106 Gay Street

Unit 305 Philadelphia, PA 19127

Structural Evaluation of Existing Storefront and Surrounding Structure

Project Address: 1904 Cecil B Moore Ave, Philadelphia, PA

To Whom it May Concern, Scope of Service

This Existing Structural Conditions Report has been prepared for the proposed storefront improvements at the above-referenced property. A site visit was conducted on July 29th, 2026, and our findings are summarized herein.

The purpose of this report is to document observed structural deficiencies at the property. The scope of evaluation is limited to the front façade, storm doors, and foundation walls beneath the façade.

Observations were made at the front façade. The foundation wall at the building perimeter beneath the storefront was also observed. No other areas or structural components were evaluated. Framing above the existing storefront was concealed at the time of the site visit and could not be observed.

The existing structure consists of rough-sawn wood framing supported by multi-wythe brick masonry bearing walls.

Summary of Key Findings

The portions of the building observed during the site visit were generally found to be in good structural condition, with no significant structural distress observed within the accessible and visible areas of the evaluation.

Localized deficiencies were identified at the storefront and are primarily associated with deterioration at the existing storm door and adjacent entrance threshold. The existing storm door exhibits corrosion and deterioration, with localized loose and deteriorated brick masonry below. Additionally, the concrete entrance threshold is cracked and uneven, and portions of the supporting brick masonry observed from the basement are loose, deteriorated, or missing.

These conditions are localized and can be addressed as part of the proposed storefront improvement work. Recommended repairs are described in the following sections of this report. No evidence of broader structural distress was observed within the limited areas evaluated.

16 August 2026

PRESTONSTRUCTURAL

SOLUTIONS.COM

+1 215 701 3375

INFO@PRESTONSTRUCTURAL

SOLUTIONS.COM

Required Structural Improvements

Item #1

Location: Sidewalk Along Cecil B. Moore Ave.

Deficiency: The existing storm door exhibits corrosion and deterioration. The brick masonry immediately below the storm door is loose, deteriorated, and rubbling in nature.

Suggested Repair: Replace the existing storm door. Carry an allowance for minor brick masonry repair below the storm door as required to provide a suitable substrate for attachment of the replacement door. Carry an allowance for localized patching of the surrounding concrete slab-on-grade as required to complete the work.

Item #2

Location: Front Facade

Deficiency: The concrete at the door threshold is cracked and uneven. When observed from the basement, the brick masonry supporting the slab-on-grade at this location was observed to be loose, deteriorated, or missing in some areas.

Suggested Repair: The contractor should carry an allowance for removal and replacement of the concrete at this location. The replacement section can be formed from the basement and constructed as a monolithic concrete pour to provide a new, level walking surface while extending down to competent masonry within the basement wall for support.

Assumptions, Limitations, and Reliance

This report has been prepared based on visual observations made during a site visit and on information available to Preston Structural Solutions, LLC at the time of the assessment. The evaluation was limited in nature and did not include comprehensive destructive testing, demolition, or verification of concealed or inaccessible conditions, except where limited exploratory demolition was observed in the field.

Preston Structural Solutions, LLC is not the original engineer of record for the structure and has not performed a complete review or verification of the original structural design, calculations, or construction documents, except where explicitly noted. The findings and recommendations herein shall not be interpreted as a certification of the overall structural adequacy of the building.

The existing framing above the storefront, supporting the overlying masonry, was not observable at the time of the site visit. This framing should be evaluated by the contractor once exposed. If significant deterioration is observed, or if there is uncertainty regarding the adequacy of the existing framing, Preston Structural Solutions, LLC should be notified for further evaluation.

The observations and conclusions presented herein are limited to conditions observed at the time of the site visit. Actual conditions may di5er as construction progresses or as concealed conditions are exposed.

Responsibility for construction means, methods, sequencing, temporary shoring, and job site safety remains solely with the contractor. If conditions encountered during construction di5er materially from those described herein, Preston Structural Solutions, LLC should be notified for further evaluation.

This report is intended for use by the client and project team for the purpose of evaluating and addressing the structural conditions described herein. Reliance by others, or use of this report for other purposes, is not authorized without written consent from Preston Structural Solutions, LLC.

Closing

We appreciate the opportunity to assist with the evaluation of the existing structural conditions at this project.

We are available to discuss the findings presented in this report, clarify recommended repair approaches, and assist with coordination as the project progresses.

Additional engineering services may be required during the implementation of repairs, upon exposure of concealed conditions, or as coordination with other project stakeholders advances. Further documentation and engineering design will be required as the project moves forward and as additional information becomes available.

Please contact our o5ice with any questions or to discuss next steps.

Sincerely, Ryan Preston, MS, PE

Founder & Principal Engineer

Preston Structural Solutions LLC

2026-08-16T16:35:39-0400
Ryan Preston
I am the author of this document

File details come from the government source that posted it. Updated .