This amendment to a request for proposal provides revisions to references in the consolidated reference list for the US Coast Guard Polar Star Service Life Extension Project contract. The document updates several drawing, diagram, manual, and publication references for ship systems and components. Revisions include updating references to newer revisions, correcting incorrect references, and noting some references have been removed from the specification. The Coast Guard will incorporate the reference updates into the specification and consolidated reference list prior to awarding the indefinite-delivery, indefinite-quantity contract for services to extend the service life of the Polar Star cutter.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Dwg CRL Version listed in RFP Title USCG Response
400 WAGB 101-402 Rev 3 SLEP-Ceiling Replacement Key Plan Drawing has been finalized. Provided as attachment to this amendment.
400 WAGB 512-1 Rev - WAGB POLAR STAR Zone Sys Comp Term Airflow Test
Reference is export controlled. Finalized document inserted in to Tech Pub 2034 Section A. USCG will update specification and CRL for contract award.
Provided as attachment to this amendment.
400 WAGB 103-11 Rev J Outboard Profile
CRL reference is incorrect and should be 400 WAGB 103-3 "Booklet of General Plans (POLAR STAR)"
400 WAGB 1108-1 Rev G Ice Shoe Revision G is the correct reference. Provided as attachment to this amendment.
400 WAGB 1112-19 Rev AF Foundations 03 Level & Above CRL reference is incorrect and should be 400 WAGB 1112-19 Revision AE.
400 WAGB 1112-83 Rev - SLEP-Foundations For New Sewage Pumps Revision "-" is the correct reference. Provided as attachment to this amendment.
400 WAGB 1202-3 Rev J Helicopter Safety Net Revision K is the correct reference. USCG will update specification and CRL for contract award.
400 WAGB 2200-8 Rev G Rudder Stock Removal A/D Revision H is the correct reference. USCG will update specification and CRL for contract award.
400 WAGB 2803-07 Rev F WarningOperating & Instruction Plates The correct reference is 400 WAGB 2803-07, Rev F.
Provided as attachment to this amendment.
400 WAGB 3802-7 Rev - Diag Stm Htg & Condensate Revision A is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 3803-1 Rev M Ventilation Configuration & A/C Diagram Revision M is the correct reference. Provided as attachment to this amendment.
400 WAGB 4000-012 Rev – SLEP Pump Renewal Key Plan Revision B is the correct reference USCG will update the specification and CRL for contract award.
400 WAGB 4112-5 Rev AF Arr S.W. Cool Diesel Gen Revision AE is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4302-1 Rev P Stern Tube Bearg & Shaft Seal Arrg Reference has been superceded by 400 WAGB 4302-4 Revision B.
400 WAGB 4801-25 Rev A RIP Arrangement Of Oil Water Separator Sys Installation Revision B is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4804-7 Rev K Diag of H&C Potable Wtr Sys Revision M is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4804-010 Rev A Diagram Hot & Cold Potable Water System Revision E is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4805-1 Rev AF Arr S.W. Cooling Gas Turb. Rm.Motor & Gear Rm.& Motor Rm Revision AG is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4808-48 Rev A RIP Arr Sanitary Flush System Modification Drawing Document is export controlled. Provided as attachment to this amendment.
400 WAGB 4808-50 Rev A RIP-General Arrangement Of Oil Water Separator System Document is export controlled. Provided as attachment to this amendment.
400 WAGB 4901-6 Rev A Arr Ship Service Air 3rd Deck & Below Revision Z is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4901-8 Diagram Of Compressed Air System Revision R is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4901-19 RIP Diagram Ships Service Air System Mod Incid To Air Cprsr Instl (POLAR STAR) Revision A is the correct reference. USCG will update the specification and CRL for contract award.
400 WAGB 4901-46 RIP Arr Ships Svcs Compa Sys Mod Incid To Air Cprsr Instl Revision A is the correct reference. USCG will update the specification and CRL for contract award.
Publications Coast Guard Polar Star 1MC System Operational Verification Test Provided as attachment to this amendment.
TS 505 2013 Piping Systems This reference has been removed from the specification.
TS 507 2015 Machinery and Piping Designating and Marking This reference has been removed from the specification.
TP 4395 Manufacturer's Instruction Book-SWBS Group(s) 243 Document is export controlled. Provided as attachment to this amendment.
TP 4989A Controlable Pitch Propeller The reference provided is correct. USCG will update consolidated index for contract award.
Inventory and Review of SLEP Technical References
TP
Damage Control Manual for USUSCGC POLAR STAR including plates
This reference has been removed from the specification. Please reference 400 WAGB 103-3 "Booklet of General Plans (POLAR STAR)"
COMDTINST M9085.1 (series) Naval Engineering Computer Aided Design Standards