30-02507 Concrete Sidewalk ADA Ramps.pdf

PDF 109 KB Posted

Attached to
2025 Milling & Paving and ADA Ramps
Solicitation number
Not on record
Issued by
Montgomery County, Northern Cambria Borough, Pennsylvania

About this file

This document is a detailed technical specification section for concrete sidewalk and handicap ramp construction, prepared for the Pennsylvania Department of Transportation (PennDOT) under Job No. WCON 1509. The specification outlines comprehensive requirements for constructing 4-inch plain cement concrete sidewalks and handicap ramps, including a minimum 6-inch aggregate subbase. The contractor is responsible for furnishing all materials, equipment, labor, and supervision necessary to complete the project, with specific emphasis on meeting approved handicap ramp design standards as per PennDOT Publication 408 and design drawings RC-67M.

The technical specifications provide precise material requirements, including air-entrained concrete with a 3,750 p.s.i. strength, AASHTO No. 57 aggregate subbase, and specific guidelines for expansion joints, formwork, placement, finishing, and curing processes. The project mandates strict quality control measures, such as resetting utility boxes to finished grade, creating proper transverse grades, using specific curing materials, and ensuring a granular texture with rounded edges. Contractors must submit material certificates, follow detailed execution guidelines, and understand that any defects or water ponding will require complete replacement at their own expense, with final acceptance determined by the engineer's satisfaction.

View the file

Other files

File Type Posted
34-Front End Docs.pdf PDF
13-rco and bid documents D1 thru D-8.pdf PDF
10-01201 Preconstruction Conference.pdf PDF
21-W FORNANCE-11x17 Land.pdf PDF
15-Ordinance 22-10 - Amendment to Chapter 133, Article I titled Responsible Contractors (RCO) - EXECUTED 202301121156300469.pdf PDF
8-01700 Project Closeout.pdf PDF
23-WOOD-11x17 Land.pdf PDF
31-9695-2001-3 Sidewalk Detectable Warning Surface - Copy.pdf PDF
32-02930 Lawns Grasses.pdf PDF
6-01001 Special Provisions.pdf PDF
17-BUTTONWOOD-11x17 Land.pdf PDF
3-2025-09-16 2025 NORR CURB REPLACEMENT SCHEDULE.pdf PDF
20-E OAK-11x17 Land.pdf PDF
1-01025 Measurement Payment.pdf PDF
2-01010 Contractors Work.pdf PDF
19-JACKSON-11x17 Land.pdf PDF
22-W OAK-11x17 Land.pdf PDF
29-03300 Concrete.pdf PDF
16-E MARSHAL-11x17 Land.pdf PDF
7-01340 Shop Drawings, Samples.pdf PDF
27-02506 Concrete Curb.pdf PDF
26-PUB-72M 2010 Change-12.pdf PDF
9-PaDot Section - 411.pdf PDF
4-01720 Project Record Documents.pdf PDF
28-02260 Finish Grading.pdf PDF
35-penndot forms.pdf PDF
14-PaDot Section - 409.pdf PDF
12-wage rate determination.pdf PDF
18-E FORNANCE-11x17 Land.pdf PDF
11-PaDot Section - 491.pdf PDF
5-PaDot Section - 350.pdf PDF
24-NOBLE-11x17 Land.pdf PDF
33-PENNDOT 944 PROPOSAL FORM.pdf PDF
25-norristown 2025 paving scope of work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Job No. WCON 1509

02507-1

SECTION 02507

CONCRETE SIDEWALK AND HANDICAP RAMPS

PART 1 GENERAL

1.1 WORK INCLUDED

A. Contractor shall furnish all materials, implements, machinery equipment, tools, supplies, transportation, labor and supervision required to construct a four (4”) inch minimum plain cement concrete sidewalk or handicap ramp on a minimum four (6”) inch aggregate minimum subbase, including removal, adjustment, resetting or replacement of adjacent facilities including but not limited to traffic signs, fences and utility boxes. Every attempt shall be made by the contractor to meet an approved

HANDICAP RAMPS as per the attached details.

1.2 RELATED WORK SPECIFIED ELSEWHERE

A. Concrete Curb and Curb Walls - Section 02506

1.3 REFERENCE STANDARDS

A. Pennsylvania Department of Transportation (PennDOT) Publication 408, Specifications, latest edition.

1.4 SUBMITTALS

A. Material Certificates: Provide copies of material certificates signed by material producer and Contractor, certifying that each material item complies with, or exceeds, specified requirements.

02507-2

PART 2 PRODUCTS

2.1 MATERIALS

A. Accessible ramps shall conform to PennDOT publication 408 and design drawings

RC-67M.

B. Concrete sidewalks shall conform to PennDOT publication 408, section 676 and design drawings RC-67M.

A. Concrete:

1. Shall be air entrained (6%), 3,750 p.s.i. PennDOT Class AA concrete in accordance with Section 704 of PennDOT Specifications, Publication 408, latest edition. Maximum water-cement ratio shall not exceed 0.47.

B. Aggregate Subbase:

1. Shall be AASHTO No. 57 (PADOT 2A) material meeting the requirements of Section 703.2, PaDOT Specifications, Publication 408, latest edition.

C. Premolded Expansion Joint Filler:

1. Shall be ½-inch thick fiber expansion joint filler.

D. Curing Materials:

1. Shall be white polyethylene sheeting, burlap, or clear or white liquid membrane-forming curing compound in accordance with PaDOT

Specifications, Publication 408, latest edition.

PART 3 EXECUTION

3.1 SUBGRADE PREPARATION

A. The sidewalk area shall be excavated to the proposed subgrade line. The excavation shall include the removal of existing paving or sidewalk, if necessary and the disposal of all excess material.

B. The subgrade line shall be ten (10”) inches below and parallel to the finished grade.

When directed, remove and replace unsuitable material with acceptable material, as approved by the Engineer.

02507-3

C. The subgrade shall be compacted to a firm, even surface and moistened as necessary to prevent absorption of water from the concrete.

D. All sewer vent boxes, gas, and water service valve boxes shall be reset to finished grade.

3.2 AGGREGATE PLACEMENT

A. The aggregate shall be placed on the prepared subgrade to form properly compacted base 6-inches deep.

B. The top surface of the aggregate base shall be four (4”) inches below and parallel to the finished grade which shall have a transverse grade of ¼-inch per foot sloping towards the roadway, unless otherwise directed or indicated.

3.3 FORMWORK

A. Shall be acceptable wood or metal forms extending the full depth of the concrete.

B. The forms shall not be removed until at least twelve (12) hours after placing the concrete.

C. After the removal of forms, honeycombed areas shall be filled with mortar.

D. After the concrete has cured for at least forty-eight (48) hours and the forms have been removed, backfill the spaces adjacent to the sidewalk, using acceptable material.

3.4 JOINTS

A. Expansion joints shall be placed at the following locations: Opposite expansion joints in adjacent curb, between the sidewalk and curb, between the sidewalk and rigid structures, and elsewhere at intervals not exceeding twenty-eight (28’) feet transversely.

B. Contraction joints having a depth of 1-inch and a width of ¼-inch shall be formed by scoring the pavement at intervals not exceeding four (4’) feet both longitudinally and transversely or as directed by the Engineer to give a uniform appearance.

C. All joints shall be neatly edged with a ¼-inch radius edging tool.

02507-4

3.5 PLACING AND FINISHING

A. Concrete shall be placed on the moist aggregate base to a depth of 4-inches, compacted and screeded to the proper grade.

B. When the concrete has firmed to a suitable consistency, the surface shall be finished with a broomed finish.

C. The finish surface shall be granular in texture and all edges shall be rounded to a radius of ¼ inch.

D. In accordance with Section 704 of PaDOT Specifications, Publication 408, latest edition.

E. Carbon copies of all concrete delivery slips, indicating quantity and mix design, shall be given to the engineer, daily, for each delivery.

3.6 PROTECTION AND CURING

A. Traffic shall be excluded and the sidewalk shall be protected and cured for a period of not less than forty-eight (48) hours after completion.

B. If polyethylene sheets of burlap are used for curing they shall be properly weighted down and the concrete shall be kept moist through the curing period.

C. Concrete sidewalk shall not be placed when the air temperature is below 40F unless approved precautions are taken to prevent freezing.

3.7 ACCEPTANCE

A. All defects found shall be repaired or replaced by the Contractor, at his expense, to the full satisfaction of the Engineer prior to acceptance.

B. Concrete sidewalk which ponds water at any location is not acceptable and must be removed and replaced at the Contractor's expense. The extent of replacement will be determined by the Engineer.

END OF SECTION