The document is a solicitation for the FY25 MWEOC Site Wide Demolition and Roadway Improvements project, issued on May 1, 2025, and amended on August 21, 2025, with solicitation number 70FA5025R00000009. The contract includes multiple Contract Line Item Numbers (CLINs) covering extensive asbestos containing material (ACM) abatement, soil removal, rock excavation, and optional roof replacement work. Specific line items include:

Base bid and optional tasks involve ACM abatement across multiple materials and locations, such as tile, ceiling tiles, pipe insulation, drywall compound, cork backer insulation, thermal system insulation fittings, waterproofing membranes, vermiculite insulation, electrical components, and fire doors. Optional roof replacement elements include choices between asphalt shingles and standing seam metal roofing (SSMR), with additional options for roof sheathing replacement and gutter/downspout installation. The solicitation provides unit pricing for various quantities, with base quantities ranging from 10 to 3,000 units depending on the specific abatement or replacement task.

View the file

Other files for this federal contract opportunity

Other files attached to ROADWAY & SITEWIDE IMPROVEMENTS, newest first.
File Type Posted
20250814 Roadway Sitewalk Notes.docx DOCX document
Solicitation questions and answers - A00001.pdf PDF
Attach 8 - 2025-0102_20250827_Approved_ESC_SWM_Sheets.pdf PDF
Attach 4 - MW Outage SHEET blank.pdf PDF
Attach 2 - Nutrient credits.pdf PDF
70FA5025R00000012 A0001.pdf PDF
Attach 3 - MWFS Menu.pdf PDF
2020-0097_20241125_Approval_Combined_ESC_SWM_Modification_No._1.pdf PDF
20240226_2023-0056_Approved_Sheets(2).pdf PDF
2020-0097_20241125_Approved_ESC_SWM_Narrative_Calcs.pdf PDF
2023-0056 Plan Submission Checklist 2023-04-03.pdf PDF
Attach 7 - Excavation permit request Form.pdf PDF
Attach 6 - 250821 SOW MWEOC Site Wide Infrastructure FY25 with B127 Updated.pdf PDF
Solicitation questions and answers - A00001.pdf PDF
B127 Roof Replacement As-Builts.pdf PDF
70FA5025R00000012 PROJECT ROADWAYS.pdf PDF
Volume 4-Specifications (3-5-2025).pdf PDF
B420 Demolition and Parking Drawings IFC 3-5-2025.pdf PDF
Building 911 Parking Expansion and Intersection Modification IFC 6-9-2025.pdf PDF
East Valley View Drive Slope and Roadway Parking Repairs IFC 3-5-2025.pdf PDF
Volume 6 Specifications (3-5-2025) .pdf PDF
Volume 5 Specifications (3-5-2025).pdf PDF
Volume 1 Specifications (3-5-2025).pdf PDF
B300-B400 FM Demo IFC 12-8-2024.pdf PDF
Volume 3 Specifications (3-5-2025).pdf PDF
Volume 2-Specifications (3-5-2025).pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY25 MWEOC Site Wide Demolition and Roadway Improvements Issued for Construction Solicitation No. 70FA5025R00000009 May 1, 2025 Amended: August 21, 2025

CLIN

Item Description

Base Bid

Estimated Qty.

Unit Price (Beyond

Base Bid Qty.)

CLIN Price

1 Base Bid 1 LUMP SUM $________

1a Unsatisfactory Soil Removal and

Replacement 200 CY $_____per CY

1b Mass Rock Excavation 500 CY $_____per CY

1c ACM Tile and Mastic Abatement 3000 SF $_____per SF

ACM Ceiling Tile Abatement 80 SF $_____per SF

ACM Pipe Insulation Abatement

100 LF $_____per LF

ACM Drywall Compound

Abatement

2700 SF $_____per SF

ACM Cork Backer Insulation

800 SF $_____per SF

ACM Thermal System Insulation

Fittings Abatement

24 Fittings $_____per Fitting

ACM Waterproofing

Membrane/Vapor Barriers

10 SF $_____per SF

FY25 MWEOC Site Wide Demolition and Roadway Improvements Issued for Construction Solicitation No. 70FA5025R00000009 May 1, 2025 Amended: August 21, 2025

ACM Vermiculite Insulation

10 SF $_____per SF

ACM Sub-Grade Electrical Conduit

/ Transite Pipe Abatement

10 LF $_____per LF

ACM Electrical Components

Abatement 1 Panel Box $_____per Panel Box

ACM Fire Doors 1 Door $_____per Door

1d LBP Door Demolition 5 Doors $_____per Door

2 NOA Compliance Plan 1 LUMP SUM $________

3 NOA Daily Program

Implementation 5 Days

$_____per additional day

4a

(OPTION)

B127 Roof Replacement w/

ASPHALT SHINGLES

1 LUMP SUM $________

4b

(OPTION)

B127 Roof Replacement w/ SSMR 1 LUMP SUM $________

4c

(OPTION)

B127 Roof Sheathing Replacement

(Unit Price Only)

3,000 SF

$_____per SF (up to 15,000sft)

4d

(OPTION)

B127 Additional Gutters and

Downspouts

1 LS LUMP SUM $________