Dewberry
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
Insured: SHALINI KATTA Home: (670) 788-8554 Cellular: (670) 789-4452Home: ROUTE 37 TR 22549 NEW-R1 TANU LANE
ASLITO, HI 96701
Property: ROUTE 37 TR 22549 NEW-R1 TANU LANE
ASLITO, HI
Claim Rep.: Casey Hoak
Estimator: Casey Hoak
Claim Number: CNMI-412601742 Policy Number: CNMI-412601742 Type of Loss: Hurricane
Date Contacted: 11/25/2019 12:30 AM Date of Loss: 10/25/2018 5:00 AM Date Received: 6/4/2019 9:23 AM
Date Inspected: 6/5/2019 8:00 PM Date Entered: 11/24/2019 9:44 AM
Date Est. Completed: 6/6/2019 2:25 PM
Price List: HIOI8X_JAN19 Restoration/Service/Remodel
Estimate: CNMI-412601742_RA
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 2
11/24/2019 CMH
Site visits batch of 4 next 20 Attending Casey Hoak, DeDe Hubbard, Brunson Taylor, Jorge Rivera PE This home was visited on a joint site visit back in August for the initial set of 40. The home has not suffered any new damage since that scope was written. Changes were made only to the gable end wall to make them 2x6 instead of 2x4.
Scaffold labor and a dumpster for hauling the debris off have also been added per FEMA Guidance. All other items listed remain the same. The roof design that was written has been reviewed by PE Jorge Rivera and he is in agreement with the design of the roof. A new set of photos has been added to the file to document the present condition of the home as of today.
JOINT SCOPING SUMMARY 8/23/2019:CMH
Attendees: FEMA : Robert Strayhorn, Chris Craft. Dewberry: Casey Hoak, Marvin Davis, DeDe Hubbard.
Roof design agreed to at joint site visit: Gable roof with Shed over Kitchen portion. Saw cut 2 gable end walls level and Pour 10" Bond Beam on the exterior perimeter wall.
Framing damaged 2x4 walls in the living room and laundry room. Framing a 2x6 exterior wall on the kitchen per FEMA to replace the damaged one present.
All other exterior walls are concrete. Installing sheathing to replace damaged sheathing in bedroom 2 where old door was covered up.
Foundation appears in good condition and should not need any work.
Windows are being replaced that were damaged with all windows getting storm shutters.
No damage to any ceramic tile floor.
All damaged doors to be replaced, paint trim and all 6 sides of the door will be added The electrical of the home will include replacement of the mast head, meter base, and 200 amp panel.
The actual count of plugs, switches and lights that were present at the time of the storm are to be replaced.
Bathrooms and Kitchens that have existing electrical outlets within 6 feet of a sink are to be protected by a GFIC per code and per FEMA Guidance. Per FEMA guidance all exterior plugs are to be replaced with a GFI.
When no plugs existed prior in these rooms or the exterior none will be added to the estimate.
Rewiring of the entire home done by the floor's square footage will be done without conduit unless needed and approved by
FEMA.
All available GFM (Government Supplied Material was identified).
All changes were agreed upon by all parties and are made a part of this revised report.
INSPECTION SUMMARY
The applicants Mother Sankita Katta met at the damaged dwelling and the following was observed.
The dwelling is a one story CMU with a metal roof and slab on grade. The home has four occupants and 2 bedrooms occupied.
The dwelling is deemed to be repairable . The one structural component damaged is the roof Reconstruction should take approximately 16 weeks from start of construction.
AGE: 2002
DAMAGE AND REPAIR SUMMARY
See attached estimate for exact repair and line items.
LATITUDE: 15.133895
LONGITUDE: 145.718454
A: ROOF: The roof is destroyed and will require replacement from the framing up. The garage portion will not be included in the replacement of the roof. A gable roof will be put over the main dwelling with a shed roof installed over the kitchen.
B: INTERIOR: The interior will require new ceiling joists, wood ceilings, window shutters, both exterior and interior doors, and painting for all doors. In the kitchen lower & upper cabinets removed and replaced with
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 3
8 LF bottom and 8LF upper with counter top. Concrete counter top will be removed and laminate replaced. There is damage to the interior walls in the Kitchen Living and Laundry Rooms.
C: STRUCTURAL: The slab is intact and are not damaged.
D: MECHANICAL OK, PLUMBING: Replace sink and faucet, WATER SYSTEM: OK
E: ELECTRICAL: All electric will need replacing from the masthead in to include plugs switches lights meter and panel.
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 4
CNMI-412601742_RA
Roof Roof
DESCRIPTION QTY
1. Material Only 2" x 6" x 20' #2 treated pine (material only) 4.00 EA
2. Material Only 2" x 6" x 18' #2 treated pine (material only) 8.00 EA
3. Material Only 2" x 6" x 92 5/8" pre-cut stud (for 8' wall, mat only) 32.00 EA
For gable end walls
5. Material Only 2" x 6" x 14' #2 treated pine (material only) 4.00 EA
6. Material Only 2" x 6" x 10' #2 treated pine (material only) 4.00 EA
7. Material Only 2" x 6" x 8' #2 treated pine (material only) 23.00 EA
8. Material Only 2" x 10" x 18' #2 treated pine (material only) 12.00 EA
9. Material Only 2" x 10" x 16' #2 treated pine (material only) 52.00 EA
10. Material Only 2" x 12" x 18' #2 treated pine (material only) 5.00 EA
11. Material Only 2" x 12" x 20' #2 treated pine (material only) 4.00 EA
12. Material Only 2" x 12" x 16' #2 treated pine (material only) 8.00 EA
14. Rafters - 2x6 - Labor only - (using rafter length) 475.68 LF
For gable end walls and collar ties
15. Rafters - 2x10 - Labor only - (using rafter length) 942.60 LF
16. Rafters - 2x12 - Labor only - (using rafter length) 285.19 LF
For Ridge beam and fascia
17. Install Sheathing - plywood - 1/2" - treated 386.30 SF
18. Material Only Sheathing - plywood - 1/2" - treated 386.30 SF
19. Install Sheathing - plywood - 3/4" - treated 1312.00 SF
20. Material Only Sheathing - plywood - 3/4" - treated 1312.00 SF
251. Siding - hardboard panel - paint grade 193.20 SF
252. Remove House wrap (air/moisture barrier) 193.20 SF
------------------ ROOFING -----------------
21. Install Metal roofing - ribbed - 24 gauge - up to 1" 1306.31 SF
22. Material Only Metal roofing - ribbed - 24 gauge - up to 1" 1306.31 SF
23. Closure strips for metal roofing - inside and/or outside 71.62 LF
24. Flashing tape - self-adhesive 480.38 LF
Seal between the metal roof seams
25. Ridge vent - Metal roofing - floating ventilator 35.81 LF
26. Additional screws for 3/4 plywood sheathing 4413.00 EA
Additional screws for 3/4 plywood sheathing above Xactimate allowance 6 % waste added
27. Additional screws for 2X4 furring 1011.00 EA
Additional screws for 2X4 furring above Xactimate allowance 6 % waste added
28. Additional screws for 2x6 furring 434.00 EA
Additional screws for 2x6 furring above Xactimate allowance 6 % waste added
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 5
CONTINUED - Roof
DESCRIPTION QTY
29. Additional screws for fascia 115.00 EA
Additional screws for fascia above Xactimate allowance 6 % waste added
31. Drip edge/gutter apron 71.62 LF
32. Install Gable trim for metal roofing - 26 gauge 90.96 LF
33. Material Only Gable trim for metal roofing - 26 gauge 90.56 LF
34. Ice & water barrier 1306.31 SF
35. Neoprene pipe jack flashing for metal roofing 1.00 EA
36. Install 2" x 4" lumber - treated (.667 BF per LF) 536.71 LF
Roof purlins
37. Material Only 2" x 4" lumber - treated (.667 BF per LF) 536.71 LF
Roof purlins
38. Install 2" x 6" lumber - treated (1 BF per LF) 285.46 LF
For Picture Frame Purlins
39. Material Only 2" x 6" lumber - treated (1 BF per LF) 285.46 LF
For Picture Frame Purlins
40. Install 2" x 6" lumber - treated (1 BF per LF) 282.85 LF
Rafter Blocking
41. Material Only 2" x 6" lumber - treated (1 BF per LF) 282.85 LF
Rafter Blocking
------------------ SOFFIT -----------------
42. Install Soffit - box framing - 1' overhang 89.64 LF
Calculation set for 16" overhang
43. Material Only Soffit - box framing - 1' overhang 89.64 LF
Calculation set for 16" overhang
44. Install Soffit & fascia - wood - 1' overhang 89.64 LF
Calculation set for 16" overhang
45. Material Only Soffit & fascia - wood - 1' overhang 89.64 LF
Calculation set for 16" overhang
46. Baffle vent - foam 71.62 LF
Cut to fit as needed for vents
47. Soffit vent - linear 44.31 LF
------------------ PAINT -----------------
48. Exterior - paint two coats 386.30 SF
To paint end walls
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 6
CONTINUED - Roof
DESCRIPTION QTY
49. Prime & paint exterior soffit - wood 95.25 SF
50. Prime & paint exterior fascia - wood, 4"- 6" wide 143.24 LF
Doubling the amount as the Fascia is 2x12 and XM8 line item covers only 6 inch fascia wood.
------------------ STRAPPING -----------------
51. 2x10 Joist hangers for rafters 52.00 EA
2x10 Joist hangers for rafters
52. Joist hangers for 2x6 rafter blocking 218.00 EA
Joist hangers for 2x6 rafter blocking, Typical one side of blocking per plans
53. Framing hurricane tie 188.00 EA
For rafter tails and gable wall studs top and bottom
54. Install Framing hurricane tie 82.00 EA
For joist to top plate
55. Material Only Framing hurricane tie 82.00 EA
For joist to top plate
57. Framing strap - 24" long 28.00 EA
58. Lag bolt - 1/2" x 5" - hex lag screw - zinc plated 128.00 EA
4 @ each rafter section & 24 at the splice on the ridge
NOTES:
Document 1
Main Level Main Level
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
59. R&R Meter mast for overhead power - 2" conduit 1.00 EA
60. R&R Meter base - 200 amp 1.00 EA
61. R&R Breaker panel - 200 amp w/arc fault breakers 1.00 EA
62. Circuit breaker - main disconnect - 150 to 200 amp 1.00 EA
63. Rewire - average residence - copper wiring 1111.59 SF
64. R&R Ground fault interrupter (GFI) outlet 1.00 EA
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 7
CONTINUED - Main Level
DESCRIPTION QTY
65. R&R Exterior light fixture 1.00 EA
66. R&R Grounding rod - copper clad with clamp, 8' 2.00 EA
67. R&R Trunk cable - aluminum - 4 wire 2/0 5.00 LF
------------------ WALL REPAIRS-----------------
68. Concrete cutting - wall (per LF per inch of saw depth) 336.00 LF
To straighten the top of the wall where needed
69. Remove Concrete wall - labor & materials - Reinforced 1.00 CY
70. Concrete - General Laborer - per hour 4.00 HR
4 hours per CY of Concrete Wall
71. Concrete Post & Beam construction - Beams 2.36 CY
To pour a bond beam on top of existing wall - includes rebar
72. Concrete anchor bolt - 1/2" x 10" 116.00 EA
73. Install 2" x 6" lumber - treated (1 BF per LF) 484.02 LF
For double sill plate on the perimeter
74. Material Only 2" x 6" lumber - treated (1 BF per LF) 484.02 LF
For double sill plate on the perimeter
75. Sill seal foam - 6" 153.78 LF
------------------ SCAFFOLD -----------------
277. Scaffolding Setup & Take down - per hour 32.00 HR
------------------ GENERAL ITEMS -----------------
76. Clean the floor - Heavy 1111.59 SF
279. Dumpster load - Approx. 20 yards, 4 tons of debris 1.00 EA
NOTES:
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 8
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom 3'
8'
8'
4'
4'
3'
' 4
' 8
6"4"
3' 8' 7"
8' 9"
2' 3" 3' 1' 9"
1' 11"
9' 1"
2'
8'
13' 6"
3' 8" 6" Living Room Height: 8'
546.67 SF Walls
825.67 SF Walls & Ceiling
31.00 SY Flooring
68.33 LF Ceil. Perimeter
279.00 SF Ceiling
279.00 SF Floor
68.33 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
77. R&R Switch 6.00 EA
78. R&R Light fixture 1.00 EA
79. R&R Outlet 4.00 EA
80. Smoke detector 1.00 EA
81. Carbon monoxide detector 1.00 EA
------------------ DOORS & WINDOWS -----------------
82. R&R Exterior door - metal - insulated - flush or panel style 1.00 EA
83. Door lockset & deadbolt - exterior 1.00 EA
84. Paint door slab only - 2 coats (per side) 2.00 EA
Painting all 6 sides of door
85. Paint door/window trim & jamb - 2 coats (per side) 2.00 EA
86. Security/storm shutter 70.00 SF
------------------ ROUGH FRAMING -----------------
87. Remove Stud wall - 2" x 4" - 16" oc 88.00 SF
To replace damaged interior wall, including framing, sheathing and paint.
88. Install Stud wall - 2" x 4" - 16" oc 88.00 SF
89. Material Only Stud wall - 2" x 4" - 16" oc 88.00 SF
90. Remove Sheathing - plywood - 1/2" - treated 88.00 SF
91. Install Sheathing - plywood - 1/2" - treated 88.00 SF
92. Material Only Sheathing - plywood - 1/2" CDX 88.00 SF
93. Seal & paint plywood sheathing 88.00 SF
------------------ INSULATION -----------------
94. Batt insulation - 10" - R30 - paper faced 279.00 SF
------------------ WALLS & CEILINGS -----------------
95. Install Sheathing - plywood - 1/2" - treated 279.00 SF
96. Material Only Sheathing - plywood - 1/2" CDX 279.00 SF
97. Seal & paint plywood sheathing 279.00 SF
98. Install Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 279.00 SF
99. Material Only Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 279.00 SF
100. Cove molding - 3/4" 68.33 LF
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 9
CONTINUED - Living Room
DESCRIPTION QTY
NOTES:
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
3'
' 9
' 1
1'
2'
3' 6'6' 10"
7' 2"
3' 1'
1'
6'
2'
0" 2'
3'
11' 11"
12' 3"
11" 1' 1"2'5' 5"
8' 9"
8' 11" Kitchen Height: 8'
517.33 SF Walls
778.58 SF Walls & Ceiling
29.03 SY Flooring
64.67 LF Ceil. Perimeter
261.25 SF Ceiling
261.25 SF Floor
64.67 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
101. R&R Switch 1.00 EA
102. R&R Light fixture 1.00 EA
103. R&R Outlet 1.00 EA
104. R&R Ground fault interrupter (GFI) outlet 2.00 EA
------------------ DOORS & WINDOWS -----------------
105. R&R Exterior door - metal - insulated - flush or panel style 1.00 EA
106. Door lockset & deadbolt - exterior 1.00 EA
107. Paint door slab only - 2 coats (per side) 2.00 EA
Painting all 6 sides of door
108. Paint door/window trim & jamb - 2 coats (per side) 2.00 EA
253. Add. charge for a retrofit window, 3-11 sf - difficult 2.00 EA
109. Storm window - aluminum, 3-11 sf 2.00 EA
110. Security/storm shutter 24.00 SF
------------------ ROUGH FRAMING -----------------
111. Install Stud wall - 2" x 6" - 16" oc 152.00 SF
Exterior wall replace per FEMA request. Sheathing and seal & paint both sides
112. Material Only Stud wall - 2" x 6" - 16" oc 152.00 SF
113. Remove Sheathing - plywood - 1/2" - treated 304.00 SF
114. Install Sheathing - plywood - 1/2" - treated 304.00 SF
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 10
CONTINUED - Kitchen
DESCRIPTION QTY
115. Material Only Sheathing - plywood - 1/2" CDX 304.00 SF
116. Seal & paint plywood sheathing 304.00 SF
------------------ INSULATION -----------------
117. Batt insulation - 10" - R30 - paper faced 261.25 SF
------------------ WALLS & CEILINGS -----------------
118. Remove Sheathing - plywood - 1/2" - treated 261.25 SF
119. Install Sheathing - plywood - 1/2" - treated 261.25 SF
120. Material Only Sheathing - plywood - 1/2" CDX 261.25 SF
121. Seal & paint plywood sheathing 261.25 SF
122. Cove molding - 3/4" 64.67 LF
------------------ CABINETRY -----------------
123. Remove Cabinetry - lower (base) units 14.00 LF
124. Cabinetry - lower (base) units 8.00 LF
125. R&R Cabinetry - upper (wall) units 8.00 LF
126. Remove Countertop - concrete 28.00 SF
127. Countertop - flat laid plastic laminate 8.00 LF
------------------ PLUMBING -----------------
128. Sink - single 1.00 EA
129. Sink faucet - Kitchen 1.00 EA
------------------GENERAL ITEMS -----------------
130. 5 lb. ABC fire extinguisher 1.00 EA
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 11
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
2' 7' 11" 8' 3"
3' 2" 3' 4"
2'
4'
4'
1"
' 1 1"
' 3
2' 6" 5' 10"4' 9"
2'
8'
Bedroom 1 Height: 8'
540.00 SF Walls
810.39 SF Walls & Ceiling
30.04 SY Flooring
67.50 LF Ceil. Perimeter
270.39 SF Ceiling
270.39 SF Floor
67.50 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
131. R&R Switch 1.00 EA
132. R&R Light fixture 1.00 EA
133. R&R Outlet 4.00 EA
134. Smoke detector 1.00 EA
------------------ DOORS & WINDOWS -----------------
135. R&R Interior door unit 2.00 EA
136. Door knob - interior 2.00 EA
137. Paint door slab only - 2 coats (per side) 4.00 EA
Painting all 6 sides of door
138. Paint door/window trim & jamb - 2 coats (per side) 4.00 EA
139. Security/storm shutter 35.00 SF
------------------ INSULATION -----------------
140. Batt insulation - 10" - R30 - paper faced 270.39 SF
------------------ WALLS & CEILINGS -----------------
141. Install Sheathing - plywood - 1/2" - treated 270.39 SF
142. Material Only Sheathing - plywood - 1/2" CDX 270.39 SF
143. Seal & paint plywood sheathing 270.39 SF
144. Install Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 270.39 SF
145. Material Only Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 270.39 SF
146. Cove molding - 3/4" 67.50 LF
------------------ HVAC -----------------
147. Comb and straighten a/c condenser fins - w/out trip charge 1.00 EA
To clean & sanitize split unit
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 12
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
3'
3'
3'
4'
0"
5'
4' 7"
4' 2"
4' 4"
4' 3"
4' 7"
5'
5'
2'
2'
2'
1"
2' 6" 5' 10"4' 9"
Bedroom 2 Height: 8'
392.94 SF Walls
543.08 SF Walls & Ceiling
16.68 SY Flooring
49.12 LF Ceil. Perimeter
150.14 SF Ceiling
150.14 SF Floor
49.12 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
148. R&R Switch 2.00 EA
149. R&R Light fixture 1.00 EA
150. R&R Outlet 2.00 EA
151. Smoke detector 1.00 EA
------------------ DOORS & WINDOWS -----------------
152. R&R Interior door unit 1.00 EA
153. Door knob - interior 1.00 EA
154. Paint door slab only - 2 coats (per side) 2.00 EA
Painting all 6 sides of door
155. Paint door/window trim & jamb - 2 coats (per side) 2.00 EA
156. Security/storm shutter 24.50 SF
------------------ INSULATION -----------------
157. Batt insulation - 10" - R30 - paper faced 150.14 SF
------------------ WALLS & CEILINGS -----------------
158. Install Sheathing - plywood - 1/2" - treated 150.14 SF
159. Material Only Sheathing - plywood - 1/2" CDX 150.14 SF
160. Seal & paint plywood sheathing 150.14 SF
161. Install Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 150.14 SF
162. Material Only Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 150.14 SF
163. Cove molding - 3/4" 49.12 LF
------------------ ROUGH FRAMING -----------------
164. Remove Sheathing - plywood - 1/2" - treated 21.00 SF
Replacing damaged sheathing were old door was.
165. Install Sheathing - plywood - 1/2" - treated 21.00 SF
166. Material Only Sheathing - plywood - 1/2" CDX 21.00 SF
167. Seal & paint plywood sheathing 21.00 SF
------------------ CABINETRY -----------------
168. Remove Cabinetry - full height unit 5.00 LF
Removal of full height built ins no replace per FEMA
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 13
CONTINUED - Bedroom 2
DESCRIPTION QTY
NOTES:
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
2' 6"
1' 2"
10" 3' 8"
5'
" 5'
2'
2' 4"
2' 6"
2' 8"
2' 10"
5'
Bathroom Height: 8'
192.00 SF Walls
227.00 SF Walls & Ceiling
3.89 SY Flooring
24.00 LF Ceil. Perimeter
35.00 SF Ceiling
35.00 SF Floor
24.00 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
169. R&R Switch 1.00 EA
170. R&R Light fixture 1.00 EA
------------------ DOORS & WINDOWS -----------------
171. R&R Interior door unit 1.00 EA
172. Door knob - interior 1.00 EA
173. Paint door slab only - 2 coats (per side) 2.00 EA
Painting all 6 sides of door
174. Paint door/window trim & jamb - 2 coats (per side) 2.00 EA
175. Security/storm shutter 7.50 SF
------------------ INSULATION -----------------
176. Batt insulation - 10" - R30 - paper faced 35.00 SF
------------------ WALLS & CEILINGS -----------------
177. Remove Sheathing - plywood - 1/2" - treated 35.00 SF
178. Install Sheathing - plywood - 1/2" - treated 35.00 SF
179. Material Only Sheathing - plywood - 1/2" CDX 35.00 SF
180. Seal & paint plywood sheathing 35.00 SF
181. Remove Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 35.00 SF
182. Install Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 35.00 SF
183. Material Only Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 35.00 SF
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 14
CONTINUED - Bathroom
DESCRIPTION QTY
184. Cove molding - 3/4" 24.00 LF
NOTES:
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
2'
2'
2'
1"
2' 6"
1' 2"
3' 8"
5'
5'
6' 2"
6' 6"
2'
6'
2'
0"
2'
13' 6"
Laundry Room Height: 8'
399.61 SF Walls
515.42 SF Walls & Ceiling
12.87 SY Flooring
49.95 LF Ceil. Perimeter
115.81 SF Ceiling
115.81 SF Floor
49.95 LF Floor Perimeter
DESCRIPTION QTY
------------------ ELECTRICAL -----------------
185. R&R Switch 1.00 EA
186. R&R Light fixture 1.00 EA
187. R&R Outlet 2.00 EA
------------------ DOORS & WINDOWS -----------------
188. R&R Interior door unit 1.00 EA
189. Door knob - interior 1.00 EA
190. Paint door slab only - 2 coats (per side) 2.00 EA
Painting all 6 sides of door
191. Paint door/window trim & jamb - 2 coats (per side) 2.00 EA
------------------ ROUGH FRAMING -----------------
192. Remove Sheathing - plywood - 1/2" - treated 88.00 SF
Replacing damaged interior adjoining wall with living room.
193. Install Sheathing - plywood - 1/2" - treated 88.00 SF
194. Material Only Sheathing - plywood - 1/2" CDX 88.00 SF
195. Seal & paint plywood sheathing 88.00 SF
------------------ INSULATION -----------------
196. Batt insulation - 10" - R30 - paper faced 115.81 SF
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 15
CONTINUED - Laundry Room
DESCRIPTION QTY
------------------ WALLS & CEILINGS -----------------
197. Install Sheathing - plywood - 1/2" - treated 115.81 SF
198. Material Only Sheathing - plywood - 1/2" CDX 115.81 SF
199. Seal & paint plywood sheathing 115.81 SF
200. Install Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 115.81 SF
201. Material Only Joist - floor or ceiling - 2x6 - w/blocking - 16" oc 115.81 SF
202. Cove molding - 3/4" 49.95 LF
------------------DEMOLITION--------------
203. General Demolition - per hour 1.00 HR
Additional labor to remove damaged cabinets in laundry room. No replacement
NOTES:
CNMI DATA
CNMI Data1' 4"
CNMI Data Height: 4"
1.57 SF Walls
2.92 SF Walls & Ceiling
0.15 SY Flooring
4.70 LF Ceil. Perimeter
1.36 SF Ceiling
1.36 SF Floor
4.70 LF Floor Perimeter
DESCRIPTION QTY
204. Install ANY REMAINS THAT REQUIRE REINTERMENT 0.00 NO
205. Material Only LATITUDE DAMAGED DWELLING 15.13 DE
15.133895
206. Material Only LONGITUDE DAMAGED DWELLING 145.72 DE
145.718454
207. Material Only 55 GAL DRUMS VISIBLE LEAKING 0.00 NO
208. Material Only PETROLEUM ABOVE GROUND TANKS 0.00 NO
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 16
CONTINUED - CNMI Data
DESCRIPTION QTY
209. Material Only DOES DWELLING HAVE A SEPTIC TANK 0.00 YS
210. DOES DWELLING HAVE A WELL 1.00 NO
211. Material Only UNDERGROUND STORAGE TANKS/OR VENTS 0.00 NO
212. Material Only APPROXIMATELY WHAT YEAR WAS THE DWELLING BUILT 2002.00 YR
213. Material Only ANY SPECIAL NEEDS OR HANDICAPPED NEEDS 0.00 NO
214. Material Only ENCROACHMENT ISSUES 0.00 NO
215. Material Only IS DEWLLING SAFE, SANITARY AND FUNCTIONAL 0.00 NO
216. Material Only DOES DWELLING HAVE MORE THAN 1 LIVING UNIT 0.00 EA
217. Material Only TOTAL SQUARE FOOTAGE OF DWELLING 1112.00 SF
218. Material Only UNUNUSAL SITE CONDITIONS 0.00 NO
219. Material Only DOES DWELLING HAVE CENTRAL HVAC SYSTEM 0.00 NO
220. Material Only HOW MANY MAJOR CONSTRUCTION COMPONENTS DAMAGED 1.00 EA
ROOF
221. Material Only IS DWELLING DESTROYED 0.00 NO
222. Material Only FOUNDATION TYPE 0.00 UN
Slab on Grade
223. Material Only DOES DWELLING HAVE POTENTIAL LEAD ISSUE 0.00 NO
224. Material Only DOES DWELLING HAVE CENTRAL HVAC SYSTEM 0.00 NO
225. Material Only DID THE MILITAY PROVIDE THE ROOFING 0.00 NO
226. Material Only DID THE MILITARY PROVIDE A TENT 0.00 YS
227. Material Only HOW MANY MAJOR CONSTRUCTION COMPONENTS DAMAGED 1.00 EA
ROOF
228. Material Only DOES DWELLING HAVE POTENTIAL ASBESTOS ISSUE 0.00 NO
229. Material Only LATITUDE OUT BUILDING 0.00 DE
230. Material Only LONGITUDE OUT BUILDING 0.00 DE
231. Material Only LATITUDE POWER POLE 15.13 DE
15.134052
232. Material Only LONGITUDE POWER POLE 145.72 DE
145.718495
233. Material Only LATITUDE WATER METER 15.13 DE
15.133998
234. Material Only LONGITUDE WATER METER 145.72 DE
145.718571
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 17
CONTINUED - CNMI Data
DESCRIPTION QTY
235. Material Only LATITUDE SEPTIC 15.13 DE
15.133830
236. Material Only LONGITUDE SEPTIC 145.72 DE
145.718550
NOTES:
Labor Minimums Applied
DESCRIPTION QTY
237. Finish hardware labor minimum 1.00 EA
238. Plumbing labor minimum 1.00 EA
NOTES:
Grand Total Areas:
2,590.12 SF Walls 1,112.95 SF Ceiling SF Walls and Ceiling3,703.07 1,112.95 SF Floor 123.66 SY Flooring 328.27 LF Floor Perimeter
0.00 SF Long Wall 0.00 SF Short Wall 328.27 LF Ceil. Perimeter
1,112.95 Floor Area 1,193.06 Total Area 2,590.12 Interior Wall Area 1,776.64 Exterior Wall Area 158.49 Exterior Perimeter of
Walls
1,306.31 Surface Area 13.06 Number of Squares 179.58 Total Perimeter Length
35.81 Total Ridge Length 0.00 Total Hip Length
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 18
1 Document 1/Main Level - 1-Scope
Date Taken: 8/30/2019
Taken By: Casey Hoak
2 Document 1/Main Level - 2-Scope
Date Taken: 8/30/2019
Taken By: Casey Hoak
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 19
3 Document 1/Main Level - 3-Scope
Date Taken: 8/30/2019
Taken By: Casey Hoak
4 Document 1/Main Level - 4-Scope
Date Taken: 8/30/2019
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 20
5 Document 1/Main Level - Front Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
6 Document 1/Main Level - Front Elevation Date Taken: 11/24/2019
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 21
7 Document 1/Main Level - Front Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
Covered carport and entry
8 Document 1/Main Level - Front Elevation Date Taken: 11/24/2019
Front Entry
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 22
9 Document 1/Main Level - Front Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
10 Document 1/Main Level - Front Elevation
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 23
11 Document 1/Main Level - Back Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
12 Document 1/Main Level - Right Elevation
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 24
13 Document 1/Main Level - Left Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
14 Document 1/Main Level - Left Elevation
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 25
15 Document 1/Main Level - Left Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
16 Document 1/Main Level - Right Elevation Date Taken: 11/24/2019
Damage to exterior wall
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 26
17 Document 1/Main Level - Right Elevation Date Taken: 11/24/2019
Taken By: Casey Hoak
18 Document 1/Main Level/Living Room - Living Room Date Taken: 11/24/2019
Taken By: Casey Hoak
Roof and ceiling damage. No roof remaining, replace CJM add insulation and paint. R/R 2x4 damaged wall @ 88 sq. ft. R/R 88 sf damaged sheathing. Electric=Replace main panel, 1 light, 6 switch, 4 plugs, add smoke and C/O. No broken jealousy panes, add total of 70sf shutters for (4) 3X4 windows.
Ceramic tile floor ok.
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 27
19 Document 1/Main Level/Living Room - Living Room Date Taken: 11/24/2019
Taken By: Casey Hoak
20 Document 1/Main Level/Living Room - Living Room
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 28
21 Document 1/Main Level/Living Room - Living Room Date Taken: 11/24/2019
Taken By: Casey Hoak
22 Document 1/Main Level/Living Room - Living Room
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 29
23 Document 1/Main Level/Kitchen - Kitchen Date Taken: 11/24/2019
Taken By: Casey Hoak
Damage to roof and ceiling. Remove joist, replace CJM add insulation and paint. Electric=1 light, 1 switch, 1 plug, 1 GFI. Reframe 2x6 exterior wall, paint. R/R 1 3X3 & 1 2x3 windows to replace damaged jealousy windows, add 24SF shutter. R/R 8LF upper cabinets and 14 LF of lower.
Replace 8 LF lower cabinets per FEMA and add new laminate counter top to replace damaged concrete counter top. Add fire extinguisher.
24 Document 1/Main Level/Kitchen - Kitchen
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 30
25 Document 1/Main Level/Kitchen - Kitchen Date Taken: 11/24/2019
Taken By: Casey Hoak
26 Document 1/Main Level/Kitchen - Kitchen
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 31
27 Document 1/Main Level/Kitchen - Kitchen Date Taken: 11/24/2019
Taken By: Casey Hoak
28 Document 1/Main Level/Kitchen - Kitchen
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 32
29 Document 1/Main Level/Kitchen - Kitchen Date Taken: 11/24/2019
Taken By: Casey Hoak
30 Document 1/Main Level/Kitchen - Kitchen
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 33
31 Document 1/Main Level/Kitchen - Kitchen Date Taken: 11/24/2019
Taken By: Casey Hoak
32 Document 1/Main Level/Bedroom 1 - Bedroom 1 Date Taken: 11/24/2019
Taken By: Casey Hoak
Damage to ceiling and roof. Replace CJM add insulation and paint.
Electric=1 light, 1 plugs, 4 outlets, add smoke. R/R 1 interior door. No broken windows, add 35sf shutters
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 34
33 Document 1/Main Level/Bedroom 1 - Bedroom 1 Date Taken: 11/24/2019
Taken By: Casey Hoak
34 Document 1/Main Level/Bedroom 1 - Bedroom 1
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 35
35 Document 1/Main Level/Bedroom 1 - Bedroom 1 Date Taken: 11/24/2019
Taken By: Casey Hoak
36 Document 1/Main Level/Bedroom 1 - Bedroom 1
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 36
37 Document 1/Main Level/Bedroom 1 - Bedroom 1 Date Taken: 11/24/2019
Taken By: Casey Hoak
38 Document 1/Main Level/Bedroom 1 - Bedroom 1
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 37
39 Document 1/Main Level/Bedroom 1 - Bedroom 1 Date Taken: 11/24/2019
Taken By: Casey Hoak
40 Document 1/Main Level/Bedroom 2 - Bedroom 2 Date Taken: 11/24/2019
Taken By: Casey Hoak
Damage to ceiling and roof. Replace CJM add insulation and paint. R/R damged sheathing 21 sq ft where old door used to be and seal & paint.
Electric=1 light, 2 plugs, 2 outlets, add smoke. Remove 5LF full height cabinets. No broken windows, add 24sf shutters
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 38
41 Document 1/Main Level/Bedroom 2 - Bedroom 2 Date Taken: 11/24/2019
Taken By: Casey Hoak
42 Document 1/Main Level/Bedroom 2 - Bedroom 2
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 39
43 Document 1/Main Level/Bedroom 2 - Bedroom 2 Date Taken: 11/24/2019
Taken By: Casey Hoak
44 Document 1/Main Level/Bathroom
- 57-Bathroom Date Taken: 11/24/2019
Taken By: Casey Hoak
(Could not get door open at site visit 11/24, used photos from previous site visit) Damage to ceiling and roof.
R/R CJM add insulation and paint.
Electric=1 light, 1 switch. No damage to window add 7.5sf shutter. No damage to floor. No damage to fixtures
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 40
45 Document 1/Main Level/Bathroom
- 58-Bathroom Date Taken: 11/24/2019
Taken By: Casey Hoak
No window damage
46 Document 1/Main Level/Bathroom
- 59-Bathroom Date Taken: 11/24/2019
No damage to fixtures
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 41
47 Document 1/Main Level/Bathroom
- 60-Bathroom Date Taken: 11/24/2019
Taken By: Casey Hoak
48 Document 1/Main Level/Bathroom
- 61-Bathroom Date Taken: 11/24/2019
Damaged ceiling and electric
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 42
49 Document 1/Main Level/Bathroom
- 62-Bathroom Date Taken: 11/24/2019
Taken By: Casey Hoak
50 Document 1/Main Level/Laundry Room - Laundry Room Date Taken: 11/24/2019
Taken By: Casey Hoak
Damage to ceiling and roof. Replace CJM add insulation and paint. R/R 88sf damaged sheathing on wall.
Replace interior door, paint trim and all 6 sides of the door. No windows, no damage to floor. Adding 1hr debris disposal to remove damaged shelving
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 43
51 Document 1/Main Level/Laundry Room - Laundry Room Date Taken: 11/24/2019
Taken By: Casey Hoak
52 69-Carport
Date Taken: 8/23/2019
HOUSING ASSESSMENT in SUPPORT of Typhoon Yutu DR-4404-MP
CNMI-412601742_RA 12/8/2019 Page: 44
53 70-Carport
Date Taken: 8/23/2019
Taken By: Casey Hoak
54 71-Carport
Date Taken: 8/23/2019
CNMI-412601742_RA 12/8/2019 Page: 45
Main Level
KitchenG
FC
I
Laundry Room Bedroom 2
Living Room Bedroom 1
Bathroom
Main Level
CNMI-412601742_RA 12/8/2019 Page: 46
Roof
Roof1 (A)F1(B)F2
Roof2
F3
Roof
CNMI-412601742_RA 12/8/2019 Page: 47
CNMI DATA
CNMI Data
CNMI DATA
CNMI-412601742_RA 12/8/2019 Page: 48
PLOT
Plot (A1)
Tanu Lane (A2)
DD (A3)
Other Home (A4)
Other Home (A5)
Power Pole (A6)
Water Meter (A7)
MSGR. Martinez Rd (A8)
Septic (A9)
PLOT