20250814 Roadway Sitewalk Notes.docx

DOCX document 743 KB Posted

Attached to
ROADWAY & SITEWIDE IMPROVEMENTS Federal contract opportunity
Solicitation number
70FA5025R00000012
Issued by
Federal Emergency Management Agency National Community Section

About this file

These are sitewalk notes for a FEMA Roadway & Sitewide Improvements project at Mount Weather Emergency Operations Center, dated 14 August 2025. The notes provide critical updates for potential bidders, including details on tank closures, demolition requirements, and bid submission guidelines. Key updates include a revised list of underground and aboveground storage tanks requiring closure assessments, permission to demolish multiple buildings simultaneously, clarification on concrete disposal, and specific instructions for bid sheet pricing.

The document outlines pricing requirements for Contract Line Items (CLINs), specifying lump sum and unit price submissions for different project components. Base bid quantities include 200 cubic yards of unsatisfactory soil removal and 500 cubic yards of rock excavation. Additional site-specific instructions cover the removal of an undocumented conex box with equipment near Building 408, and guidance on concrete disposal, noting that most materials will need to be hauled offsite. The solicitation is for a Best Value award method, with proposals due August 29th, 2025, covering demolition of existing structures, roof replacement, utility upgrades, and roadway improvements.

View the file

Other files for this federal contract opportunity

Other files attached to ROADWAY & SITEWIDE IMPROVEMENTS, newest first.
File Type Posted
Solicitation questions and answers - A00001.pdf PDF
Attach 8 - 2025-0102_20250827_Approved_ESC_SWM_Sheets.pdf PDF
Attach 3 - MWFS Menu.pdf PDF
Attach 4 - MW Outage SHEET blank.pdf PDF
Attach 2 - Nutrient credits.pdf PDF
70FA5025R00000012 A0001.pdf PDF
2020-0097_20241125_Approved_ESC_SWM_Narrative_Calcs.pdf PDF
2023-0056 Plan Submission Checklist 2023-04-03.pdf PDF
Attach 7 - Excavation permit request Form.pdf PDF
Attach 6 - 250821 SOW MWEOC Site Wide Infrastructure FY25 with B127 Updated.pdf PDF
Solicitation questions and answers - A00001.pdf PDF
2020-0097_20241125_Approval_Combined_ESC_SWM_Modification_No._1.pdf PDF
20240226_2023-0056_Approved_Sheets(2).pdf PDF
Attach 1 - 250821 Bid Form MWEOC Site Wide Infrastructure.pdf PDF
Volume 4-Specifications (3-5-2025).pdf PDF
B127 Roof Replacement As-Builts.pdf PDF
70FA5025R00000012 PROJECT ROADWAYS.pdf PDF
B300-B400 FM Demo IFC 12-8-2024.pdf PDF
Volume 3 Specifications (3-5-2025).pdf PDF
Volume 2-Specifications (3-5-2025).pdf PDF
B420 Demolition and Parking Drawings IFC 3-5-2025.pdf PDF
Building 911 Parking Expansion and Intersection Modification IFC 6-9-2025.pdf PDF
East Valley View Drive Slope and Roadway Parking Repairs IFC 3-5-2025.pdf PDF
Volume 6 Specifications (3-5-2025) .pdf PDF
Volume 5 Specifications (3-5-2025).pdf PDF
Volume 1 Specifications (3-5-2025).pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

14 August 2025 Roadway Sitewalk Notes for Solicitation Update:

1. Updated VDEQ tank closure list is below. This list supersedes the plans, please disregard the plan notes stating the closure requirements.

B315 – 1000 gal AST (Fuel Oil) Registered with DEQ. Will require AST closure assessment.

B320/320A – 2000 gal UST (fuel oil) Not regulated.

B320/320A - 2 AST propane tanks Not regulated.

B310 – 2000 gal UST (fuel oil) Not regulated.

B310 – 10,000 gal UST (MOGAS) Registered with DEQ. Will require UST closure assessment.

B310 – 10,000 gal UST (Diesel) Registered with DEQ. Will require UST closure assessment.

B310 – 400 gal AST (Waste Oil) Not regulated.

B310 – OWS (concrete vault) Not regulated.

B400 – 500 gal UST (fuel oil) Not regulated.

B408/408A – 2000 gal AST (fuel oil) Registered with DEQ. Will require AST closure assessment.

B420 – 1500 gal AST (fuel oil) Not regulated.

2. Please include the removal of this additional manhole and segment of sewer lateral in the estimate of the bid. It was erroneously omitted in the B911/Intersection plans.

3. Disregard all CLINs and phasing regarding the demolition of B310, B315, and B320. These buildings can now be demolished all at once should the successful offeror elect to do so. Refer to sheets 300-400 Demolition Sheets CD-101 and CD-102.

4. A participant inquired if Mount Weather has a concrete disposal site. While MW does have a disposal site for some concrete, we anticipate that the site will not handle the full disposal of concrete demolished in this project. Offerors should anticipate hauling most materials offsite. Concrete materials disposed on MW must be processed to 8” and without rebar.

5. To clarify bid sheet:

a. Provide only Lump Sum Prices for CLINs 1, 2, 4a, 4b, 4d.

b. Provide only Unit Prices for CLINs 1a, 1b, 1c,1d, and 4c for quantities encountered above the base bid included quantities.

c. Provide a Lump Sum Price and a Unit Price for CLIN 3. Lump Sum Price is for 5 days of NOA Daily Program. Unit Price is price per day after day 5.

d. Base Bid includes 200 CY of Unsatisfactory Soil Removal.

e. Base Bid includes 500 CY of Rock Excavation.

f. Rock Excavation includes classified rock with or without NOA (Spec 312000 Part 2.4.B).

6. There is a conex box with equipment adjacent to 408 not shown on the plans. This shall be removed by the contractor.