8-01700 Project Closeout.pdf

PDF 38 KB Posted

Attached to
2025 Milling & Paving and ADA Ramps
Solicitation number
Not on record
Issued by
Montgomery County, Northern Cambria Borough, Pennsylvania

About this file

This document is a Project Closeout specification section (Section 01700) detailing the procedures and requirements for completing a construction project. The section outlines the processes for substantial completion and final observation of work, including the contractor's responsibilities for submitting written notices, addressing deficiencies, and preparing for project closeout. Key steps include submitting a written notice of substantial completion, providing a list of items requiring correction, and undergoing engineering observations to verify project status.

The document specifies the administrative requirements for finalizing the project, including submittal of project record documents, spare parts, and maintenance materials. It also describes the financial close-out process, requiring the contractor to submit a final statement of accounting that reflects the original contract sum, all adjustments (such as change orders, allowances, and deductions), and the final payment calculation. The section includes provisions for second observation fees, where the engineer can deduct compensation from the final payment if additional site visits are required due to incomplete or incorrect work.

View the file

Other files

File Type Posted
34-Front End Docs.pdf PDF
13-rco and bid documents D1 thru D-8.pdf PDF
10-01201 Preconstruction Conference.pdf PDF
21-W FORNANCE-11x17 Land.pdf PDF
30-02507 Concrete Sidewalk ADA Ramps.pdf PDF
15-Ordinance 22-10 - Amendment to Chapter 133, Article I titled Responsible Contractors (RCO) - EXECUTED 202301121156300469.pdf PDF
23-WOOD-11x17 Land.pdf PDF
31-9695-2001-3 Sidewalk Detectable Warning Surface - Copy.pdf PDF
32-02930 Lawns Grasses.pdf PDF
6-01001 Special Provisions.pdf PDF
17-BUTTONWOOD-11x17 Land.pdf PDF
3-2025-09-16 2025 NORR CURB REPLACEMENT SCHEDULE.pdf PDF
20-E OAK-11x17 Land.pdf PDF
1-01025 Measurement Payment.pdf PDF
2-01010 Contractors Work.pdf PDF
19-JACKSON-11x17 Land.pdf PDF
22-W OAK-11x17 Land.pdf PDF
29-03300 Concrete.pdf PDF
16-E MARSHAL-11x17 Land.pdf PDF
7-01340 Shop Drawings, Samples.pdf PDF
27-02506 Concrete Curb.pdf PDF
26-PUB-72M 2010 Change-12.pdf PDF
9-PaDot Section - 411.pdf PDF
4-01720 Project Record Documents.pdf PDF
28-02260 Finish Grading.pdf PDF
35-penndot forms.pdf PDF
14-PaDot Section - 409.pdf PDF
12-wage rate determination.pdf PDF
18-E FORNANCE-11x17 Land.pdf PDF
11-PaDot Section - 491.pdf PDF
5-PaDot Section - 350.pdf PDF
24-NOBLE-11x17 Land.pdf PDF
33-PENNDOT 944 PROPOSAL FORM.pdf PDF
25-norristown 2025 paving scope of work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01700-1

SECTION 01700

PROJECT CLOSEOUT

PART 1 GENERAL

1.1 RELATED WORK SPECIFIED ELSEWHERE

A. Project Record Documents - Section 01720.

1.2 SUBSTANTIAL COMPLETION

A. When the work is considered substantially complete, submit a written notice that the work, or a designated portion thereof, is substantially complete. Include a list of all items that require completion or correction.

B. Within a reasonable time after receipt of such notice, an observation will be made to determine the status of completion.

C. If the Work is not considered substantially complete, the Contractor will be notified in writing, giving the reasons therefore.

D. Contractor shall remedy the deficiencies in the Work, and send a second written notice of substantial completion. This notice shall include a statement of action taken on each item noted a requiring correction or completion to achieve "Substantial

Completion" status.

E. The Work will be observed a second time.

F. When the Engineer concurs that the Work is substantially complete, he will:

1. Issue a letter accompanied by Contractor's list of items to be completed or corrected, as verified and amended by the Engineer.

1.3 FINAL OBSERVATION

A. When the Work is considered complete, submit written certification that:

1. Contract Documents have been reviewed.

2. Work has been observed and has been completed in compliance with

Contract Documents.

01700-2

3. Equipment and systems have been tested in the presence of the Engineer and are operational.

4. Work is ready for final observation.

B. Observation will be made to verify the status of completion with reasonable promptness after receipt of such certification.

C. If the Work is not considered complete, the Contractor will be notified in writing, listing the incomplete or defective work.

D. Contractor shall take immediate steps to remedy the stated deficiencies and, after correcting deficiencies, he shall send a second written certificate that the work is complete. This certification shall itemize each deficiency noted and a statement of action taken to remedy or complete the Work.

E. The work will be observed a second time.

F. When the Work is acceptable under the Contract Documents, the Contractor shall be required to make closeout submittals.

1.4 SECOND OBSERVATION FEES

A. Should the Engineer perform a second observation due to failure of the work to comply with the claims of status of completion made by the Contractor:

1. Engineer will deduct the amount of such compensation from the final payment to the Contractor.

1.5 CLOSEOUT SUBMITTALS

A. Project Record documents as specified under Section 01720.

1.6 SPARE PARTS AND MAINTENANCE MATERIALS

A. Furnish spare parts and maintenance materials as specified under various Sections of the Specifications.

B. Package and label parts and materials and store in area of the building where directed by the Engineer.

1.7 FINAL ADJUSTMENT OF ACCOUNTS

01700-3

A. Submit a final statement of accounting.

B. Statement shall reflect all adjustments to the Contract Sum:

1. The original Contract Sum.

2. Additions and deductions resulting from:

a. Previous Change Orders.

b. Allowances.

c. Unit Prices.

d. Deductions for uncorrected Work.

e. Deductions for re-inspection payments.

f. Other adjustments.

3. Total Contract Sum, as adjusted.

4. Previous payments.

5. Sum remaining due.

C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Orders.

1.8 FINAL APPLICATION FOR PAYMENT

A. Submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contracts.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION