This is a Proposal and Contract document (MS-944) for the Municipality of Norristown in Montgomery County, Pennsylvania, covering a 2025 Milling & Paving and ADA Ramps project. The project involves roadway milling, asphalt wearing courses, bituminous base repair, leveling courses, line striping, and pavement marking across multiple street sections including W Forrance St, E Marshall St, Buttwood Marshall St, W Wood St, Noble St, W Oak St, and alternate sections for E Oak St, E Fornance St, and Jackson St. The proposal includes detailed work specifications for approximately 12,200-8,606 square yards of roadway milling, multiple base repairs, leveling courses, ADA ramps, and various striping requirements. The bid proposal is due on 11/13/25 at 11:00 AM, with work to be completed within 90 calendar days after the Notice to Proceed, and liquidated damages of $500 per calendar day for delays.
The contract includes multiple bid items with quantities and will be awarded based on the aggregate total for like items. The proposal requires a 10% bid bond, performance and payment bonds, and compliance with Pennsylvania and federal employment and non-discrimination regulations. Special provisions include requirements for traffic control, safety devices, material certifications, utility coordination, property owner notifications, and strict working hours from 7:00 AM to 7:00 PM Monday through Saturday. The contractor is responsible for project coordination, utility adjustments, signalization equipment protection, and must provide insurance with the Borough and Pennoni Associates Inc. named as additional insureds. The maximum time between milling and paving is five working days, and all restoration work must be completed within five days of area disturbance.
View the file
Other files
Show all 34
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MS-944 (7-09)
PROPOSAL AND CONTRACT
( WHEN EXECUTED ) THIS PROPOSAL INCLUDES
INSTRUCTIONS TO BIDDERS
INSTRUCTIONS ON PAGE 4
A. DEPOSIT OF PROPOSALS.
All envelopes containing Bid proposals shall
Municipality of Norristown
2025 Milling & Paving and ADA Ramps be clearly marked “Bid Proposal for letting of MUNICIPALITY (NAME & TYPE)
11/13/25 ."
DATE Leonard Lightner
Municipal Adminstrator
Sealed Proposals will be received on or before
11:00 AM on the above Letting Date. 235 East Airy St
TIME Norristown PA 19401
ADDRESS
Bids will be opened and read at approximately
11:00 AM , on the above Letting Date.
PROPOSALS MUST BE SUBMITTED ONLINE
THRU THE PENNBID WEB SITE.
TIME .
The contractor proposes to furnish and deliver all materials ( including Form CS-4171, CERTIFICATE OF COMPLIANCE and/ or TR-465 DAILY BITUMINOUS MIXTURE
CERTIFICATION ) and to do and perform all work on the following project as more specifically set forth in the Schedule of Prices (Attachment), in accordance with drawings and specifications on file at
Municipality of
Norristown as well as the supplements and special requirements contained herein and/ or attached hereto and current PennDOT
Specifications (Publication 408), except Volumetric testing of bituminous paving materials is not required (Sec. 409).
If designated as the successful bidder, the contractor will begin work on the date specified in the notice to proceed, or as otherwise provided in the special requirements, and will complete all work within see attachment
1-B calendar days.
3 Accompanying this proposal is a certified check or bid bond in the amount of 10% of Bid made payable to the municipality as a proposal guarantee which, it is understood, will be forfeited in case the contractor fails to comply with the requirements of the proposal.
B. PROPOSAL OF:
NAME / ADDRESS OF CONTRACTOR
CONTRACTORS CERTIFICATION
It is hereby certified as follows:
1 The only person interested in the proposal as principal (s) is (are):
2 None of the above persons are employees of the municipality.
3 This proposal is made without collusion with any other person, firm or corporation.
All plans and specifications referred to above and the site of the work have been examined by the contractor. The contractor understands that the quantities indicated herein are approximate and are subject to change as may be required; and that all work is payable on the basis of the unit price listed on the Schedule of Prices. (Attachment 1).
The contractor will comply with all requirements of the laws and implementing regulations of the
Commonwealth of Pennsylvania and the United States relating to human relations, equal opportunity and non-discrimination in employment, and will pay to workmen employed in the performance of the contract the wages to which they may be entitled.
6 The contractor will provide the municipality with a performance bond, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions thereof, and a payment bond, conditioned on the prompt payment of all material furnished and labor supplied or performed in the prosecution of the work, in accordance with the Public Works
Contractors’ Bond Law of 1967; and an affidavit accepting the provisions of the Workmen’s
Compensation Act of 1915, as amended.
CONTRACTOR
BY: DATE:
TITLE:
WITNESSED OR ATTESTED BY: DATE:
TO BE EXECUTED ONLY IN THE EVENT THE ABOVE PROPOSAL IS ACCEPTED
ACCEPTED ON :
DATE
Municipality of Norristown
Municipality
BY:
TITLE: Leonard Lightner Municipal Administrator
BY:
TITLE: .
BY:
ATTESTED BY:
SEAL
ATTACHMENT 1
TO MS - 944 ( PROPOSAL AND CONTRACT MS - 944 )
County:
Montgomery
Municipality: Municipality of Norristown
Project Number:
T
H
IS
P O
R T
IO
N
T O
B E
C O
M P
L E
T E
D
B Y
T H
E M
U N
IC
IP
A L
IT
Y
LOCATION OF WORK:
See attached map
DESCRIPTION OF WORK:
Milling, asphalt wearing courses, bituminous base repair, bituminous leveling course, line striping, and pavement marking in accordance with Borough Specifications
(attached) and PennDOT 408 specifications, latest edition thereof.
ESCALATOR CLAUSE:( if adopted by Municipality.)
Applies to this project
SCHEDULE OF PRICES
Item
1 No.
Approximate
2 Quantities
Unit
*Description
Unit
5 Price
Total
W Forrance St Dekalb St to Harding Blvd
1-1 12,200 Sqyd Roadway Milling 11/2”
1-2 12,200 Sqyd Super Pave Wearing Course 9.5mm
1-3 610 Sqyd 4” Base Repair
1-4 150 Tons Leveling Course 9.5 mm Wearing
1-5 41 Ea ADA Ramps
1-6 558 Lf 24” Stop Bar Striping
1-7 2520 Lf 4” Cross Walk Striping
E Marshall St -New Hope St to Arch St.
1-8 8,606 Sqyd Roadway Milling 11/2”
1-9 8,606 Sqyd Super Pave Wearing Course 9.5mm
1-10 430 Sqyd 4” Base Repair
1-11 125 Tons Leveling Course 9.5 mm Wearing
1-12 12 Ea ADA Ramps
1-13 2 Ea Trunkcated Domes
1-14 286 Lf 24” Stop Bar Striping
1-15 1,196 Lf 4” Cross Walk Striping
Continued on Attachment 1-A
ATTACHMENT 1A
Item 1
No.
*Description
Unit
5 Price
Total
Buttwood Marshall St. to Elm St.
1-16 5,880 Sqyd Roadway Milling 11/2”
1-17 5,880 Sqyd Super Pave Wearing Course 9.5mm
1-18 294 Sqyd 4” Base Repair
1-19 30 Tons Leveling Course 9.5 mm Wearing
1-20 10 Ea ADA Ramps
1-21 216 Lf 24” Stop Bar Striping
1-22 864 Lf 4” Cross Walk Striping
W Wood St. Swede St. to Harding Blvd
1-23 4,532 Sqyd Roadway Milling 11/2”
1-24 4,532 Sqyd Super Pave Wearing Course 9.5mm
1-25 277 Sqyd 4” Base Repair
1-26 25 Tons Leveling Course 9.5 mm Wearing
1-27 16 Ea ADA Ramps
1-28 162 Lf 24” Stop Bar Striping
1-29 1296 Lf 4” Cross Walk Striping
*Description
Unit
5 Price
Total
Noble St Marshal to Airy St.
1-30 4,025 Sqyd Roadway Milling 11/2”
1-31 4,025 Sqyd Super Pave Wearing Course 9mm
1-32 201 Sqyd 4” Base Repair
1-33 25 Tons Leveling Course 9.5 mm Wearing
1-34 6 Ea ADA Ramps
1-35 158 Lf 24” Stop Bar Striping
1-36 770 Lf 4” Cross Walk Striping
W Oak St Stanbridge to Noble St.
1-37 1,999 Sqyd Roadway Milling 11/2”
1-38 1,999 Sqyd Super Pave Wearing Course 9.5mm
1-39 100 Sqyd 4” Base Repair
1-40 15 Tons Leveling Course 9.5 mm Wearing
1-41 12 Ea ADA Ramps
1-42 140 Lf 24” Stop Bar Striping
1-43 700 Lf 4” Cross Walk Striping
1-44 6,061 Lf Property owners curb replacement per schedule provided
1-45 600 Sqft Additional sidewalk at ADA curb ramps as directed and approved by Engineer.
Alternate #1
E Oak St Walnut St. to Arch
2-1 2,136 Sqyd Roadway Milling 11/2”
2-2 2,136 Sqyd Super Pave Wearing Course 9.5mm
2-3 107 Sqyd 4” Base Repair
2-4 15 Tons Leveling Course 9.5 mm Wearing
2-5 8 Ea ADA Ramps
2-6 63 Lf 24” Stop Bar Striping
2-7 350 Lf 4” Cross Walk Striping
*Description
Unit
5 Price
Total
Alternate #2
E. Fornance St Sandy Hill Rd to 815 E Fornance
3-1 2,764 Sqyd Roadway Milling 11/2”
3-2 2,764 Sqyd Super Pave Wearing Course 9.5mm
3-3 15 Tons Leveling Course 9.5 mm Wearing
3-4 8 Ea ADA Ramps
3-5 80 Lf 24” Stop Bar Striping
3-6 320 Lf 4” Cross Walk Striping
Alternate #3
Jackson St Rosemount Ave to Hartranft St.
4-1 923 Sqyd Roadway Milling 11/2”
4-2 923 Sqyd Super Pave Wearing Course 9.5mm
4-3 46 Sqyd 4” Base Repair
4-4 10 Tons Leveling Course 9.5 mm Wearing
4-5 2 Ea ADA Ramps
4-6 45 Lf 24” Stop Bar Striping
4-7 60 Lf 4” Cross Walk Striping
Must include ADT on wearing surfaces
USE OF CUTBACK ASPHALT IS PROHIBITED
BETWEEN MAY 1st AND OCTOBER 31st, EXCEPT
AS NOTED IN BULLETIN NO. 25.
FOR OPTION OR PHASE BIDS THE TOTALS FOR
EACH MUST BE INCLUDED.
BASE BID ITEMS
ALTERNATE #1
ALTERNATE #2
ALTERNATE #3
TOTAL CONTRACT AMOUNT
(5-06) SPECIAL PROVISIONS TO CONTRACT MS-944 ( Attachment 1-B )
CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR
The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an "X".
X Traffic Control and Safety Devices to be provided by the Contractor.
X ( Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)
X Delivery tickets for all materials.
X CS-4171 Certificate of Compliance and/ or TR-465 Daily Bituminous Mixture Certification required for all materials.
X Notify the Municipality five working days prior to start of project.
X Work to be completed on or before 90 days . After Notice to Proceed Liquidated damages apply at
X the rate of $ 500.00 per calendar day.
X Roadway to be power broomed by (contractor X municipality ) prior to start of project.
X Excess material to be removed by (contractor X municipality )
X Municipality to inspect project.
Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.
X Tack Coat required per Section 460, or 409 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.
Prime Coat required per Section 461 of Specifications 408.
X Bituminous Seal on all abutting pavement and curbs required.
X Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.
X Scratch/ Leveling Courses to be placed at the discretion of appointed inspector(s).
Full width pavement with one pass required.
X Municipality reserves the right to limit work completed.
Taper pavement the last 3 feet to curb.
For FOB Source bids, hauling distance will determine selection of bid award.
Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.
X Incidental Preparation and clean up required. ( Project Construction Materials )
X The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.
X Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.
X Contractor responsible for defects that occur within 18 months of applications.
Contractor required to review proposed project with Municipality’s Representative prior to bidding.
Oil Samples required from each distributor truck by contractor (1) one quart : A.M. & P.M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)
At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.
Complete all testing in accordance with Specification Form 408 Section 409 except for superpave volumetric testing.
Nuclear Gauge Testing for density in accordance with PaDot Publication 408 Section 409
X Notice to Proceed will be the date of PennDOT Project Approval.
X Final Completion Certificate & Notice of Completion required.
X Future award of Contract will be based on quality of work as determined by the municipality.
X Contractor to notify all residents of pending work to be performed.
X See “List of Additional Contract Documents” for additional contract documents including contractor’s insurance requirements.
X Borough and Pennoni Associates Inc. shall be named additionally insured. Three (3) copies of insurance shall be provided with the executed contract.
X Borough work hours are 7:00 A.M. to 7:00 P.M. Monday through Saturday; no work, or operation of machinery, may be performed before or after these hours or on Sunday or holidays unless written permission is provided by the Municipality.
X The maximum elapsed time between the milling operation and the paving shall be five (5) working days unless written permission is provided by the Borough. All restoration work on the roadway shoulder and edges must be completed within five (5) days of disturbance of the area. No areas shall be left in an unstabilized condition longer than five (5) days unless written permission is given by the engineer.
X The contractor is required to schedule a preconstruction meeting with the Borough prior to commencing work on this contract.
X The contractor is required to submit a proposed schedule indicating anticipated start date, timeframe for project completion from beginning to end, and estimated sequence of construction.
X The Contactor’s construction operations, equipment, materials and any other such items shall not leave the permanent right-
X of-ways without written permission of the property owner and engineer.
For each roadway section under this contract, the contractor shall notify all property owners along the roadway section five (5) days prior to commencement of work on said roadway section. Notice shall be provided in writing, delivered by hand and/or posted for public view, and include: description and limits of work; date and time work will begin; duration of work; and traffic information such as road closures, detours, and parking restrictions.
X The Contractor shall neither damage nor destroy any curbs, sidewalk, driveway aprons, trees or shrubs. Tracking of paving equipment shall be limited to avoid damage to paved surfaces outside of work area. All damages are to be replaced in kind by the Contractor at no additional cost to the municipality.
X The Contractor is required to fully inform themselves concerning location of public utilities on, under or over the project which may or may not require removal, resetting, construction or reconstruction and which may interfere with their operations. They shall be assumed to have prepared their bid and entered into contract in full contemplation of the conditions to be encountered and their responsibility in connection therewith. The Contractor shall use special care in execution of the work in order to avoid interference or damage to any operating utilities (including, but not limited to painting exposed utility structures during construction). When there is any possibility of such interference or damage, the Contractor shall make satisfactory arrangements with responsible officers or owners of the utilities covering the necessary precautions to be used during performance of the work by the Contractor. Such arrangements shall be made before work is started and shall be subject to the approval of the engineer, which approval will not be considered as releasing the contractor from any responsibility for acts of themselves or their representatives.
X Adjustments to utility boxes are the responsibility of the contactor at no additional expense to the municipality.
X The Contractor is responsible for coordinating with the Borough for any work near signalized intersections to avoid
X interference or damages to traffic signalization equipment on, under or adjacent to the roadway. Signal loops damaged during construction are to be replaced at the Contractor’s expense.
My signature signifies that I have read and understand the above special provisions to this contract, and by being authorized by this company to act as their authorized representative, and on their behalf hereby agree to adhere to any and all of the provisions pertaining to this contract.
Contractor’s Representative Date Municipality’s Representative Date
Municipality of Norristown
Company Municipality
File details come from the government source that posted it. Updated .