Amendment 5 - 47PH0825R0001 2025 01 10.pdf

PDF 383 KB Posted

Attached to
Design Build Contract for Kika De La Garza Land Port of Entry (LPOE) Border Roadway Improvement and Construction (BRIC), Pharr, TX
Solicitation number
47PH0825R0001
Issued by

About this file

This is Amendment 5 to solicitation 47PH0825R0001 for the Kika De La Garza Land Port of Entry Border Roadway Improvement and Construction project in Pharr, TX. The amendment makes two key changes: (1) corrects CLINs 0006 and 0008 of the Base Scope & IRA Pricing Sheet, and (2) extends the proposal due date to January 21, 2025 at 2:00pm Central Time.

The amendment includes detailed pricing sheets for low embodied carbon materials across multiple construction areas (PORTRD1, CIDOCKPK1-3, CIDOCKRD1, GANTRYRD1, etc.). These sheets require pricing for concrete, asphalt, and steel components measured in cubic yards (C.Y.) and tons. The project involves approximately 515,000 sf of concrete pavement repair/replacement using Low Embodied Carbon materials. The work is being funded partially through the Inflation Reduction Act (IRA) and is set aside for small businesses under NAICS code 237310 with a size standard of $45.0 Million.

View the file

Other files

File Type Posted
Amendment 6 - 47PH0825R0001 2025 06 10.pdf PDF
Pharr LPOE Bid Sheet 2025 01 10.xlsx XLSX spreadsheet
Amendment 4 - 47PH0825R0001 2025 01 08.pdf PDF
Pharr LPOE Bid Sheet 2024 12 20.xlsx XLSX spreadsheet
Amendment 3 - 47PH0825R0001 2024 12 20.pdf PDF
Amendment 2 - 47PH0825R0001 2024 12 13.pdf PDF
Pharr LPOE Bid Sheet_12.10.24 (1).xlsx XLSX spreadsheet
Amendment 1 - 47PH0825R0001 2024 12 05.pdf PDF
Communications Plan Template LPOE project 03 22 posted version.docx DOCX document
13. 2022.08.03 PHAR - Final Concepts Report_3_Rev-Redacted 10-8-24signed.pdf PDF
15. IRA Project Submittal Form and Data Dictionary PDF.pdf PDF
5. TX20240255 Building 2024 08 23.pdf PDF
10. Concrete - GSA IRA Low Embodied Carbon Requirements (Dec. 2023).pdf PDF
8. Award Allocation Form IRA.xlsx XLSX spreadsheet
FY2024 Metric Waiver FINAL.pdf PDF
14. Bid Bond.pdf PDF
1. GSA Affiliated Custom Accounts (GACA) for Google Drive.pdf PDF
12. Asphalt - GSA IRA Low Embodied Carbon Requirements (Dec. 2023).pdf PDF
3. Past Experience_Past Performance Questionnaire (Factor 2).pdf PDF
Pharr Div 01 Specs.pdf PDF
6. GSA 527-21 - Contractor's Qualifications and Financial Informatio.pdf PDF
2. Past Experience & Performance of Co Questionnaire Factor 1.pdf PDF
9. Sample IRA Project Submittal_ Reporting Form.xlsx XLSX spreadsheet
7. Offeror Representations and Certifications Form Dec 2023 (1).pdf PDF
11. Steel - GSA IRA Low Embodied Carbon Requirements (Dec. 2023).pdf PDF
5. TX20240003 Highway 2024 01 05.pdf PDF
4. Factor 4 LEC Material IRA Sustainability Factor Table.xlsx XLSX spreadsheet
Pharr Solicitation 2024 11 22.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

RFP No. 47PH082 R000

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

GSA, PBS, Acquisition Management Division 819 Taylor Street, Floor 11 Fort Worth, TX 76210 Attn: Ashley Morgan, Contracting Officer

X

AMENDMENT 5 – Kika De La Garza Land Port of Entry Border Roadway Improvement and u Pharr, TX, RFP No. 47PH0825R0001

This amendment is issued to update the following:

1. Correct CLINs 0006 and 0008 of the Base Scope & IRA Pricing Sheet (see attached).

2. The Proposal u b to January 21, 2025, 2:00pm Central Time.

Quantity Unit

C.Y

C.Y

Tons

Quantity Unit

Clin 0003AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ CIDOCKPK1 C.Y

Clin 0003AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ CIDOCKPK1 C.Y

Clin 0003AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ CIDOCKPK1 Tons

Quantity Unit

C.Y

C.Y

Tons

Quantity Unit

Clin 0005AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ CIDOCKPK3 C.Y

Clin 0005AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ CIDOCKPK3 C.Y

Clin 0005AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ CIDOCKPK3 Tons

Quantity Unit

C.Y

C.Y

Tons

Quantity Unit

Clin 0007AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ GANTRYRD1 C.Y

Clin 0007AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ GANTRYRD1 C.Y

Clin 0007AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ GANTRYRD1 Tons

Quantity Unit

Clin 0008AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ KENNELRD1 C.Y

Clin 0008AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ KENNELRD1 C.Y

Clin 0008AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ KENNELRD1 Tons

Clin 0002AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ PORTRD1

Clin 0002AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ PORTRD1

Clin 0002AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ PORTRD1

CLIN 0006 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0005 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION)

CLIN 0003 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0004 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Shown on Summary Sheet

IRA LEC OPTIONS (CONSTRUCTION) IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS

Clin 0001 ‐ DESIGN AND ASSOCIATED EXPENSES

CLIN 0002 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Low Embodied Carbon Materials Kika De La Garza (Pharr) LPOE Paving GSA RFP Number ‐ #47PH0825R0001

Description

BASE SCOPE CLIN 0001 ‐ (Design) IRA ACQUISITION AND INSTALLATION OF LOW EMBODIED CARBON MATERIALS COST / TOTAL

COST / TOTAL

CLIN 0007 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Clin 0004AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ CIDOCKPK2

Clin 0004AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ CIDOCKPK2

Clin 0004AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ CIDOCKPK2

CLIN 0008 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

‐$ Clin 0006AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ CIDOCKRD1

Clin 0006AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ CIDOCKRD1

Clin 0006AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ CIDOCKRD1

Quantity Unit

Clin 009AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ POVSPK1 C.Y

Clin 009AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ POVSPK1 C.Y

Clin 009AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ POVSPK1 Tons

Quantity Unit

Clin 010AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ POVSRD3 C.Y

Clin 010AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ POVSRD3 C.Y

Clin 010AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ POVSRD3 Tons

Quantity Unit

Clin 011AA‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ KENNELPK1 C.Y

Clin 011AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ KENNELPK1 C.Y

Clin 011AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ KENNELPK1 Tons

Quantity Unit

Clin 004AJ ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ KENNELPK2 C.Y

Clin 004AK ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ KENNELPK2 C.Y

Clin 004AL ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ KENNELPK2 Tons

Quantity Unit

Clin 013AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ POVPPK1 C.Y

Clin 005AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ POVPPK1 C.Y

Clin 005AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ POVPPK1 Tons

Quantity Unit

C.Y

C.Y

Tons

Quantity Unit

Clin 015AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ ADMINPK2 C.Y

Clin 015AB‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ ADMINPK2 C.Y

Clin 015AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ ADMINPK2 Tons

Quantity Unit

Clin 016AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ CARGORD1 C.Y

Clin 016AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ CARGORD1 C.Y

Clin 016AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ CARGORD1 Tons

Quantity Unit

CLIN 0011 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION)

CLIN 0012 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION)

COST / TOTAL

COST / TOTAL

CLIN 0017 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0009 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION)

CLIN 0013 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION)

COST / TOTAL

COST / TOTAL

Clin 014AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ ADMINPK1

Clin 014AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ ADMINPK1

Clin 014AC‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ ADMINPK1

CLIN 0010 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0014 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0015 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0016 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Clin 017AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ COMMPRD1 C.Y

Clin 017AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ COMMPRD1 C.Y

Clin 017AC‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ COMMPRD1 Tons

Quantity Unit

Clin 018AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ COMMSRD1 C.Y

Clin 018AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ COMMSRD1 C.Y

Clin 018AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ COMMSRD1 Tons

Quantity Unit

Clin 006AG ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ COMMPRD2 C.Y

Clin 006AH ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ COMMPRD2 C.Y

Clin 006AI ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ COMMPRD2 Tons

Quantity Unit

Clin 020AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ POVPRD1 C.Y

Clin 020AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ POVPRD1 C.Y

Clin 020AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ POVPRD1 Tons

Quantity Unit

Clin 021AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ADMINRD1 C.Y

Clin 021AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ ADMINRD1 C.Y

Clin 021AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ ADMINRD1 Tons

Quantity Unit

Clin 022AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ FMCSAPK1 C.Y

Clin 022AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ FMCSAPK1 C.Y

Clin 022AC ‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ FMSCAPK1 Tons

Quantity Unit

Clin 023AA ‐ LOW EMBODIED CARBON CONCRETE AND ASSOCIATED EXPENSES ‐ FMCSARD1 C.Y

Clin 023AB ‐ LOW EMBODIED CARBON ASPHALT AND ASSOCIATED EXPENSES ‐ FMCSARD1 C.Y

Clin 023AC‐ LOW EMBODIED CARBON STEEL AND ASSOCIATED EXPENSES ‐ FMSCARD1 Tons

CLIN 0020 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Clin 0026 ‐ Div. 32 Exterior Improvements Shown on Summary Sheet

COST / TOTAL

Shown on Summary Sheet

COST / TOTAL

Shown on Summary Sheet

Clin 0024 ‐ Division 1

Subtotal ‐ Construction Quantities Costs

CLIN 0024

CLIN 0025

Clin 0025 ‐ Div. 31 Earthwork

CLIN 0026 COST / TOTAL

CLIN 0022 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0023 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0018 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0019 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

CLIN 0021 ‐ QUANITIES OF LOW EMBODIED CARBON MATERIALS (CONSTRUCTION) COST / TOTAL

Type or Print Name

Title

Signature

Firm Name

Date

Subtotal ‐ Bond, Insurance

Total Evaluated Price Shown on Summary Sheet

Insurance 0.00% ‐$

Profit 0.00%

0.00%

Overhead 0.00% ‐$

Subtotal ‐ Overhead, Profit

Bond

File details come from the government source that posted it. Updated .