WINDOW SIGNAGE ALLOWANCE

PER PHILADELPHIA CODE 14-904

GLASS AREA 17.5+17.9+17.5+12.3 = 65.2 SF

MAX. SIGNAGE AREA (20%) 13 SF

PROPOSED SIGNAGE AREA 7.5+.7+1.2 = 9.4 SF - IN COMPLIANCE

DRAWN BY:

SCALE:

N O

T

FO

R C

O N

ST

R

UC

TI

O N

PROJECT:

SWRL STUDIO, LLC

2715 Folsom St Philadelphia, PA 19130

©2026

DATE:

PROJECT NO:

NOTES:

swrl studio

NO. DATE DESCRIPTION

ARCHITECT

STRUCTURAL ENGINEER

PRESTON STRUCTURAL SOLUTIONS, LLC

106 Gay Street, Unit 305, Philadelphia, 19127

1/4" = 1'-0"

A000

DH

COVER SHEET

2224 RIDGE

PROCESS

JUNIOR'S

2224 RIDGE AVE

PHILADELPHIA, PA 19121

10/24/26 2026_02

1 08/21/2025 PERMIT SUBMISSION

PROJECT LOCATION

PHILADELPHIA, PA 19121

SCOPE:

EXTERIOR RENOVATION OF EXISTING BARBERSHOP INCLUDING NEW

AWNING, EXTERIOR WALL SIGN AND WINDOW SIGNAGE

APPLICABLE CODE SUMMARY:

PHILADELPHIA BUILDING CODE (2021 INTERNATIONAL BUILDING CODE)

PHILADELPHIA EXISTING BUILDING CODE (2021 INTERNATIONAL EXISTING BUILDING CODE)

PHILADELPHIA ELECTRICAL CODE (2020 NATIONAL ELECTRIC CODE)

PROJECT DATA:

JURISDICTION: CITY OF PHILADELPHIA

ZONING: CMX-2 NEIGHBORHOOD COMMERCIAL MIXED-USE

BUSINESS NAME: PROCESS JUNIOR'S BARBERSHOP

PHOTO : EXISTING RENDERING : PROPOSED

2224 RIDGE AVE BASE SCOPE - DEMO

DB-01 DEMOLISH STUCCO BETWEEN CANOPY AND SECOND STORY WINDOWS TO

PREPARE FOR NEW WORK

DB-02 DEMOLISH EXISTING CANOPY. REPORT CONDITION OF STRUCTURAL BEAM TO

DESIGN TEAM

DB-03 UNINSTALL EXISTING SECURITY CAMERAS, STORE AND PREPARE FOR

REINSTALLATION

DB-04 DEMOLISH STUCCO TO PREPARE FOR NEW BRICK VENEER

BASE SCOPE - PROPOSED

B-01 NEW 1/2" PVC WALL SIGNAGE ON PAN

B-02 PREP & PAINT EXISTING OH ROLLING GATE. INSPECT FOR PROPER FUNCTION

B-03 NEW ALUMINUM AWNING

B-04 NEW LIGHTING INSTALLED ON UNDERSIDE OF AWNING - 4 FIXTURES

B-05 NEW VINYL WINDOW SIGNAGE

B-07 NEW THIN BRICK VENEER, 82 SF, BOD: GLEN-GERY HERITAGE S

B-08 NEW ALUMINUM CLADDING PAINTED BLACK TO MATCH STOREFRONT

B-09 PAINT EXISTING TRIM AND RESIDENTIAL DOOR, BLACK

B-10 REINSTALL EXISTING SECURITY CAMERAS

AD-ALT SCOPE - PROPOSED

A-01 NEW CONCRETE TOP COAT, BROOM FINISH

SHEET INDEX

SHEET

NUMBER SHEET NAME BI

D S

ET

0/

/2

A000 COVER SHEET ●

A101 EXTERIOR ELEVATIONS ●

S001 GENERAL NOTES ●

S100 STRUCTURAL PLANS & SECTIONS ●

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

GENERAL NOTES:

ALL DRAWINGS ARE TO SCALE AS INDICATED. THE CONTRACTOR MUST

VERIFY THE SCALE BEFORE BEGINNING CONSTRUCTION. DO NOT SCALE

DIRECTLY FROM THE DRAWINGS.

IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO OBTAIN ALL

PERMITS FOR PLUMBING AND ELECTRICAL WORK, AND ANY OTHER WORK

NOT PERMITTED UNDER A GENERAL BUILDING PERMIT.

WORK NOT INDICATED ON A PART OF THE DRAWINGS BUT REASONABLY

IMPLIED TO BE SIMILAR TO THAT SHOWN AT CORRESPONDING PLACES,

SHALL BE REPEATED.

CONTRACTOR SHALL COORDINATE OPENINGS SHOWN ON THE DRAWINGS.

CONTRACTOR SHALL VERIFY AND/OR ESTABLISH ALL EXISTING CONDITIONS

AND DIMENSIONS AT THE SITE.

IF THE EXISTING FIELD CONDITIONS DO NOT PERMIT THE INSTALLATION OF

THE WORK IN ACCORDANCE WITH THE DETAILS SHOWN, THE CONTRACTOR

SHALL NOTIFY THE ARCHITECT IMMEDIATELY AND PROVIDE A SKETCH OF

THE CONDITION WITH CONTRACTOR’S PROPOSED MODIFICATION OF THE

DETAILS GIVEN ON THE CONTRACT DOCUMENTS.

IT SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR AND ALL

SUB-CONTRACTORSTO COORDINATE THE WORK AND VERIFY ALL

DIMENSIONS AND INSPECT CONDITIONS OF PRIOR WORK BY ALL TRADES

BEFORE PROCEEDING WITH ANY WORK. UNACCEPTABLE OR INCORRECT

PRIOR WORK SHALL BE REPAIRED OR REPLACED BEFORE STARTING WORK.

PROCEEDING WITH THE WORK SHALL CONSTITUTE ACCEPTANCE OF PRIOR

WORK.

WHERE WORK INVOLVES EXISTING SUPPORTING STRUCTURE, THE

CONTRACTOR SHALL PROVIDE SHORING AND PROTECTION REQUIRED TO

INSURE THE STRUCTURAL INTEGRITY OF THE EXISTING STRUCTURE.

UNLESS SPECIFICALLY SHOWN OR NOTED ON THE DRAWINGS, NO

STRUCTURAL MEMBER SHALL BE CUT, NOTCHED, BORED OR OTHERWISE

MODIFIED WITHOUT THE PERMISSION OF THE STRUCTURAL ENGINEER OF

RECORD

ALL PRODUCTS AND MATERIALS TO BE INSTALLED FOLLOWING

MANUFACTURERS' RECOMMENDATIONS.

CONTRACTOR SHALL NOTIFY THE ARCHITECT OF ANY DISCREPANCIES IN

THE DOCUMENTS PRIOR TO PROCEEDING WITH ANY WORK INVOLVED.

THE PURPOSE OF THESE DRAWINGS IS FOR THE CONTRACTOR TO INCLUDE

ALL THE LABOR, MATERIALS AND SERVICES REQUIRED FOR THE

COMPLETION OF ALL WORK SHOWN OR REASONABLY IMPLIED BUT NOT

LIMITED TO THAT EXPLICITLY SHOWN IN THE DOCUMENTS.

1.

2.

3.

4.

5.

PROJECT NOTES:

"BASE SCOPE" MEANS THE MINIMUM SCOPE OF WORK. ADDITIONAL SCOPE

MAY BE REQUIRED TO COMPLY WITH CODE, LIFE SAFETY AND STRUCTURAL

REQUIREMENTS.

"AD-ALT SCOPE" MEANS ADDITIONAL AND ALTERNATIVE SCOPE. THE

OWNER HAS THE RIGHT TO INCLUDE OR EXCLUDE ANY OR ALL ITEMS

IDENTIFIED IN THE FINAL SCOPE OF WORK

PAINTING APPLIES TO FIRST LEVEL ONLY UNLESS NOTED OTHERWISE

FOR NEW OR REPLACEMENT GATES, INSTALL SEE-THROUGH GRILLES ONLY

WINDOW DECALS TO HAVE CLEAR BACKGROUNDS RATHER AN OPAQUE

PANELS OR FULL-WINDOW COVERING, TYP.

AD-ALT SCOPE - DEMO

DA-01 DEMOLISH TERRAZZO AND PREPARE FOR NEW CONCRETE TOP COAT

A101

B-01B-01

B-03B-03

B-10B-10

B-08B-08

B-07B-07

B-09B-09

B-05B-05

B-02B-02

B-04B-04

A-01

17.5 sf 17.5 sf17.9 sf

12.3 sf

.7 sf 1.2 sf

7.5 sf

EXISTING ALUMINUM PANEL

TO REMAIN

DB-01DB-01

DB-02DB-02

DB-03DB-03

DB-04DB-04

DA-01

TREE, TO BE PROTECTED

THROUGHOUT WORK,

NEW CONCRETE TOPPING,

BROOM FINISH

A101

LINE OF AWNING ABOVE

20"88"88"

RECESSED LIGHTS ABOVE

REINSTALL EXISTING

SECURITY CAMERAS

REINSTALL EXISTING

SECURITY CAMERAS

44"44"

NEW METAL AWNING, COLOR TBD

NEW SIGNAGE, SEE

ELEVATIONS

A101

REINSTALL EXISTING

FLOOD LIGHT

B-07

B-09

A-01

A101

NEW METAL AWNING

NEW SIGNAGE

REPAIR EXISTING STUCCO AS NEEDED

NEW WEEP SCREED AT STUCCO REPAIR AND

THROUGH METAL FLASHING

VINYL ADRESS

EXTRA LONG Z-CLIP ANCHOR AS

NECESSARY, SEE STRUCTURE

36"

NEW WEEP SCREED @ STUCCO

REPAIR, THROUGH FLASHING OVER

NEW WORK

NEW BENT ALUMINUM CORNICE

PROFILE

NEW SIGNAGE LETTERING

NEW 2" ALUMINUM SIGNAGE PAN

NEW METAL AWNING

RECESSED LIGHTING

8"

EXPANDED METAL, PAINTED. BOD:

MCNICHOLS TYPE 304 3/4" NO. 16

FLATTENED, 79% OPEN AREA

ALIGN

FIBER CEMENT PANEL ON

CEILING. BOD: HARDIE PANEL HZ5

WINDOW SIGNAGE ALLOWANCE

PER PHILADELPHIA CODE 14-904

GLASS AREA 17.5+17.9+17.5+12.3 = 65.2 SF

MAX. SIGNAGE AREA (20%) 13 SF

PROPOSED SIGNAGE AREA 7.5+.7+1.2 = 9.4 SF - IN COMPLIANCE

DRAWN BY:

SCALE:

N O

T

FO

R C

O N

ST

R

UC

TI

O N

PROJECT:

SWRL STUDIO, LLC

2715 Folsom St Philadelphia, PA 19130

©2026

DATE:

PROJECT NO:

NOTES:

swrl studio

NO. DATE DESCRIPTION

ARCHITECT

STRUCTURAL ENGINEER

PRESTON STRUCTURAL SOLUTIONS, LLC

106 Gay Street, Unit 305, Philadelphia, 19127

As indicated

A101

FC

EXTERIOR

ELEVATIONS

2224 RIDGE

PROCESS

JUNIOR'S

2224 RIDGE AVE

PHILADELPHIA, PA 19121

10/24/26 2026_02

SCALE: 1/4" = 1'-0"

2 ELEVATION - RIDGE AVE PROPOSED

SCALE: 1/4" = 1'-0"

1 ELEVATION - RIDGE AVE DEMO

SCALE: 1/2" = 1'-0"

3 FLOOR PLAN - PROPOSED

SCALE: 1/2" = 1'-0"

4 WALL SECTION

SCALE: 1/2" = 1'-0"

5 ENLARGED ELEVATION - RIDGE AVE

SCALE: 1" = 1'-0"

6 AWNING DETAIL

BASE SCOPE - DEMO

DB-01 DEMOLISH STUCCO BETWEEN CANOPY AND SECOND STORY WINDOWS TO

PREPARE FOR NEW WORK

DB-02 DEMOLISH EXISTING CANOPY. REPORT CONDITION OF STRUCTURAL BEAM TO

DESIGN TEAM

DB-03 UNINSTALL EXISTING SECURITY CAMERAS, STORE AND PREPARE FOR

REINSTALLATION

DB-04 DEMOLISH STUCCO TO PREPARE FOR NEW BRICK VENEER

BASE SCOPE - PROPOSED

B-01 NEW 1/2" PVC WALL SIGNAGE ON PAN

B-02 PREP & PAINT EXISTING OH ROLLING GATE. INSPECT FOR PROPER FUNCTION

B-03 NEW ALUMINUM AWNING

B-04 NEW LIGHTING INSTALLED ON UNDERSIDE OF AWNING - 4 FIXTURES

B-05 NEW VINYL WINDOW SIGNAGE

B-07 NEW THIN BRICK VENEER, 82 SF, BOD: GLEN-GERY HERITAGE S

B-08 NEW ALUMINUM CLADDING PAINTED BLACK TO MATCH STOREFRONT

B-09 PAINT EXISTING TRIM AND RESIDENTIAL DOOR, BLACK

B-10 REINSTALL EXISTING SECURITY CAMERAS

AD-ALT SCOPE - PROPOSED

A-01 NEW CONCRETE TOP COAT, BROOM FINISH

AD-ALT SCOPE - DEMO

DA-01 DEMOLISH TERRAZZO AND PREPARE FOR NEW CONCRETE TOP COAT

A.B. ANCHOR BOLT

A.F.F. ABOVE FINISH FLOOR

ADDL. ADDITIONAL

ALT. ALTERNATE

ARCH. ARCHITECT

B.C.E. BOTTOM CHORD EXTENSION

B.O. BOTTOM OF

BLDG. BUILDING

BM. BEAM

BOTT. BOTTOM

BRG. BEARING

BSMT. BASEMENT

BTWN. BETWEEN

CL CENTERLINE

CANT. CANTILEVER

CMU CONCRETE MASONRY UNIT

COL. COLUMN

CONC. CONCRETE

CONN. CONNECTION

CONT. CONTINUOUS

CTRD. CENTERED

Ø DIAMETER

DWG. DRAWING

E.F. EACH FACE

E.O.D. EDGE OF DECK

E.O.S. EDGE OF SLAB

E.W. EACH WAY

EA. EACH

EL. ELEVATION

ELEV. ELEVATOR

EMBED. EMBEDMENT

EQ. EQUAL

EQUIP. EQUIPMENT

EWB EACH WAY BOTTOM

EX. EXISTING

EXIST. EXISTING

EXP. EXPANSION

EXT. EXTERIOR

FDN. FOUNDATION

FIN. FINISH

FLR. FLOOR

FT. FEET

FTG. FOOTING

GA. GAGE

GALV. GALVANIZED

H.P. HIGH POINT

HORIZ. HORIZONTAL

I.F. INSIDE FACE

IN. INCHES

INFO. INFORMATION

INT. INTERIOR

JT. JOINT

EWT EACH WAY TOP

BP_ BEARING PLATE

GB_ GRADE BEAM

k KIP k-ft KIP-FEET

L.P. LOW POINT

L.W. LIGHT WEIGHT

LLH LONG LEG HORIZONTAL

LLV LONG LEG VERTICAL

LWB LONG WAY BOTTOM

M.E.P. MECHANICAL ELECTRICAL PLUMBING

M.S.T. METAL STUD TRUSS

MAX. MAXIMUM

MECH. MECHANICAL

MEZZ. MEZZANINE

MFR. MANUFACTURER

MIN. MINIMUM

MISC. MISCELLANEOUS

N.T.S. NOT TO SCALE

N.W. NORMAL WEIGHT

o/c ON CENTER

PL PLATE

PC PILE CAP

PSF POUNDS PER SQUARE FOOT

PSI POUNDS PER SQUARE INCH

PTN. PARTITION

REINF. REINFORCEMENT

REQ'D. REQUIRED

RET'G. RETAINING

S.F. STEP FOOTING

S.O.G. SLAB ON GRADE

SCHED. SCHEDULE

SECT. SECTION

SIM. SIMILAR

SPECS. SPECIFICATIONS

STIFF. STIFFENER

STRUCT. STRUCTURAL

SWB SHORT WAY BOTTOM

T&B TOP AND BOTTOM

T. TOP

T.O. TOP OF

T.O.C. TOP OF CONCRETE

T.O.S. TOP OF STEEL

T.S. THICKENED SLAB

TCELE TOP CHORD EXTENSION LEFT END

TCERE TOP CHORD EXTENSION RIGHT END

TDS TURN DOWN SLAB

THK. THICK OR THICKENED

TYP. TYPICAL

U.N.O. UNLESS NOTED OTHERWISE

V.I.F. VERIFY IN FIELD

VERT. VERTICAL

W.R.T. WOOD ROOF TRUSS

w/ WITH

WWF WELDED WIRE FABRIC

P.C. PRECAST

P.A.F. POWDER ACTUATED FASTENER

M.P. MASONRY PIER

N.B.L. NON BEARING LINTEL

W.P. WALL PLATE

W.C. WET COLUMN

ABBREVIATIONS

PROJECT DESCRIPTION

1. Project consists of a facade improvment to an existing mixed use building. Existing superstructure is

3 levels above grade and 1 level below grade. Foundations consist of CMU and stone foundation walls. Superstructure is wood floor sheathing over rough sawn wood framing.

2. This description is for general orientation only. The General Contractor is responsible for all scope items described in the drawings and project specifications as well as for all material and labor that can reasonably be inferred there from.

GENERAL APPLICATION

1. These structural drawings are intended to be used in conjunction with the project’s architectural, mechanical, and electrical drawings. All disciplines must be reviewed collectively to fully understand the design intent and construction requirements.

2. Contractors shall not bid or proceed with any portion of the work without thoroughly reviewing all relevant project documents, including but not limited to architectural, mechanical, and electrical drawings and specifications.

3. Any perceived discrepancies, omissions, or ambiguities in the structural drawings shall be promptly brought to the attention of the Structural Engineer. No related work shall proceed until the Engineer has issued written clarification or direction.

4. The Contractor is responsible for notifying the Structural Engineer in writing of any proposed deviation or substitution from the contract documents. Approval or review of shop drawings, product data, or similar submittals by the Structural Engineer shall not constitute acceptance of deviations unless such deviations have been clearly and explicitly identified in writing at the time of submission.

MISCELLANEOUS NOTES

1. The Contractor is solely responsible for implementing and maintaining all safety measures, programs, and precautions associated with the execution of the work on this project.

2. The Contractor shall protect all persons and property, both on-site and adjacent to the project site, from injury, damage, or loss. Responsibility for such protection lies exclusively with the Contractor.

3. The selection and execution of construction means, methods, techniques, sequences, and procedures—including the erection of structural elements—are entirely the responsibility of the Contractor.

4. The structure is engineered to perform as a complete system only upon full completion and under the design loads specified. The Contractor is responsible for ensuring construction-phase stability, including evaluating the structure’s capacity to support construction loads. Provide all temporary bracing, shoring, and other measures required to maintain stability and safety during construction.

5. No openings or modifications to structural elements—including changes in size, shape, or location— shall be made without prior written approval from the Structural Engineer.

6. Openings measuring 1'-4" or less on a side are typically not shown on the structural drawings. Refer to the drawings of other design disciplines for the locations and dimensions of such openings.

7. Openings in floors and roofs for utility penetrations are not detailed on structural drawings. The Contractor shall coordinate the required locations and dimensions with the respective trade responsible for the utility work.

8. All proposed openings in structural members shall be clearly indicated on shop drawings and submitted for review. Any opening not shown on the structural drawings is subject to written acceptance and shall not be implemented without prior approval.

9. Fireproofing requirements for structural components are not depicted on these drawings. Refer to project specifications and architectural documents for fireproofing locations and requirements.

10. Do not scale these drawings. Use only the dimensions shown. In the event of discrepancies or conflicts, obtain clarification from the Architect and Structural Engineer before proceeding with affected work.

11. No structural repairs, alterations, or modifications shall be undertaken without prior review and written approval from the Structural Engineer. All proposed modifications must be supported by detailed drawings and structural calculations prepared by a licensed Professional Engineer registered in the state where the project is located and retained by the Contractor.

12. If framed floors are used for staging or temporary material storage, the Contractor shall verify that the applied unit loads do not exceed the design loads of the floor framing system.

QUALITY ASSURANCE AND QUALITY CONTROL

1. The Contractor is solely responsible for ensuring the quality of all workmanship and materials, including those provided by subcontractors and suppliers.

2. Testing or inspections performed by or on behalf of the Owner do not relieve the Contractor of the obligation to perform all work in full compliance with the Contract Documents.

3. Workmanship: The Contractor shall correct, at their own expense, any work that fails to meet specified requirements.

4. All deficient work shall be corrected using methods acceptable to the Architect. Any additional costs incurred by the Architect in reviewing or approving corrective work shall be the responsibility of the Contractor.

5. Testing and special inspections required by the structural drawings, applicable building code, and the local authority having jurisdiction shall be performed by the Owner’s Testing Agency. The agency must comply with ASTM E329 and shall, upon completion of the work, provide a certificate of compliance signed by a Professional Engineer licensed in the state where the project is located, and responsible for the special inspections and testing.

6. The individual overseeing soils and foundation testing on behalf of the Testing Agency shall be a licensed Professional Engineer specializing in geotechnical engineering, herein referred to as the Geotechnical Engineer. This individual is responsible for verifying that soils, earthwork, and foundations conform to the foundation design and the referenced geotechnical report. Refer to the “Foundations” section of these General Notes for further requirements.

7. Refer to the “Special Inspections” section of these General Notes for a detailed list of required inspections and testing.

SPECIAL INSPECTION

1. Special inspections and testing shall be performed in accordance with the requirements of the applicable building code, the local authority having jurisdiction, and the construction documents.

Refer to the “Quality Assurance” section of these General Notes for additional guidance.

2. The Contractor shall coordinate and schedule all required inspections and testing in advance of commencing work subject to such requirements. Reasonable notice must be provided to the Special Inspector to facilitate timely performance.

3. Any deficiencies identified during inspections or testing shall be corrected to the satisfaction of the Testing Agency before acceptance of the work.

4. Inspections conducted by local code officials do not substitute for the inspections and testing required to be performed by the Owner’s Testing Agency, as stipulated in the construction documents.

SPECIFICATIONS

1. These General Notes are intended to function as the structural portion of project specifications.

SUBMITTALS

1. Refer to the “Materials” section of these General Notes for a list of items requiring shop drawing submittals.

2. Submit all required documentation (e.g., manufacturer’s product data, shop drawings, etc.) in electronic format (PDF or equivalent).

3. Reproducible copies of the contract documents shall not be used as the basis for shop drawings or submittals.

4. All submittals shall be transmitted directly to Preston Structural Solutions LLC for review and further distribution.

5. Prior to submission, submittals must be reviewed by both the Contractor and applicable

Subcontractors. Each drawing shall bear the Contractor’s approval stamp, confirming coordination of dimensions, quantities, and interface with other trades in accordance with the contract documents.

6. Allow a minimum of 14 calendar days for the review process following receipt of complete submittal packages.

7. Reviewed submittals will be returned to the Contractor with comments, if any, by Preston Structural Solutions LLC in electronic format.

COMMON NAIL DIMENSIONS

Common Nail (Steel Wire) Minimum Length (in)

6d

0.131

0.148

2 1/2

3 1/20.162

Minimum Diameter (in)

8d

10d

16d

0.113

DESIGN VALUES FOR DIMENSIONAL LUMBER

Species & Grade Compressive

Stress

Select Structural

Flexural Stress

1,400 psi

No. 1

No. 2

Stud

975 psi

850 psi

675 psi

1,500 psi

1,350 psi

1,300 psi

800 psi

Horizontal Shear Stress

150 psi

150 psi

150 psi

150 psi

Modulus of Elasticity

1,600 ksi

1,500 ksi

1,300 ksi

1,200 ksi

HEM-FIR (HF)

Building Code: 2021 International Building Code (Note 1)

Structural Design Criteria

Local Jurisdiction: Philadelphia, PA Risk Category: II

Foundations:

Notes:

1. The governing building code defines the applicable edition of referenced codes and standards. Where governing building code does not define referenced codes and standards, the latest edition shall be used.

2. Foundation design criteria determined utilizing 2021 IBC minimum bearing capacity tables. Contractor shall verify in-situ soils reflect the provided bearing capacity.

Wind Loading Basic Wind Speed Exposure Category

Vult= 114 MPH B

Seismic Loading Seismic Importance Factor, Ie 1.00 Mapped Spectral Response Acceleration Ss 0.181 S1 0.047 Site Class D Spectral Response Coefficients Sds 0.193 Sd1 0.076 Snow Loading Ground Snow Load, Pg 25 PSF Minimum Flat Roof Snow Load, Pf 21 PSF

Allowable Bearing Capacity 2,000 PSF Minimum Frost Depth 36 IN

GCpi +/-0.18 Ultimate Components & Cladding Wind Design Pressure, PSF 20ft2 50ft2 100ft2

Wall Pressures

-22.2/20.4 -21.0/19.2 -20.0/18.2Interior (Zone 4) -26.6/20.4 -24.1/19.2 -22.2/18.2Corner (Zone 5)

Importance Factor, IS 1.0

WOOD FRAMING

GENERAL:

1. All wood construction shall conform to ANSI/AWC NDS unless otherwise noted. A current copy of this standard shall be maintained on-site by the Contractor at all times.

2. Refer to the “Wood Materials Tables” for specified material types and properties.

3. Qualifications: All carpentry work shall be performed by tradespeople experienced with projects of comparable size and complexity and familiar with conventional light-frame construction and the minimum fastening requirements of the IBC.

PRODUCTS:

1. All wood framing shall be at a moisture content of 19% or less and shall be marked S-Dry (surface dried) or KD (kiln dried).

2. Unless noted otherwise, all sizes noted on these drawings are nominal. Actual sizes are based on

"Minimum Dressed-Dry" dimensions according to American Softwood and Lumber Standard PS20-10.

Members which the architect, engineer, or inspector judge to be misgraded shall be reinspected by a qualified lumber grader. Members which have permissible grade characteristics in such combination to affect the performance of the member are also subject to replacement at the discretion of the architect, engineer, or inspector.

3. Unless noted otherwise, all manufactured framing sizes are based on specified manufacturers published information.

4. See plan notes for wall framing material and spacing.

5. Wood I-joists: where framing members are noted TJI on the drawings, use engineered products by

Weyerhaeuser or approved equal.

6. Structural Panels: Sheathing for roofs and walls shall conform to APA PS-2 standards. All panels shall be Exposure 1, unless noted otherwise.

7. Sills: Sill plates shall be pressure treated Southern Pine stamped to show compliance with AWPA standards.

8. Wood stud wall framing elements including but not limited to headers, top plates, sole plates, cripple studs, trimmers, and sills shall match stud member specification, unless noted otherwise.

CONNECTORS:

1. All connectors, anchors, bolts, and fasteners in contact with preservative-treated wood shall be either hot-dipped galvanized (G90 or G185) or stainless steel (Type 304 or 316).

2. Provide anchor bolts at all foundation top surfaces to secure sill plates. See typical details for anchor size, spacing, and embedment.

3. J- and L-type anchor bolts are acceptable for sill plate anchorage.

4. Provide plate washers at all anchor bolt connections in shear walls. Refer to the “Typical Wood Shear

Wall” details for configuration.

5. All nailing shall meet or exceed the minimum requirements of IBC Table 2304.9.1 unless more stringent requirements are indicated in the drawings or notes.

6. Nails shall conform to ASTM F1667 and be steel common wire type.

7. Pre-drill nail holes where necessary to prevent splitting of wood members.

8. Steel plates used in wood construction shall conform to ASTM A36.

9. Bolts shall conform to ASTM A307.

10. Exposed bolts not in contact with treated wood may be plain, uncoated steel.

11. Bolt holes shall be 1/16" larger than the bolt diameter unless specified otherwise.

12. All bolts shall be retightened before enclosure or concealment.

13. Lag screws shall penetrate a minimum of 8 times the shaft diameter into the main member unless otherwise noted.

14. Diagonal (toe-nail) lag screws shall have a minimum edge distance of 4 times the shaft diameter.

INSTALLATION:

1. Built-up wood columns concealed within wall framing may be constructed using multiple 2x members.

Do not splice individual laminations. Refer to typical details for required nailing.

2. At roof and floor levels, install wood panels with their long dimension perpendicular to supports and stagger short edges.

3. Refer to plan notes for nailing patterns at roof and floor sheathing.

4. Refer to the plans for locations requiring special blocking and additional fastening.

5. Refer to plan notes for vertical wall sheathing requirements.

6. For all designated shear walls, sheathing contributes to lateral resistance. Refer to typical details for required fastening of sheathing to framing members.

7. Provide solid blocking with flat 2x4s at all sheathing edges within shear walls.

FRAMING TOLERANCES:

1. Wall and partition layout: ±¼" from intended position.

2. Plates and runners: Deviation not to exceed ¼" in 8'-0" from a straight line.

3. Studs: Out-of-plumb tolerance of ¼" in 8'-0", not cumulative.

4. Face of framing: Deviation from true plane not to exceed ¼" in 8'-0".

WOOD STRUCTURAL PANEL REQUIREMENTS

Supporting Element Minimum Thickness

Roof over roof joists

24 OC Single Floor

32/16

15/32"

APA Span Rating

32/16

23/32"

15/32"

Floors (Sturd-I T&G)

Walls

LIGHT GAUGE METAL FRAMING

1. Light-gage metal framing shall be fabricated and installed in accordance with these drawings, the project specifications, and the latest editions of AISI S100, AISI S240, and ASTM C955. Shop drawings shall be submitted for review prior to fabrication and shall include member sizes, thicknesses, connections, bracing, bridging, openings, and all other details necessary for fabrication and installation.

2. All metal stud lintels shall be fabricated as detailed on the structural drawings. Shop drawings shall include lintel configurations, connections, and reinforcement.

3. Structural cold-formed steel framing shall be fabricated from steel conforming to ASTM A1003/A1003M and shall be hot-dip galvanized in accordance with ASTM A653/A653M. Unless noted otherwise:

A. 54 mil (16 ga.) and thicker: Fy = 50 ksi B. 43 mil (18 ga.) and 33 mil (20 ga.): Fy = 33 ksi C. Provide G60 minimum coating for typical framing and G90 coating where specifically indicated on the structural drawings.

4. Member thicknesses indicated on the structural drawings are minimum design thicknesses. Gauge designations, where provided, are for reference only.

Substituted members shall have equal or greater thickness, yield strength, and section properties than the members specified.

5. All welding of cold-formed steel members shall be performed by qualified welders in accordance with AWS D1.3.

6. Connections shall be installed using the fastener type, quantity, and spacing indicated on the structural drawings. Where not specifically detailed, connections shall be installed in accordance with the manufacturer's published requirements and shall develop the required design strength.

7. Cut cold-formed steel members using saws or shears. Flame cutting is not permitted. Field cutting, notching, or modification of structural framing beyond manufacturer-provided punchouts shall not be permitted without approval of the Engineer of Record.

8. Provide bridging, bracing, blocking, deflection tracks, and all required accessories as shown on the structural drawings or as required by AISI S240 for a complete and stable installation.

9. Field conditions that differ from those shown on the structural drawings shall be reported to the Engineer of Record prior to fabrication or installation.

DRAWN BY:

SCALE:

N O

T F

O R

C O

N S

T R

U C

T

IO

N

PROJECT:

SWRL STUDIO, LLC

2715 Folsom St Philadelphia, PA 19130

©2026

DATE:

PROJECT NO:

NOTES:

swrl studio

NO. DATE DESCRIPTION

ARCHITECT

STRUCTURAL ENGINEER

PRESTON STRUCTURAL SOLUTIONS, LLC

106 Gay Street, Unit 305 Philadelphia, PA 19127

3/4" = 1'-0"

S001

REP

GENERAL

NOTES

2224 RIDGE

PROCESS

JUNIOR'S

2224 RIDGE AVE

PHILADELPHIA, PA, 19121

08/06/26

152602

STRUCTURAL DRAWING LIST

SHEET

NUMBER SHEET NAME

S001 GENERAL NOTES

S100 STRUCTURAL PLANS & SECTIONS

PREFAB CANOPY

(BY OTHERS)

PREFAB CANOPY

(BY OTHERS)

300ZG-54

@ 16" o/c

EX. FLOOR SHEATHING

400S200-54 (33 KSI) @ 24" o/c

(MAX.) TYP. WHERE INDICATED

300ZG-54 @ 16" o/c

EX. FLOOR SHEATHING

CONTRACTOR NOTES:

1. EXISTING STEEL BEAM AND FLOOR FRAMING WERE NOT VISIBLE AT THE TIME OF THE FIELD SURVEY. CONTRACTOR SHALL EXPOSE

THE EXISTING FRAMING AND VERIFY THAT THE EXISTING MEMBER SIZES, ORIENTATION, AND GEOMETRY ARE CONSISTENT WITH THE CONDITIONS SHOWN AND SUITABLE FOR THE PROPOSED CONNECTION DETAILS. CONTACT THE ENGINEER OF RECORD IF EXISTING CONDITIONS DIFFER FROM THOSE SHOWN OR IF THE PROPOSED DETAILS CANNOT BE INSTALLED AS INDICATED.

2. WHERE EXISTING FLOOR JOISTS FRAME PERPENDICULAR TO THE EXTERIOR WALL, OMIT THE FULL-DEPTH 2x BLOCKING AND FASTEN THE LIGHT-GAUGE STEEL FRAMING DIRECTLY TO THE EXISTING FLOOR JOISTS IN ACCORDANCE WITH THE CONNECTION

REQUIREMENTS SHOWN.

ATTACHMENT METHOD #1 (DEEP PERIMETER BEAM)

ATTACHMENT METHOD #2 (SHALLOW PERIMETER BEAM)

STOREFRONT WINDOW BELOW

(2)0.157" SST PDPA/PDPAT-62KP

@ EA. STUD

CONT. 600T200-43 (33) TOP TRACK

STOREFRONT WINDOW BELOW

FULL DEPTH 2x BLOCKING

AT SOFFIT ATTACHMENT

POINT @ 24" o/c

400S200-54 (33 KSI) @ 24" o/c

(MAX.) TYP. WHERE INDICATED

(3)#10-16 SCREWS,

TYP. WHERE

INDICATED

CONN. TO STRUCT. BY

CANOPY SUPPLIER

CONN. TO STRUCT. BY

CANOPY SUPPLIER

FULL DEPTH 2x BLOCKING

AT SOFFIT ATTACHMENT

POINT @ 24" o/c

(3)#10-16 SCREWS,

TYP. WHERE

INDICATED

S100

DRAWN BY:

SCALE:

N O

T F

O R

C O

N S

T R

U C

T

IO

N

PROJECT:

SWRL STUDIO, LLC

2715 Folsom St Philadelphia, PA 19130

©2026

DATE:

PROJECT NO:

NOTES:

swrl studio

NO. DATE DESCRIPTION

ARCHITECT

STRUCTURAL ENGINEER

PRESTON STRUCTURAL SOLUTIONS, LLC

106 Gay Street, Unit 305 Philadelphia, PA 19127

As indicated

S100

REP

STRUCTURAL

PLANS &

SECTIONS

2224 RIDGE

PROCESS

JUNIOR'S

2224 RIDGE AVE

PHILADELPHIA, PA, 19121

08/07/26

152602

3/4" = 1'-0"

2 CANOPY CONNECTION DETAIL

1/4" = 1'-0"

1 ELEVATION - RIDGE AVE PROPOSED

A000 - COVER SHEET
A101 - EXTERIOR ELEVATIONS
S001 - GENERAL NOTES
S100 - STRUCTURAL PLANS & SECTIONS