Attachment J-3 High Level CGMCS Scope for POLAR STAR.pdf
PDF 352 KB Posted
- Attached to
- Request for Proposal (RFP) for the USCG POLAR STAR Service Life Extension Project (SLEP)
- Solicitation number
- 70Z02320RAPS00200
About this file
This federal contract opportunity is a request for proposal for services to extend the service life of the US Coast Guard cutter Polar Star. The Coast Guard intends to award an indefinite-delivery, indefinite-quantity contract to provide tasks including replacing enclosures and equipment on the cutter, installing new computer and input/output racks, and modifying bridge consoles. The contract would have firm-fixed-price and fixed-price award fee line items as specified in the solicitation. Offerors must be able to handle materials subject to export controls, and the small business size standard is 1,250 employees. Proposals are due by the date listed on federal business opportunities sites, and the contract would have a one-year base period and four one-year options that could extend the work through 2026.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Coast Guard Yard High Level SOW for FY21 CGMCS Support
2021 (6 electricians rotated for 60 days, 2 technicians to support testing post installation 40 days, then 2 days dock trials 5 days Sea Trials. 4 Mechanics onsite approximately 30 days to support foundation work and other modifications)
Remove existing enclosures and replace with new enclosures RIB1A/B, RIB2A/B, RIB3A/B, RIB4A, RIB5.
Reinstall field cabling and connect new CAT5e and power cabling. Foundation work required
Replace subpanels in RDU4 and RDU6 and install new subpanels. Reinstall field cabling and connect new CAT5e and power cabling. Modify enclosures panels.
Install new I/O racks in the Engineering Control Center (ECC) for Vital alarms.
Replace existing computers in ECC with new computers.
Remove existing Opto22 IO racks in bridge consoles and install new Rockwell racks mounted on plates
(4)
Run signal cables from Pilothouse center console to PBW, SBW and Aloft Conn (<14 conductor cable )
Remove existing Opto 22 IO racks in ECC and install new Rockwell racks mounted on plates (4).
Remove existing UPS and foundations in ECC.
Remove existing switches including 19 inch Rack in ECC and Install new Rack, Switches (2) and Rack mounted computer.
Install new UPS units in ECC (2 bulkhead mounted units)
Remove existing Computers/Monitors at Bridge (4) including brackets, install new computers, monitors and brackets (4)
Install power cabling from UPS to all new devices, Ethernet cabling from ECC to all new devices.
Insert new pushbuttons and lights in bridge consoles for transfer of control. Connect wiring to existing
Opto22 units in bridge consoles.
Install terminals and replace power supplies in ECC for power distribution.
Install ETAP in LMAS units to connect to existing Opto22 Rack (5)
Install MVI and ETAP in Main GT LOCOPs (3)
Install CAT5e cable from OOD Station Computers to Bridge switch (3)
Support signal testing for field signals (Fluke simulator or similar)
Support operational testing for plant including dock and Sea Trials
2022 (2 electricians for 20 days)
Install quarterdeck monitoring (3 locations). Power and CAT-5 communication to be run from ECC to the quarterdeck locations.
Install signal cable from RDU4 to the Vibration monitoring system
Support testing for Quarterdeck and Vibration monitoring systems
2023 (2 electricians for 15 days)
Remove existing Opto22 IO racks in the LMAS enclosures replacing with two Rockwell 1794 devices.
Replace power supplies with one 24VDC power supply. (5 LMAS units total)
Support testing for LMAS signals.