10-01201 Preconstruction Conference.pdf

PDF 32 KB Posted

Attached to
2025 Milling & Paving and ADA Ramps
Solicitation number
Not on record
Issued by
Montgomery County, Northern Cambria Borough, Pennsylvania

About this file

This document is a Section 01201 specification for a Preconstruction Conference, involving a Borough and a Contractor for an unspecified construction project. The Preconstruction Conference is scheduled to be held within ten working days after contract execution, with the primary purpose of clarifying contract administration procedures. The conference will be conducted by an Engineer and requires attendance by authorized representatives of the Contractor and major subcontractors. The minimum agenda includes discussing organizational arrangements, communication channels, construction schedule, contract document distribution, shop drawing processing, field decisions, work performance regulations, and procedures for safety, security, and quality control.

The document outlines specific requirements for conference preparation, including the Contractor's obligation to provide personnel with the authority to commit to solutions discussed during the meeting. The Engineer will compile and distribute conference minutes, providing three copies to the Contractor and required copies to the Borough. Attendees are advised to notify the Engineer at least 24 hours in advance of any additional agenda items they wish to discuss. The specification emphasizes the importance of clear communication, organizational alignment, and establishing protocols for project execution prior to the actual start of work.

View the file

Other files

File Type Posted
34-Front End Docs.pdf PDF
13-rco and bid documents D1 thru D-8.pdf PDF
21-W FORNANCE-11x17 Land.pdf PDF
30-02507 Concrete Sidewalk ADA Ramps.pdf PDF
15-Ordinance 22-10 - Amendment to Chapter 133, Article I titled Responsible Contractors (RCO) - EXECUTED 202301121156300469.pdf PDF
8-01700 Project Closeout.pdf PDF
23-WOOD-11x17 Land.pdf PDF
31-9695-2001-3 Sidewalk Detectable Warning Surface - Copy.pdf PDF
32-02930 Lawns Grasses.pdf PDF
6-01001 Special Provisions.pdf PDF
17-BUTTONWOOD-11x17 Land.pdf PDF
3-2025-09-16 2025 NORR CURB REPLACEMENT SCHEDULE.pdf PDF
20-E OAK-11x17 Land.pdf PDF
1-01025 Measurement Payment.pdf PDF
2-01010 Contractors Work.pdf PDF
19-JACKSON-11x17 Land.pdf PDF
22-W OAK-11x17 Land.pdf PDF
29-03300 Concrete.pdf PDF
16-E MARSHAL-11x17 Land.pdf PDF
7-01340 Shop Drawings, Samples.pdf PDF
27-02506 Concrete Curb.pdf PDF
26-PUB-72M 2010 Change-12.pdf PDF
9-PaDot Section - 411.pdf PDF
4-01720 Project Record Documents.pdf PDF
28-02260 Finish Grading.pdf PDF
35-penndot forms.pdf PDF
14-PaDot Section - 409.pdf PDF
12-wage rate determination.pdf PDF
18-E FORNANCE-11x17 Land.pdf PDF
11-PaDot Section - 491.pdf PDF
5-PaDot Section - 350.pdf PDF
24-NOBLE-11x17 Land.pdf PDF
33-PENNDOT 944 PROPOSAL FORM.pdf PDF
25-norristown 2025 paving scope of work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01201-1

SECTION 01201

PRECONSTRUCTION CONFERENCE

PART 1 GENERAL

1.1 DESCRIPTION

A. Work included: To help clarify construction contract administration procedures, the Engineer will conduct a Preconstruction Conference prior to start of the Work.

Provide attendance by the designated personnel.

B. Related Work:

1. Documents affecting work of this Section include, but are not necessarily limited to, General Conditions, Supplementary Conditions, and Sections in

Division 1 of these Specifications.

1.2 QUALITY ASSURANCE

A. For those persons designated by the Contractor, his subcontractors, and suppliers to attend the Preconstruction Conference, provide required authority to commit the entities they represent to solutions agreed upon in the Conference.

1.3 SUBMITALS

A. To the maximum extent practicable, advise the Engineer at least twenty-four (24) hours in advance of the Conference as to items to be added to the agenda.

B. The Engineer will compile minutes of the Conference, and will furnish three copies of the minutes to the Contractor and required copies to the Borough. The

Contractor may make and distribute such other copies as he wishes.

1.4 PRECONSTRUCTION CONFERENCE

A. The Conference will be scheduled to be held within ten (10) working days after the Borough has executed the Contracts, but prior to actual start of Work.

B. Attendance:

1. Provide attendance by authorized representatives of the Contractor and major subcontractors.

01201-2

2. The Engineer will advise other interested parties, including the Borough, and request their attendance.

C. Minimum agenda: Data will be distributed and discussed.

1. Organizational arrangement of Contractor's forces and personnel, and those of subcontractors, materials, suppliers, and the Engineer.

2. Channels and procedures for communication.

3. Construction schedule, including sequence of critical work.

4. Contract Documents, including distribution of required copies of

Drawings and revisions.

5. Processing of Shop Drawings and other data submitted the Engineer for review.

6. Processing of field decisions and Change Orders.

7. Rules and regulations governing performance of the Work.

8. Procedures for safety and first air, security, quality control, housekeeping, and related matters.

END OF SECTION