8. Award Allocation Form IRA.xlsx
XLSX spreadsheet 119 KB Posted
- Solicitation number
- 47PH0825R0001
About this file
This document contains a Post Award Allocation Form and a Bid Tabulation Form related to a federal contract opportunity.
The Post Award Allocation Form provides details on a Design Build contract for the Kika De La Garza Land Port of Entry (LPOE) Border Roadway Improvement and Construction (BRIC) project in Pharr, TX. The project, funded in part by the Inflation Reduction Act of 2022, requires the use of low embodied carbon materials for pavement repair and replacement of approximately 515,000 sf. The contractor must have NAICS code 237310 (Concrete and Asphalt Paving) and the current small business size standard is $45.0 Million. The project is expected to take approximately 460 calendar days to complete. The Bid Tabulation Form shows bid pricing from multiple contractors for various construction divisions and trade work required for the project.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Information
POST AWARD ALLOCATION FORM IRA
| PROJECT NAME | ||||
| BUILDING NAME | ||||
| BUILDING ADDRESS | BUILDING NUMBER | |||
| ESTIMATED | ||||
| START DATE | PERIOD OF PERFORMANCE DAYS | |||
| SOLICITATION # | DELIVERY METHOD | JOC/IDIQ |
| OWNER INFORMATION | CONTRACTOR INFORMATION | ||
| OWNER | |||
| COMPANY NAME | CONTRACTOR COMPANY NAME | ||
| OWNER | |||
| CONTACT NAME | CONTRACTOR CONTACT NAME | ||
| ADDRESS | ADDRESS | ||
| OWNER | |||
| PHONE | CONTRACTOR PHONE | ||
| OWNER | |||
| CONTRACTOR EMAIL |
| SCOPE OF WORK |
| TEXT |
| MATERIALS AND SERVICES NOT INCLUDED |
| TEXT |
| ASSUMPTIONS |
| TEXT |
| NET ZERO CONTRIBUTIONS |
| TEXT |
Masterformat CSI
PBS MASTERFORMAT CSI
| Masterformat | |||
| CSI | System Elements (Trade Work) | Self Performed/ | |
| Subcontracted? | Amount |
| Div. 00 | Design Services - for Design Build | |
| Div. 00A | High Performing Green Buildings | |
| Div. 00B | Emerging and Sustainable Technologies | |
| Div. 01 | General Requirements (Please Include Jobsite Overhead) | |
| Div. 02 | Existing Conditions | |
| Div. 03 | Concrete | 0 |
| Div. 03A | Low Embodied Carbon Concrete | |
| Div 03.B | Non LEC Concrete | |
| Div. 04 | Masonry | |
| Div. 05 | Metals | 0 |
| Div. 05A | Low Embodied Carbon Steel | |
| Div 05.B | Non LEC Metals | |
| Div. 06 | Wood, Plastics, Composites | |
| Div. 07 | Thermal and Moisture Protection | |
| Div. 08 | Openings | 0 |
| Div. 08A | Low Embodied Carbon Glass | |
| Div 05.B | Non LEC Openings | |
| Div. 09 | Finishes | |
| Div. 10 | Specialties | |
| Div. 11 | Equipment | |
| Div. 12 | Furnishings | |
| Div. 13 | Special Construction | |
| Div. 14 | Conveying Equipment | |
| Div. 21 | Fire Suppression | |
| Div. 22 | Plumbing | |
| Div. 23 | Heating, Ventilating, and Air Conditioning (HVAC) | |
| Div. 26.1 | Electrical | |
| Div. 26.2 | Lighting | |
| Div. 27 | Communications | |
| Div. 28.1 | Electronic Safety | |
| Div. 28.2 | Electronic Security (TI - Non-BSAC) | |
| Div. 31 | Earthwork | |
| Div. 32 | Exterior Improvements | 0 |
| Div. 32.A | LEC Asphalt | |
| Div. 32.B | Rest of Exterior Improvements | |
| Div. 33 | Utilities | |
| Div. 34 | Transportation | |
| Div. 35 | Waterway and Marine Construction | |
| Div. 40 | Process Integration | |
| Div. 41 | Material Processing and Handling Equipment | |
| Div. 42 | Process Heating, Cooling and Drying Equipment | |
| Div. 43 | Process Gas and Liquid Handling, Purification and Storage Equipment | |
| Div. 44 | Pollution and Waste Control Equipment | |
| Div. 45 | Industry Specific Manufacturing Equipment | |
| Div. 46 | Water and Wastewater Equipment | |
| Div. 48 | Electrical Power Generation | |
| Subtotal | Trade Cost | $0.00 |
| General Conditions | ||
| Insurances (General Liability, Subcontractor Performance, Builders Risk Program) | ||
| Payment and Performance Bond |
| Subtotal | Estimated Cost of Work | $0.00 |
| Overhead | ||
| Profit | ||
| Proposal Price | $0.00 |
Bid Tabulation
| PBS BID TABULATION FORM | |||||
| Company Name: | Project No.: | ||||
| Project Name: | |||||
| Location: | |||||
| Architect: | Independent Government Estimate (IGE) | CONTRATOR B | CONTRACTOR C | CONTRACTOR D |
| Bid Date: | |||||||||||||
| BID QUANTITIES | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | UNIT AMOUNT | BID | |||
| Ref # | Item Description | Qty. | UNIT | ||||||||||
| Div. 00 | Design Services - for Design Build | 500 | $500.00 | 500 | $500.00 | $ - | $ - | $ - | |||||
| Div. 01 | General Requirements (Please Include Jobsite Overhead) | 900 | $900.00 | 1000 | $1,000.00 | $ - | $ - | $ - | |||||
| Div. 02 | Existing Conditions | 600 | $600.00 | 600 | $600.00 | $ - | $ - | $ - | |||||
| Div. 03 | Concrete | 210 | $210.00 | 200 | $200.00 | $ - | $ - | $ - | |||||
| Div. 03A | Low Embodied Carbon Concrete | 200 | $200.00 | 200 | $200.00 | $ - | $ - | $ - | |||||
| Div 03.B | Non LEC Concrete | 4.5 | $45.00 | 5 | $50.00 | $ - | $ - | $ - | |||||
| Div. 04 | Masonry | 5 | $50.00 | 6 | $60.00 | $ - | $ - | $ - | |||||
| Div. 05 | Metals | 6 | $60.00 | 5 | $50.00 | $ - | $ - | $ - | |||||
| Div. 05A | Low Embodied Carbon Steel | 1.4 | $280.00 | 1.5 | $300.00 | $ - | $ - | $ - | |||||
| Div 05.B | Non LEC Metals | 500 | $500.00 | 500 | $500.00 | $ - | $ - | $ - | |||||
| Div. 06 | Wood, Plastics, Composites | 1.25 | $250.00 | 1.25 | $250.00 | $ - | $ - | $ - | |||||
| Div. 07 | Thermal and Moisture Protection | 590 | $590.00 | 600 | $600.00 | $ - | $ - | $ - | |||||
| Div. 08 | Openings | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 05A | Low Embodied Carbon Glass | $ - | $ - | $ - | $ - | $ - | |||||||
| Div 05.B | Non LEC Openings | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 09 | Finishes | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 10 | Specialties | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 11 | Equipment | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 12 | Furnishings | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 13 | Special Construction | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 14 | Conveying Equipment | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 21 | Fire Suppression | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 22 | Plumbing | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 23 | Heating, Ventilating, and Air Conditioning (HVAC) | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 26.1 | Electrical | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 26.2 | Lighting | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 27 | Communications | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 28.1 | Electronic Safety | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 28.2 | Electronic Security (TI - Non-BSAC) | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 31 | Earthwork | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 32 | Exterior Improvements | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 32.A | LEC Asphalt | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 32.B | Rest of Exterior Improvements | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 33 | Utilities | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 34 | Transportation | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 35 | Waterway and Marine Construction | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 40 | Process Integration | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 41 | Material Processing and Handling Equipment | $ - | $ - | ||||||||||
| Div. 42 | Process Heating, Cooling and Drying Equipment | $ - | $ - | $ - | $ - | $ - | |||||||
| Div. 43 | Process Gas and Liquid Handling, Purification and Storage Equipment | $ - | $ - | ||||||||||
| Div. 44 | Pollution and Waste Control Equipment | $ - | $ - | ||||||||||
| Div. 45 | Industry Specific Manufacturing Equipment | $ - | $ - | ||||||||||
| Div. 46 | Water and Wastewater Equipment | $ - | $ - | ||||||||||
| Div. 48 | Electrical Power Generation | $ - | $ - | ||||||||||
| $4,185.00 | $4,310.00 | ||||||||||||
| $426.69 | $426.69 | ||||||||||||
| $4,611.69 | $4,736.69 |