This is a Pre-Award Request for Information (RFI) Log for the B401 Tenant #6 Fit-Out project, containing 16 answered questions dated August 26 through September 9, 2025. The project involves a Digital, Addressable Fire Alarm/Mass Notification System (NAICS 283113) and includes modifications to existing VESDA (Very Early Smoke Detection Apparatus) systems to accommodate new slab-to-slab demising partitions. The current building automation system uses Alerton controllers with Tridium N4.13 as the graphical user interface. The RF shielding and privacy film specification references 088000.002.01 with Signal Defense Films SD1000/1010 Surface-Applied Film. Work is scheduled during normal building hours, with after-hours work requiring advance approval via an After Hours Work Request Form.
Access and badging procedures are stringent and require National Crime Information Center (NCIC) checks for all contractor personnel. Badged contractors will not require escort, while non-badged pre-screened staff approved for One-Day Access must be escorted at all times. Delivery drivers requiring more than three day passes must submit complete badging packets for approval through the Information Security Management System (ISMS). The project requires Virginia Department of Professional and Occupational Regulation (VADPOR) contractor licensing, with contracts unable to proceed to award until licensing is obtained. Additional documentation requirements include commissioning reports, fire alarm system details, SF-25/SF-25A performance and payment bonds, Optional Form 336 for CLIN structure, and bid bonds (photocopies with wet signatures acceptable). Responses to all RFIs were provided between September 4 and September 10, 2025.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #: Date: Question: Answer: Date Answered:
1 8/26/2025
283113 – Digital, Addressable Fire Alarm/Mass Notification System
The issued drawings and specifications do not indicate any requirements for modifications to the existing VESDA (Very Early Smoke Detection Apparatus) systems. Are there any changes or modifications to the existing VESDA systems required under this contract? If so, please provide information on any required modifications.
It is anticipated that modifications to the VESDA (Very Early Smoke Detection Apparatus) systems shall be required to accommodate the new slab-to-slab demising partitions. We are transmitting with this correspondence two documents. The first is : 20128F B401 VESDA INT DESIGN pdf, and the second is 24083F B401 VESDA 2ND FLR RECONFIG.pdf
9/4/2025
2 8/26/2025 Door Opening 228 does not call out an STC rating but calls out for SHW-07 hardware which is for STC opening. Is this door supposed to be STC rated? If so, please provide rating.
Door 228 is not STC rated but would still need the security hardware outlined in SHW-07 with the exception of the acoustic door seals. 9/4/2025
3 8/26/2025 Please confirm contractor will not need to provide escorts for this project.
Under normal operating procedures, badged contractors will NOT require escort, they will be permitted to come and go as necessary. However for non-badged contractor support staff that HAVE been pre-screened and approved for One-Day Access will require escort. These individuals may include, delivery drivers, inspectors, testing staff, and similar. In these cases the GC will be responsible for the escorting. NOTE: During escort services the escorted must keep the escorted in sight at all times. Any staff requiring repeated access to the MWEOC shall be processed for badged access.
9/4/2025
4 8/26/2025 Please confirm badges will be provided for the contractors associated with this project.
Yes, badges will be provided to construction contractors once the following steps are complete: 1) Those who plan on accessing the site must undergo an NCIC check by submitting an Area A Access Form. The form and NCIC check must be processed before the applicant arrives on site. Applicant fills out part one (1) only.
| 2) | If their NCIC is denied, they will not be allowed on site. |
| 3) | If their NCIC is approved, the rest of their packet will be submitted to HQ for processing. |
| 4) | Once a case is a created in ISMS (Information Security Management System), that individual can come on site to get fingerprinted and pick up |
their badge.
5) When complete, applicant can begin work.
Important Notes:
- When all the above steps are complete, the applicant still holds his/her responsibility to answer all questions and/or provide documentation to their case specialist. If the applicant falls non-compliant, they will not be allowed to work on the site.
- To get fingerprints taken, applicant must provide two (2) valid forms of ID. Must be original documents. Photos, copies, or expired documents will not be accepted.
| • | Primary Forms of ID: |
| o | Real ID Driver’s License or other state photo identity cards issued by the De-partment of Motor Vehicles (DMV). |
| o | State-issued Enhanced Driver’s License (EDL) or Enhanced ID (EID) |
| o | U.S. Passport |
| o | U.S. Passport card |
| • | Secondary Forms of ID: |
| o | Voter’s Registration Card |
| o | Social Security Card |
| o | Birth Certificate |
| o | Naturalization Certificate Additionally |
attached for your use are: Area A Access Form, DHS, Form 11000-25, FCRA 11000-9, NDA - DHS Form 11000-6, and Declaration for Federal Employment.
9/4/2025
Pre-Award RFI Log B401 Tenant #6 Fit-Out
5 8/26/2025 Please provide the current BAS system for the existing building. The current system we have is alerton controllers with Tridium N4.13 as the graphic user interface. 9/8/2025
6 8/26/2025 Please provide the list of contractors from the base building.
Prime: The Christman Company22560 Glenn Drive, Suite 108 Sterling, VA 20164 4440; MK Concrete; D. L. George & Sons; TEI Electrical Solutions; Capital Electric; Jernigan; Southern Insulation; Cochran & Mann Commercial Painters and wallcovering; Module Custom Signage Solutions; PCI performance Contracting Inc, Gypsum Board / Cold-Formed Metal; Bonitz (Access Flooring); Brewer (Fire Suppression); Alberio Controls; Arc Floors; CMC Duct & Duct Accessories; CES; WRA Commissioning (Hugh Dalhouse); JD Long Masonry; Kalkreuth; One Diversified Copper, Optical & Coaxial Cabling; Roberts Land Surveying; Specialized Engineering; Tanks Direct - Facility Gray-Water Storage Tanks; Valley Lighting; Diamond Engineering; Custom Glass; CMAC General Labor (Christman Mid-Atlantic Constructors); Gradeline Construction - Pavement Markings / Signage;
9/10/2025
7 8/26/2025 Please confirm work will occur during normal building hours.
Yes, work will be scheduled during normal building hours/working hours. If the GC wished to work evenings or weekends an After Hours Work Request Form will be required in advance.
9/4/2025
8 8/26/2025 Please advise if delivery drivers will need to be badged.
If the delivery drivers come on site, they must go through the NCIC check and get badged.
See process below.
| • | Day Passes |
| o | Must have NCIC check. If approved, they will receive a visitors’ badge and must al-ways be escorted. |
| o | Note: An individual can only receive three (3) day passes per contract. IF the individual-al plans being on the contract more than three (3) days, |
they must submit a full pack-et.
| • | Full Packet (on contract) |
| o | Must have NCIC check. If approved, their packet will be sent to HQ for processing. Once they have a case created in ISMS (Information Security |
Management System), they can come on site to get their fingerprints taken and pick up their badge. They will receive an orange badge and will not need to be escorted.
o Note: Those who receive an orange badge only have access to the contracts (con-construction sites) they are approved to be on in ISMS. The orange badge does not give an individual free range of the site. Random badge checks will be performed through-out the site.
9/4/2025
9 8/26/2025 Please provide final building CX report for base building. Final Commissioning Report September 2025, will be transmitted with this correspondence 9/4/2025
10 8/26/2025 Please provide details of existing RF film and acceptance testing data for this space.
088000.002.01 – RF Shielding and Privacy Film; Signal Defense Films - SD1000/1010 Surface-Applied Film 9/8/2025
11 8/26/2025 Please provide details for the base building FA system. FA Systems information, submittals and drawings shall be transmitted with this correspondence
12 8/26/2025 Section B.1 CLINs states “SEE OPTIONAL FORM 336". Please provide form 336 / Section B CLIN structure.
O+D15:D19ptional form 336 will be issued shortly 9/10/2025
13 8/26/2025 Attachment D - Performance Bond SF-25/ Payment Bond SF-25A (Total of 4 Pages) is referenced in Section J, but not included with the solicitation package. Please provide.
SF25 and SF25A will be sent via email. 9/10/2025
14 8/26/2025
L.11(b) indicates “Preliminary Screening Factors: Submit this portion before all other portions, as this will be the first portion evaluated. See Section M for information required for this portion.
”Section M says in part: “Preliminary Screening Factors:
1.To be eligible for this contract, each Offeror shall be licensed in the state of Virginia. Provide a copy of your firm’s active/current Virginia Department of Professional and Occupation Regulation (VADPOR) contractor’s license dated within three (3) business days of the proposal submission date.”
Please clarify the due date of Part 1 Preliminary Screening Factors.
Virginia construction license is required for any Mt. Weather construction contract. The contract cannot be awarded until license is obtained. 9/10/2025
15 8/26/2025
Regarding Preliminary Screening Factors as stated in Section L.11 and M.1:
AOPS is not presently licensed in the state of Virginia. We respectfully request confirmation that, while we are in the process of securing the required license, the license held by our major subcontractor, JS Global, will be accepted to fulfill this requirement in the interim.
see above 9/10/2025
16 9/9/2025
Section L.12 ADDITIONAL SUBMISSION INFORMATION indicates "(a) A copy of Offeror’s current/valid Commonwealth of Virginia contractor’s license and required bid bond."
Please confirm that a photocopy of the fully executed bid bond will be acceptable for submission, as a the original bond with the wet signature will require additional time for delivery.
A photocopy of the signed bid bond is acceptable (wet signature not required). 9/10/2025