7-01340 Shop Drawings, Samples.pdf

PDF 33 KB Posted

Attached to
2025 Milling & Paving and ADA Ramps
Solicitation number
Not on record
Issued by
Montgomery County, Northern Cambria Borough, Pennsylvania

About this file

This document is Section 01340, a technical specification section detailing requirements for Shop Drawings, Product Data, and Samples submission for a construction project. The section provides comprehensive guidelines for contractors regarding the preparation, submission, and review of technical documentation related to project materials and equipment. Contractors are required to submit Shop Drawings, Product Data, and Instruction Manuals electronically, with specific instructions for formatting and content.

The submission requirements mandate that all documents include detailed information such as submission dates, project title, contract number, names of contractor, supplier, and manufacturer, product identification, applicable standards, and any deviations from contract documents. Submittals must be clear, thorough, and include performance characteristics, dimensions, and clearances. Contractors must promptly submit documents in a sequence that prevents work delays, and they are expected to make corrections and resubmit documents as required by the Engineer until final approval is obtained. The specification emphasizes the importance of precise documentation and coordination between all project parties.

View the file

Other files

File Type Posted
34-Front End Docs.pdf PDF
13-rco and bid documents D1 thru D-8.pdf PDF
10-01201 Preconstruction Conference.pdf PDF
21-W FORNANCE-11x17 Land.pdf PDF
30-02507 Concrete Sidewalk ADA Ramps.pdf PDF
15-Ordinance 22-10 - Amendment to Chapter 133, Article I titled Responsible Contractors (RCO) - EXECUTED 202301121156300469.pdf PDF
8-01700 Project Closeout.pdf PDF
23-WOOD-11x17 Land.pdf PDF
31-9695-2001-3 Sidewalk Detectable Warning Surface - Copy.pdf PDF
32-02930 Lawns Grasses.pdf PDF
6-01001 Special Provisions.pdf PDF
17-BUTTONWOOD-11x17 Land.pdf PDF
3-2025-09-16 2025 NORR CURB REPLACEMENT SCHEDULE.pdf PDF
20-E OAK-11x17 Land.pdf PDF
1-01025 Measurement Payment.pdf PDF
2-01010 Contractors Work.pdf PDF
19-JACKSON-11x17 Land.pdf PDF
22-W OAK-11x17 Land.pdf PDF
29-03300 Concrete.pdf PDF
16-E MARSHAL-11x17 Land.pdf PDF
27-02506 Concrete Curb.pdf PDF
26-PUB-72M 2010 Change-12.pdf PDF
9-PaDot Section - 411.pdf PDF
4-01720 Project Record Documents.pdf PDF
28-02260 Finish Grading.pdf PDF
35-penndot forms.pdf PDF
14-PaDot Section - 409.pdf PDF
12-wage rate determination.pdf PDF
18-E FORNANCE-11x17 Land.pdf PDF
11-PaDot Section - 491.pdf PDF
5-PaDot Section - 350.pdf PDF
24-NOBLE-11x17 Land.pdf PDF
33-PENNDOT 944 PROPOSAL FORM.pdf PDF
25-norristown 2025 paving scope of work.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01340-1

SECTION 01340

SHOP DRAWINGS, PRODUCT DATA AND SAMPLES

PART 1 GENERAL

1.1 WORK INCLUDED

A. Submit Shop Drawings, Product Data, and Instruction Manuals required by Contract

Documents.

1.2 RELATED REQUIREMENTS

A. Definitions, and Additional Responsibilities of Parties: Conditions of the Contract.

1.3 SHOP DRAWINGS

A. Drawings shall be presented in a clear and thorough manner.

1. Details shall be identified by reference to sheet and detail, shown on

Contract Drawings.

1.4 PRODUCT DATA

A. Preparation

1. Clearly mark each copy to identify pertinent products or models.

2. Show performance characteristics and capacities.

3. Show dimensions and clearances required.

1.5 SUBMISSION REQUIREMENTS

A. Make submittals promptly in accordance with approved schedule, and in such sequence as to cause no delay in the Work or in the work of any other contractor.

B. Number of Submittals Required:

1. Shop Drawings: Submit electronically.

2. Product Data: Submit electronically.

C. Submittals Shall Contain:

01340-2

1. The date of submission and the dates of any previous submissions.

2. The Project title and contract number.

3. The names of:

a. Contractor.

b. Supplier.

c. Manufacturer.

4. Identification of the product, with the specification section number.

5. Applicable standards, such as ASTM or Federal Specification numbers.

6. Identification of deviations from Contract Documents.

7. Identification of revisions on resubmittals.

8. An 8 in. x 3 in. blank space for Contractor and Engineer stamps.

9. Contractor's stamp, initialed or signed, certifying to review of submittal, verification of products, field measurements and field construction criteria, and coordination of the information within the submittal with requirements of the Work and of Contract Documents.

1.6 RESUBMISSION REQUIREMENTS

A. Make any corrections or changes in the submittals required by the Engineer and resubmit until approved.

B. Shop Drawings and Product Data:

1. Revise initial drawings or data, and resubmit as specified for the initial submittal.

2. Indicate any changes which have been made other than those previously noted by the Engineer.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION