) – the work content as described is not necessarily all inclusive.

X.01 Program Management – Including program leadership, resource management, program planning (schedule), data management, configuration management, support for major design reviews

X.02 Systems Engineering - Including system engineering leadership, interface management (instrument, launch vehicle, ground), system specification definition and flow-down, verification planning, system level analysis and modeling

X.03 Mission Assurance - Including mission assurance leadership, quality engineering, subcontract surveillance, safety, reliability, parts and materials management

X.04 Hardware / Software – All subsystem hardware and software effort including parts and materials which should be accounted for in a separate line. Effort included in each level 2 WBS

X.05 Integration & Test - Including instrument baseline testing and environmental testing and post environment test activities including instrument packing and shipping.

X.06 Ground Support Equipment (GSE) – design, fabrication, procurement assembly, test and maintenance of electrical, mechanical GSE and mission simulation and GSE software

X.07 Post Delivery Support (PDS) – Any support required after the Pre-Ship Review/Pre-

Storage Review including satellite integration and testing and if needed storage costs or testing during storage prior to shipping to spacecraft vendor

X.08 Launch and Post Launch Testing– support for pre-launch planning, launch site support, support for mission unique or special launch services, launch-vehicle integration (spacecraft portion), and the first 6 months of post-launch testing prior to the handoff to NOAA.

X.09 Special Tasks – Actual and projected cost of special tasks issued for a specific level 2

WBS.

X.10 Long Term Support – Long term mission support including any management, business management support, systems engineering etc that is not unique to a particular mission

Level 4 – The Contractor shall define WBS level within each level 3 and provide a brief description of the work content. For Example A.04.01 C&DH

WBS Description

Lev2

↓ Lev3

A.0 B.0 C.0 D.0 G.0 H.0

Total (Level 1) Lev4↓ NRE FM1 FM2 FM3

Special Tasks

Long Term Support

Program Management X.01 0.0

Mission Assurance X.02 0.0

Systems Engineering X.03 0.0

Hardware / Software X.04 0.0

Subsystem 1 X.04.01 0.0

Subsystem 2 X.04.02 0.0

Subsystem 3 X.04.03 0.0

Subsystem 4 X.04.04 0.0

Subsystem 5 X.04.05 0.0

Subsystem etc X.04.etc 0.0

Integration & Test X.05 0.0

Ground Support Equipment X.06

0.0

PDS X.07 N/A 0.0

Launch and Early MO X.08 N/A 0.0

Special Tasks X.09

Long Term Support X.10

Reserve / Uncertainty 0.0

COM / Fee 0.0

Total Estimate 0 0 0 0 0 0 0.0

2022-12-16T11:02:07-0500
Heather Matthews
2022-12-16T11:06:25-0500
CANDACE CARLISLE