Attachment J-2 Description of the CGMCS and EPPD NAVSEA work items.pdf

PDF 89 KB Posted

Attached to
Request for Proposal (RFP) for the USCG POLAR STAR Service Life Extension Project (SLEP)
Solicitation number
70Z02320RAPS00200
Issued by

About this file

This document outlines requirements for a federal contract opportunity to provide engineering services for the US Coast Guard Polar Star cutter. The Coast Guard seeks to award an indefinite-delivery, indefinite-quantity contract to extend the service life of the Polar Star through 2023. Task orders will consist of firm-fixed price and fixed price award fee contract line items. Engineering support is required for installation of new electrical equipment aboard the cutter in 2021, including voltage regulator cabinets, switchboards, battery units, and cabling. Additional support is required in 2022 and 2023 to maintain the installed systems. Offerors must comply with export regulations and have access to materials subject to ITAR or EAR. The solicitation number is 70Z02320RAPS00200.

View the file

Other files

File Type Posted
70Z02320RAPS00200 SF30 Amendment 000006.pdf PDF
Amendment 06 Page from Section L 19 MAY 2020.pdf PDF
70Z02320RAPS00200 Amendment 05 SF30.pdf PDF
Amendment 05 Reference Document List.pdf PDF
Amendment 04 Page from Section F 27 APR 2020.pdf PDF
70Z02320RAPS00200 Amendment 04 SF30.pdf PDF
Amendment 03 - Pages from Section L 03 APR 2020.pdf PDF
70Z02320RAPS00200 Amendment 000003 SF30 .pdf PDF
70Z02320RAPS00200 Amendment 000002 SF30.pdf PDF
Amendment 02 Section C-M 11 MAR 2020.pdf PDF
Attachment J-3 High Level CGMCS Scope for POLAR STAR.pdf PDF
70Z02320RAPS00200 Amendment 000001 SF30.pdf PDF
Attachment J-4 USCG_WAGB10_Install_High_Level_SOW.pdf PDF
Amendment 01 Section C-M 03 FEB 2020.pdf PDF
Attachment J-5 POLAR STAR SLEP CDRL_4FEB20.pdf PDF
Attachment L-3 Site Visit Vendor Access Roster.pdf PDF
70Z02320RAPS00200 Section A and B 1449.pdf PDF
Attachment C-1 POLAR_STAR _SLEP_ Rev2.pdf PDF
Attachment L-5 PSTAR_SLEP_Notional_Work_Item_Schedule.pdf PDF
Attachment L-4 Sample Work Breakdown Structure.docx.pdf PDF
Attachement J-1 Pricing Worksheet.xlsx XLSX spreadsheet
Attachment C-2 - SFLC-Std-Spec-0000.pdf PDF
Attachment L-2 Notice for Agency Protest.pdf PDF
70Z02320RAPS00200 Section C-M 31 Jan 2020.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NSWCPD 442 – Steam & Diesel Electric Power Systems Generation, Automation, & Distribution

Ship Systems Engineering Station, Philadelphia PA

NSWCPD CODE 442

High Level SOW Summary for PPD Installation aboard USCGC POLAR STAR FY 2021 / FY2022 / FY2023 Availabilities

2021 Availability

Work Force (Phases - 60 days of install, 40 days of testing, 2 days of Dock Trials, 5 days of Sea Trials)

8 Electricians rotated for 60 days 6 Mechanics onsite for 40 days 2 Electricians to support testing post installation 40 days 2 electricians 2 days of dock trials 2 Electricians 5 days of Sea Trials 8-10 NSWCPD Engineers at any time

High Level Scope

• Disconnect existing power & control cables inside existing Generator and Motor Voltage Regulator cabinets and remove cabinets within ECC o STBD Generator Voltage Regulator Cabinet o CTR Generator Voltage Regulator Cabinet o PORT Generator Voltage Regulator Cabinet o Motor Voltage Regulator Cabinet

• Remove existing and install new foundations for the Voltage Regulator cabinets. Install new Voltage Regulator cabinets.

• Westinghouse Switchboards o Disconnect existing wiring and remove devices/ equipment to be removed from backplanes o Mount new devices/ equipment inside Switchboard and terminate existing wiring

• Install new battery units for UPS units on new foundation in ECC (3 units)

• Install power cabling from UPS to all new devices, Ethernet cabling from

ECC to all new devices.

• Remove asbestos and lead paint associated with tasking, paint and lag disturbed areas.

• Install deck and bulkhead penetrations as required to run new cabling.

Install cable tags for newly installed cabling.

• Signal ringout for all wiring/ signals Voltage Regulator Enclosures and connected enclosures

• Support signal testing for field signals (Fluke simulator or similar)

• Support operational testing for plant including dock and Sea Trials

Work Spaces

ECC, AUX 1/ 2/ 3, Diesel 1 & 2, Motor Gear Compartment

2022 Availability

Work Force

2 Electricians, 2 Mechanics onsite 3 weeks 2- 4 NSWCPD Engineers at any time

High Level Scope

• Groom existing system, confirm right and tight

• Support testing/ trouble shooting

Work Spaces

• ECC, AUX 1/ 2/ 3, Diesel 1 & 2, Motor Gear Compartment

2023 Availability

Work Force

2 Electricians, 2 Mechanics onsite 3 weeks 2- 4 NSWCPD Engineers at any time

High Level Scope

• Groom existing system, confirm right and tight

• Support testing/ trouble shooting

Work Spaces

• ECC, AUX 1/ 2/ 3, Diesel 1 & 2, Motor Gear Compartment

File details come from the government source that posted it. Updated .