27-02506 Concrete Curb.pdf

PDF 106 KB Posted

Attached to
2025 Milling & Paving and ADA Ramps
Solicitation number
Not on record
Issued by
Montgomery County, Northern Cambria Borough, Pennsylvania

About this file

This document is a technical specification section (Section 02506) from the Pennsylvania Department of Transportation (PennDOT) for concrete curb and curb walls construction. The specification provides comprehensive guidelines for contractors performing concrete curbing work, detailing requirements for materials, construction methods, and quality standards. Contractors are expected to furnish all necessary materials, equipment, labor, and supervision to construct curved or straight concrete curbing at specified locations, following PennDOT Publication 408 specifications and design drawings RC-64M and RC-67M.

The technical specification mandates the use of air-entrained (6%) PennDOT Class AA concrete with a compressive strength of 3,750 p.s.i., and provides detailed instructions for subgrade preparation, formwork, joint placement, concrete pouring, finishing, and curing processes. Key technical requirements include using 3/4-inch expansion joint filler, creating contraction joints at specific intervals, protecting and curing concrete for a minimum of 72 hours, and ensuring all work meets PennDOT engineering standards. The specification also requires contractors to repair or replace any defects at their own expense to the Engineer's satisfaction, emphasizing quality control and adherence to established construction standards.

View the file

Other files

File Type Posted
34-Front End Docs.pdf PDF
13-rco and bid documents D1 thru D-8.pdf PDF
10-01201 Preconstruction Conference.pdf PDF
21-W FORNANCE-11x17 Land.pdf PDF
30-02507 Concrete Sidewalk ADA Ramps.pdf PDF
15-Ordinance 22-10 - Amendment to Chapter 133, Article I titled Responsible Contractors (RCO) - EXECUTED 202301121156300469.pdf PDF
8-01700 Project Closeout.pdf PDF
23-WOOD-11x17 Land.pdf PDF
31-9695-2001-3 Sidewalk Detectable Warning Surface - Copy.pdf PDF
32-02930 Lawns Grasses.pdf PDF
6-01001 Special Provisions.pdf PDF
17-BUTTONWOOD-11x17 Land.pdf PDF
3-2025-09-16 2025 NORR CURB REPLACEMENT SCHEDULE.pdf PDF
20-E OAK-11x17 Land.pdf PDF
1-01025 Measurement Payment.pdf PDF
2-01010 Contractors Work.pdf PDF
19-JACKSON-11x17 Land.pdf PDF
22-W OAK-11x17 Land.pdf PDF
29-03300 Concrete.pdf PDF
16-E MARSHAL-11x17 Land.pdf PDF
7-01340 Shop Drawings, Samples.pdf PDF
26-PUB-72M 2010 Change-12.pdf PDF
9-PaDot Section - 411.pdf PDF
4-01720 Project Record Documents.pdf PDF
28-02260 Finish Grading.pdf PDF
35-penndot forms.pdf PDF
14-PaDot Section - 409.pdf PDF
12-wage rate determination.pdf PDF
18-E FORNANCE-11x17 Land.pdf PDF
11-PaDot Section - 491.pdf PDF
5-PaDot Section - 350.pdf PDF
24-NOBLE-11x17 Land.pdf PDF
33-PENNDOT 944 PROPOSAL FORM.pdf PDF
25-norristown 2025 paving scope of work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

02506-1

SECTION 02506

CONCRETE CURB AND CURB WALLS

PART 1 GENERAL

1.1 WORK INCLUDED

A. Contractor shall furnish all materials, implements, machinery equipment, tools, supplies, transportation, labor and supervision required to construct curved or straight concrete curbing of the size indicated, at the locations shown on the plan or as directed by the Engineer.

1.2 RELATED WORK SPECIFIED ELSEWHERE

A. Concrete Sidewalk and ADA Ramps - Section 02507

1.3 REFERENCE STANDARDS

A. Pennsylvania Department of Transportation (PennDOT) Publication 408, Specifications, latest edition.

1.4 SUBMITTALS

A. Material Certificates: Provide copies of material certificates signed by material producer and Contractor, certifying that each material item complies with, or exceeds, specified requirements.

PART 2 PRODUCTS

2.1 MATERIALS

A. Plain cement concrete curb and curb walls shall conform to PennDOT Form 408, Section 630, and PennDOT design drawings RC-64M and RC-67M.

B. Concrete:

1. Shall be air entrained (6%), 3,750 p.s.i. PennDOT Class AA concrete in accordance with Section 704 of PennDOT Specifications, Publication 408, latest edition.

02506-2

B. Premolded Expansion Joint Filler:

1. Shall be 3/4-inch thick fiber expansion joint filler.

C. Curing Materials:

1. Shall be white polyethylene sheeting, burlap, or clear or white liquid membrane - forming curing compound in accordance with PennDOT

Specifications, Publication 408, latest edition.

PART 3 EXECUTION

3.1 SUBGRADE PREPARATION

A. The curb area shall be excavated to the proposed subgrade line, the excavation shall include the removal of existing paving and curbing, if necessary, and the disposal of all excess material.

B. The subgrade line shall be eighteen (18”) inches below and parallel to the top of finished curbing. Any areas which are over-excavated shall be filled with PennDOT

2A stone at the Contractor's expense.

C. When directed, remove and replace unsuitable material with acceptable material.

3.2 FORMWORK

A. Metal forms shall be staked securely to the established lines and grades. Wood forms are acceptable on sharp curves and for closure sections.

B. Forms shall be cleaned and oiled prior to each use, without causing a discoloration of the concrete. Forms shall not be removed until such time as it will not be detrimental to the concrete. Upon removal of the forms minor defects shall be filled with mortar.

C. As soon as possible after the removal of the forms, backfill the voids adjacent to the curb, using acceptable material.

02506-3

3.3 JOINTS

A. Expansion joints, using 3/4-inch thick expansion joint material, cut to the cross-sectional area of the curb, shall be located at structures, changes of grade, ends of sections of curved curbing, cold joints and elsewhere at intervals not exceeding 50 feet.

B. Contraction joints, 3/16-inch wide and 2-inches deep shall be formed or sawed at intervals not exceeding ten (10’) feet.

C. All joints shall be neatly edged with a ¼-inch radius edging tool.

3.4 PLACING AND FINISHING CONCRETE

A. In accordance with PaDOT Specifications, Publication 408, latest edition.

B. Carbon copies of all concrete delivery slips, indicating quantity and mix design, shall be given to the Engineer, daily, for each delivery.

C. Concrete shall be placed in the forms in layers not exceeding 6 inches in depth and shall be spaded or vibrated sufficiently to eliminate voids.

D. As indicated or directed provide drainage openings through the curb, at the elevation and of the size required.

E. As indicated or directed, place depressed curb for drives or ramps for the handicapped.

F. Finish the top surface of the curb smoothly and evenly using a wood float, using an edging tool round the edges of the face and back of curb as indicated.

3.5 PROTECTION AND CURING

A. Curb shall be protected and cured for a period of not less than seventy-two (72) hours after completion.

B. If polyethylene sheets of burlap are used for curing they shall be properly weighted down and the concrete shall be kept moist through the curing period.

C. Concrete curb shall not be placed when the air temperature is below 40F unless approved precautions are taken to prevent freezing.

3.6 ACCEPTANCE

02506-4

A. All defects found shall be repaired or replaced by the Contractor, at his expense, to the full satisfaction of the Engineer prior to acceptance.

END OF SECTION