A003.pdf
PDF 5 MB Posted
- Attached to
- CO FLAP US50(1) Little Blue Creek Canyon
- Solicitation number
- 6982AF20B000008
About this file
This document contains a federal contract opportunity and related amendment for the CO FLAP US50(1) Little Blue Creek Canyon project. The project involves reconstructing 4.17 miles of roadway to provide a consistent 12-foot travel way and 1.5 miles of climbing lanes. New construction work includes large scale rock excavation and embankment, roadway realignment, drainage culvert installation, guardrail, aggregate base, asphalt concrete pavement, minor bridge and bridge railing work, pavement markings, and traffic control. Significant quantities include 180,000 cubic yards of roadway excavation, 38,500 cubic yards of waste, 580 cubic yards of grouted riprap for stream armoring, 60,000 square feet of mechanically stabilized earth wall, 2,500 linear feet of rock bolts, and 70,000 tons of aggregate base. The amendment adds various survey and staking, erosion control, construction schedule, contractor quality control, and testing items. The solicitation number is 6982AF20B000008 and is issued by the Department of Transportation Federal Highway Administration.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
A - 6
Bidder/Offeror please note: Before preparing the bid, carefully read the Solicitation Provisions. Insert a unit bid price, in figures, for each pay item for which a quantity appears in the bid schedule. Multiply the unit price by the quantity for each pay item and show the amount bid. Should any mathematical check made by the Government show a mistake in the amount bid, the corrected unit price extension shall govern. When the word "LPSM" (Lump Sum) appears as a unit bid price, insert an amount for each lump sum pay item. When a sum based on a fixed rate appears for any pay item in the amount bid column, include the Government inserted amount bid for the item in the total bid amount. Total all of the amounts bid for each pay item and show the total bid amount.
Bid Schedule
Project No:CO FLAP US50(1)
Project Name:Little Blue Creek Canyon
Amendment A003
A - 7
Contract Quantity Pay Items
41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK)
56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE)
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
A0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
A0040 15214-2000 SURVEY AND STAKING, RETAINING WALL
ALL LPSM $___LPSM_____ $____________
A0060 15215-1000 SURVEY AND STAKING, APPROACH ROAD
4 EACH $____________ $____________
A0080 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
30 EACH $____________ $____________
A0100 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
2.392 MILE $____________ $____________
A0120 15236-2000 SURVEY CONTROL, GRADE FINISHING
4.510 MILE $____________ $____________
A0140 15301-0000 CONTRACTOR QUALITY CONTROL
ALL LPSM $___LPSM_____ $____________
A0160 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
A0180 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
A0200 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL)
ALL LPSM $___LPSM_____ $____________
A0220 15701-0000 SOIL EROSION CONTROL (NON-STORMWATER CONTROL)
ALL LPSM $___LPSM_____ $____________
A0240 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 8
A0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
A0280 15802-0000 WATERING FOR DUST CONTROL
ALL LPSM $___LPSM_____ $____________
A0300 20101-0000 CLEARING AND GRUBBING
33.0 ACRE $____________ $____________
A0320 20301-0300 REMOVAL OF BOX CULVERT
1 EACH $____________ $____________
A0340 20301-0700 REMOVAL OF DELINEATOR
80 EACH $____________ $____________
A0360 20301-1100 REMOVAL OF GATE
4 EACH $____________ $____________
A0380 20301-1900 REMOVAL OF PIPE CULVERT
30 EACH $____________ $____________
A0400 20301-2400 REMOVAL OF SIGN
50 EACH $____________ $____________
A0420 20302-0700 REMOVAL OF FENCE
17,500 LNFT $____________ $____________
A0440 20302-1200 REMOVAL OF GUARDRAIL
4,800 LNFT $____________ $____________
A0460 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER
1,550 LNFT $____________ $____________
A0480 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 1)
30 SQYD $____________ $____________
A0500 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 2)
30 SQYD $____________ $____________
A0520 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 3)
5.0 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 9
A003 A0540 20401-0000 ROADWAY EXCAVATION
120,000 CUYD $____________ $____________
A0560 20402-0000 SUBEXCAVATION
2,000 CUYD $____________ $____________
A0580 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
560 CUYD $____________ $____________
A0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
135 CUYD $____________ $____________
A0620 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4
360 CUYD $____________ $____________
A0640 25112-2400 PARTIALLY GROUTED RIPRAP, METHOD B, CLASS 4
1,220 CUYD $____________ $____________
A0660 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED
1,800 CUYD $____________ $____________
A0680 25210-0000 ROCKERY
4,800 SQFT $____________ $____________
A0700 25305-1000 REVET MATTRESS, GALVANIZED OR ALUMINIZED COATED
300 SQYD $____________ $____________
A0720 25701-1000 CONTRACTOR FURNISHED GEOSYNTHETIC REINFORCED SOIL (GRS)
RETAINING WALL DESIGN
ALL LPSM $___LPSM_____ $____________
A0740 26001-0000 ROCK BOLT
820 LNFT $____________ $____________
A0760 26002-0000 ROCK DOWEL
4,700 LNFT $____________ $____________
A0780 26201-0000 GEOSYNTHETIC REINFORCED SOIL (GRS) RETAINING WALL
54,000 SQFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 10
A0800 30101-0000 AGGREGATE BASE (CLASS 6)
38,000 TON $____________ $____________
A0860 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH
NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
14,100 TON $____________ $____________
A0880 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
140.0 TON $____________ $____________
A0920 40601-0000 FOG SEAL
22.0 TON $____________ $____________
A0940 41102-1000 PRIME COAT, METHOD 1
51,000 SQYD $____________ $____________
A0960 41105-0000 BLOTTER
75 TON $____________ $____________
A0980 41201-0000 TACK COAT
23.0 TON $____________ $____________
A1000 41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK)
549 SQYD $____________ $____________
A1020 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
2,500 SQYD $____________ $____________
A1040 55221-0000 REPAIR CONCRETE (CDOT DECK PATCHING)
5.0 CUYD $____________ $____________
A1060 55222-0000 REPAIR CONCRETE (CURB)
ALL LPSM $___LPSM_____ $____________
A1080 55603-1000 REMOVE AND RESET BRIDGE RAILING
ALL LPSM $___LPSM_____ $____________
A1100 56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE)
549 SQYD $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 11
A1120 60103-0240 CONCRETE, HEADWALL FOR 54-INCH PIPE CULVERT
5 EACH $____________ $____________
A1140 60201-0600 18-INCH PIPE CULVERT (CMP)
100 LNFT $____________ $____________
A1160 60201-0800 24-INCH PIPE CULVERT (CMP)
180 LNFT $____________ $____________
A1180 60201-1000 36-INCH PIPE CULVERT (CMP)
1,300 LNFT $____________ $____________
A1200 60201-1200 48-INCH PIPE CULVERT (CMP)
320 LNFT $____________ $____________
A1220 60201-1300 54-INCH PIPE CULVERT (CMP)
500 LNFT $____________ $____________
A1240 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT (CMP)
4 EACH $____________ $____________
A1260 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (CMP)
6 EACH $____________ $____________
A1280 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT (CMP)
17 EACH $____________ $____________
A1300 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT (CMP)
7 EACH $____________ $____________
A1320 60210-1300 END SECTION FOR 54-INCH PIPE CULVERT (CMP)
1 EACH $____________ $____________
A1340 60212-1000 ELBOW, 36-INCH
3 EACH $____________ $____________
A1360 60212-1200 ELBOW, 48-INCH
1 EACH $____________ $____________
A1380 60403-0000 INLET (TYPE D)
16 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 12
A1400 60403-0000 INLET (VANE GRATE INLET)
1 EACH $____________ $____________
A1420 60501-0000 STANDARD UNDERDRAIN SYSTEM
2,500 LNFT $____________ $____________
A1440 60602-0900 PIPE ANCHOR ASSEMBLY, 36-INCH (CMP)
2 EACH $____________ $____________
A1460 60901-1200 CURB, CONCRETE, 14-INCH DEPTH
735 LNFT $____________ $____________
A1480 60908-1000 PAVED DITCH, ASPHALT
325 SQYD $____________ $____________
A1500 61701-4100 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS A
50 LNFT $____________ $____________
A1520 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
7,000 LNFT $____________ $____________
A1540 61702-0000 TERMINAL SECTION (TYPE 3K)
1 EACH $____________ $____________
A1560 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
1 EACH $____________ $____________
A1580 61702-1600 TERMINAL SECTION, TYPE MGS FLARED
2 EACH $____________ $____________
A1600 61702-1700 TERMINAL SECTION, TYPE MGS-BAT
1 EACH $____________ $____________
A1620 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3S)
100 LNFT $____________ $____________
A1640 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3G)
50 LNFT $____________ $____________
A1660 61801-0000 CONCRETE BARRIER (TYPE 9 SINGLE SLOPE BARRIER)
780 LNFT $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 13
A1680 61901-0000 FENCE (SNOW FENCE)
1,200 LNFT $____________ $____________
A1700 61901-0000 FENCE (WILDLIFE FRIENDLY)
17,800 LNFT $____________ $____________
A1720 61902-0000 GATE
5 EACH $____________ $____________
A1740 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
100 HOUR $____________ $____________
A1760 62201-0350 BACKHOE
40 HOUR $____________ $____________
A1780 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
80 HOUR $____________ $____________
A1800 62201-2750 MOTOR GRADER
60 HOUR $____________ $____________
A1820 62201-3000 HYDRAULIC EXCAVATOR
200 HOUR $____________ $____________
A1840 62301-0000 GENERAL LABOR
80 HOUR $____________ $____________
A1860 62302-0100 SPECIAL LABOR, SLOPE SCALING
1,100 HOUR $____________ $____________
A1880 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
60 HOUR $____________ $____________
A1900 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
100 HOUR $____________ $____________
A1920 62405-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH
71,000 SQYD $____________ $____________
A1940 62510-2000 SEEDING, HYDRAULIC METHOD
13.5 ACRE $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 14
A1960 62515-2000 MULCHING, HYDRAULIC METHOD
13.5 ACRE $____________ $____________
A1980 62632-0000 PLANTINGS (WILLOW STAKES)
ALL LPSM $___LPSM_____ $____________
A2000 62901-1100 ROLLED EROSION CONTROL PRODUCT, TYPE 4
13,000 SQYD $____________ $____________
A2020 63301-0000 SIGN SYSTEM
45 EACH $____________ $____________
A2040 63309-0100 DELINEATOR, TYPE 1
130 EACH $____________ $____________
A2060 63309-0200 DELINEATOR, TYPE 2
5 EACH $____________ $____________
A2080 63309-0300 DELINEATOR, TYPE 3
85 EACH $____________ $____________
A2100 63326-0000 MUMBLE STRIP
2.5 MILE $____________ $____________
A2120 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID
4.40 MILE $____________ $____________
A2140 63412-0700 RECESSED PAVEMENT MARKINGS, TYPE D, SOLID
4.40 MILE $____________ $____________
A2160 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
ALL LPSM $___LPSM_____ $____________
A2180 63501-3500 TEMPORARY TRAFFIC CONTROL, PUBLIC INFORMATION PROGRAM
ALL LPSM $___LPSM_____ $____________
A2200 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
20 EACH $____________ $____________
A2220 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
1,050 EACH $____________ $____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 15
A2240 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
450 EACH $____________ $____________
A2260 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
38 EACH $____________ $____________
A2280 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
10 EACH $____________ $____________
A2300 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION
4 EACH $____________ $____________
A2320 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
1 EACH $____________ $____________
A2340 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
6,000 LNFT $____________ $____________
A2360 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
1,000 LNFT $____________ $____________
A2380 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
4,000 SQFT $____________ $____________
A2400 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
23.0 MILE $____________ $____________
A2420 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
34,000 HOUR $____________ $____________
A2440 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
5,000 HOUR $____________ $____________
A2460 65101-1000 DRAPED ROCKFALL PROTECTION, WIRE MESH
9,100 SQYD $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:A Schedule Type:Base
Project No:CO FLAP US50(1)
A - 16
Contract Quantity Pay Items
41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK)
56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE)
Amendment Item No. Pay Item No. Description Quantity Unit Unit Price Amount
B0020 15101-0000 MOBILIZATION
ALL LPSM $___LPSM_____ $____________
B0040 15214-2000 SURVEY AND STAKING, RETAINING WALL
ALL LPSM $___LPSM_____ $____________
B0060 15215-1000 SURVEY AND STAKING, APPROACH ROAD
14 EACH $____________ $____________
B0080 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE
40 EACH $____________ $____________
B0100 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL
4.419 MILE $____________ $____________
B0120 15236-2000 SURVEY CONTROL, GRADE FINISHING
8.564 MILE $____________ $____________
B0140 15301-0000 CONTRACTOR QUALITY CONTROL
ALL LPSM $___LPSM_____ $____________
B0160 15401-0000 CONTRACTOR TESTING
ALL LPSM $___LPSM_____ $____________
B0180 15501-0000 CONSTRUCTION SCHEDULE
ALL LPSM $___LPSM_____ $____________
B0200 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL)
ALL LPSM $___LPSM_____ $____________
B0220 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL)
ALL LPSM $___LPSM_____ $____________
B0240 15701-0000 SOIL EROSION CONTROL (NON-STORMWATER CONTROL)
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 17
B0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
ALL LPSM $___LPSM_____ $____________
B0280 15802-0000 WATERING FOR DUST CONTROL
ALL LPSM $___LPSM_____ $____________
B0300 20101-0000 CLEARING AND GRUBBING
62.0 ACRE $____________ $____________
B0320 20301-0300 REMOVAL OF BOX CULVERT
1 EACH $____________ $____________
B0340 20301-0700 REMOVAL OF DELINEATOR
155 EACH $____________ $____________
B0360 20301-1100 REMOVAL OF GATE
4 EACH $____________ $____________
B0380 20301-1900 REMOVAL OF PIPE CULVERT
35 EACH $____________ $____________
B0400 20301-2400 REMOVAL OF SIGN
70 EACH $____________ $____________
B0420 20302-0700 REMOVAL OF FENCE
17,500 LNFT $____________ $____________
B0440 20302-1200 REMOVAL OF GUARDRAIL
10,400 LNFT $____________ $____________
B0460 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER
1,550 LNFT $____________ $____________
B0480 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 1)
30 SQYD $____________ $____________
B0500 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 2)
30 SQYD $____________ $____________
B0520 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 3)
5.0 SQYD $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 18
A003 B0540 20401-0000 ROADWAY EXCAVATION
151,000 CUYD $____________ $____________
B0560 20402-0000 SUBEXCAVATION
2,000 CUYD $____________ $____________
B0580 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1
560 CUYD $____________ $____________
B0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3
225 CUYD $____________ $____________
B0620 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4
360 CUYD $____________ $____________
B0640 25112-2400 PARTIALLY GROUTED RIPRAP, METHOD B, CLASS 4
1,220 CUYD $____________ $____________
B0660 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED
1,800 CUYD $____________ $____________
B0680 25210-0000 ROCKERY
4,800 SQFT $____________ $____________
B0700 25305-1000 REVET MATTRESS, GALVANIZED OR ALUMINIZED COATED
300 SQYD $____________ $____________
B0720 25701-1000 CONTRACTOR FURNISHED GEOSYNTHETIC REINFORCED SOIL (GRS)
RETAINING WALL DESIGN
ALL LPSM $___LPSM_____ $____________
B0740 26001-0000 ROCK BOLT
820 LNFT $____________ $____________
B0760 26002-0000 ROCK DOWEL
4,700 LNFT $____________ $____________
B0780 26201-0000 GEOSYNTHETIC REINFORCED SOIL (GRS) RETAINING WALL
54,000 SQFT $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 19
B0820 30101-0000 AGGREGATE BASE (CLASS 6)
72,000 TON $____________ $____________
B0840 30401-5900 FULL DEPTH RECLAMATION, METHOD 2, 12-INCH DEPTH
0.700 MILE $____________ $____________
B0860 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH
NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL
31,000 TON $____________ $____________
B0900 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
310.0 TON $____________ $____________
B0940 40601-0000 FOG SEAL
48.0 TON $____________ $____________
B0960 41102-1000 PRIME COAT, METHOD 1
113,000 SQYD $____________ $____________
B0980 41105-0000 BLOTTER
160 TON $____________ $____________
B1000 41201-0000 TACK COAT
49.0 TON $____________ $____________
B1020 41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK)
549 SQYD $____________ $____________
B1040 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1
2,500 SQYD $____________ $____________
B1060 55221-0000 REPAIR CONCRETE (CDOT DECK PATCHING)
5.0 CUYD $____________ $____________
B1080 55222-0000 REPAIR CONCRETE (CURB)
ALL LPSM $___LPSM_____ $____________
B1100 55603-1000 REMOVE AND RESET BRIDGE RAILING
ALL LPSM $___LPSM_____ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 20
B1120 56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE)
549 SQYD $____________ $____________
B1140 60103-0240 CONCRETE, HEADWALL FOR 54-INCH PIPE CULVERT
5 EACH $____________ $____________
B1160 60201-0600 18-INCH PIPE CULVERT (CMP)
220 LNFT $____________ $____________
B1180 60201-0800 24-INCH PIPE CULVERT (CMP)
250 LNFT $____________ $____________
B1200 60201-1000 36-INCH PIPE CULVERT (CMP)
1,900 LNFT $____________ $____________
B1220 60201-1200 48-INCH PIPE CULVERT (CMP)
320 LNFT $____________ $____________
B1240 60201-1300 54-INCH PIPE CULVERT (CMP)
500 LNFT $____________ $____________
B1260 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT (CMP)
8 EACH $____________ $____________
B1280 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (CMP)
8 EACH $____________ $____________
B1300 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT (CMP)
23 EACH $____________ $____________
B1320 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT (CMP)
7 EACH $____________ $____________
B1340 60210-1300 END SECTION FOR 54-INCH PIPE CULVERT (CMP)
1 EACH $____________ $____________
B1360 60212-1000 ELBOW, 36-INCH
3 EACH $____________ $____________
B1380 60212-1200 ELBOW, 48-INCH
1 EACH $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 21
B1400 60403-0000 INLET (TYPE D)
20 EACH $____________ $____________
B1420 60403-0000 INLET (VANE GRATE INLET)
1 EACH $____________ $____________
B1440 60501-0000 STANDARD UNDERDRAIN SYSTEM
2,500 LNFT $____________ $____________
B1460 60602-0900 PIPE ANCHOR ASSEMBLY, 36-INCH (CMP)
2 EACH $____________ $____________
B1480 60704-0000 CLEANING CULVERT IN PLACE
2 EACH $____________ $____________
B1500 60901-1200 CURB, CONCRETE, 14-INCH DEPTH
735 LNFT $____________ $____________
B1520 60908-1000 PAVED DITCH, ASPHALT
325 SQYD $____________ $____________
B1540 61701-4100 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS A
50 LNFT $____________ $____________
B1560 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
12,000.0 LNFT $____________ $____________
B1580 61702-0000 TERMINAL SECTION (TYPE 3K)
1 EACH $____________ $____________
B1600 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
1 EACH $____________ $____________
B1620 61702-1600 TERMINAL SECTION, TYPE MGS FLARED
10 EACH $____________ $____________
B1640 61702-1700 TERMINAL SECTION, TYPE MGS-BAT
1 EACH $____________ $____________
B1660 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3G)
50 LNFT $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 22
B1680 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3S)
100 LNFT $____________ $____________
B1700 61801-0000 CONCRETE BARRIER (TYPE 9 SINGLE SLOPE BARRIER)
780 LNFT $____________ $____________
B1720 61901-0000 FENCE (STEEL SNOW FENCE)
1,200 LNFT $____________ $____________
B1740 61901-0000 FENCE (WILDLIFE FRIENDLY)
17,800 LNFT $____________ $____________
B1760 61902-0000 GATE
5 EACH $____________ $____________
B1780 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY
120 HOUR $____________ $____________
B1800 62201-0350 BACKHOE
80 HOUR $____________ $____________
B1820 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED CAPACITY
120 HOUR $____________ $____________
B1840 62201-2750 MOTOR GRADER
80 HOUR $____________ $____________
B1860 62201-3000 HYDRAULIC EXCAVATOR
240 HOUR $____________ $____________
B1880 62301-0000 GENERAL LABOR
120 HOUR $____________ $____________
B1900 62302-0100 SPECIAL LABOR, SLOPE SCALING
1,100 HOUR $____________ $____________
B1920 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES
80 HOUR $____________ $____________
B1940 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES
120 HOUR $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 23
B1960 62405-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH
136,000 SQYD $____________ $____________
B1980 62510-2000 SEEDING, HYDRAULIC METHOD
26.0 ACRE $____________ $____________
B2000 62515-2000 MULCHING, HYDRAULIC METHOD
26.0 ACRE $____________ $____________
B2020 62632-0000 PLANTINGS (WILLOW STAKES)
ALL LPSM $___LPSM_____ $____________
B2040 62901-1100 ROLLED EROSION CONTROL PRODUCT, TYPE 4
13,000 SQYD $____________ $____________
B2060 63301-0000 SIGN SYSTEM (FLASHING BEACON)
1 EACH $____________ $____________
B2080 63301-0000 SIGN SYSTEM
75 EACH $____________ $____________
B2100 63309-0100 DELINEATOR, TYPE 1
230 EACH $____________ $____________
B2120 63309-0200 DELINEATOR, TYPE 2
40 EACH $____________ $____________
B2140 63309-0300 DELINEATOR, TYPE 3
120 EACH $____________ $____________
B2160 63326-0000 MUMBLE STRIP
7.5 MILE $____________ $____________
B2180 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID
7.90 MILE $____________ $____________
B2200 63402-0800 PAVEMENT MARKINGS, TYPE D, BROKEN
0.80 MILE $____________ $____________
B2220 63412-0700 RECESSED PAVEMENT MARKINGS, TYPE D, SOLID
9.00 MILE $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 24
B2240 63412-0800 RECESSED PAVEMENT MARKINGS, TYPE D, BROKEN
1.50 MILE $____________ $____________
B2260 63413-0050 RECESSED PAVEMENT MARKINGS, SYMBOLS (THERMOPLASTIC)
6 EACH $____________ $____________
B2280 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC CONTROL SUPERVISOR
ALL LPSM $___LPSM_____ $____________
B2300 63501-3500 TEMPORARY TRAFFIC CONTROL, PUBLIC INFORMATION PROGRAM
ALL LPSM $___LPSM_____ $____________
B2320 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
20 EACH $____________ $____________
B2340 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE
1,050 EACH $____________ $____________
B2360 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM
450 EACH $____________ $____________
B2380 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B
38 EACH $____________ $____________
B2400 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE CHANGEABLE MESSAGE SIGN
10 EACH $____________ $____________
B2420 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION
4 EACH $____________ $____________
B2440 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC SIGNAL SYSTEM
1 EACH $____________ $____________
B2460 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER
6,000 LNFT $____________ $____________
B2480 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE
1,000 LNFT $____________ $____________
B2500 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
4,000 SQFT $____________ $____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
A - 25
B2520 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS
26.5 MILE $____________ $____________
B2540 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER
38,000 HOUR $____________ $____________
B2560 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR
6,000 HOUR $____________ $____________
B2580 65101-1000 DRAPED ROCKFALL PROTECTION, WIRE MESH
9,100 SQYD $____________ $____________
Submitted by:____________________________________ Schedule Total:____________
Bid Schedule Schedule:B Schedule Type:Base
Project No:CO FLAP US50(1)
E-36
CO FLAP US50(1)
Little Blue Creek Canyon
156.07 Maintaining Roadways During Non-Work Periods. Maintain roadways and traffic control for public traffic during periods when work is not in progress. Snow removal to provide public access is the responsibility of the maintaining agency. If a “shoo-fly” is used, submit design proposed for use.
Design shoo-flies that may be left in place over weekends, can accommodate two-way traffic and meet 25 mph design criteria according to the 2011 AASHTO Green Book. Remove all Shoo-fly’s prior to winter shutdown unless approved be CO.
156.07 Limitations on Construction Operations.
(c) Delete the first sentence and substitute the following:
For alternate one-way traffic control, provide a minimum lane width of 12 feet. For two-way traffic, provide a minimum roadway width of 24 feet.
(i) Delete the text and substitute the following:
(i) Impacts to public traffic. If emergency services needs to travel through the project, suspend operations and ensure the roadway is traversable to emergency services. In addition to the holidays and times shown in Section 108.01, the following restrictions shown below apply through the duration of project. The permitted closures and openings to public traffic are shown below. All traffic that arrives at the queue during opening times must be allowed to pass through the project.
Table 156-1 Closures/Openings to Public Traffic
Type Month - Month Day to
Day Time Remarks
Weekend Openings
Notice to Proceed – End of Project
Friday – Monday
5:30pm Friday – 8:30am Monday
US 50 open to two-way traffic without delays
Day Closure April 1, 2021 – July 31, 2021
Monday – Friday
8:30 a.m. - 12:30 p.m.
1:30 p.m. - 5:30 p.m.
Applies to Sta. 587+00 to Sta. 617+00 only. Refer to
108.01 for more information.
Day Closure April 1, 2021 – April 30, 2022
Monday – Friday
8:30 a.m. - 12:30 p.m.
1:30 p.m. - 5:30 p.m.
Alternating Traffic
May 1, 2022 – End of Project
Monday – Friday
6:30 a.m. – 7:30 p.m.
Limit construction caused delays to public traffic to a maximum of 30 minutes per passage through the project.
Nighttime Closure
April 1, 2021 – End of Project
Monday – Thursday
7:30 p.m. – 6:30 a.m. Refer to (1) below.
E-37
(1) From October 16 to April 1, U.S. 50 must be open to two-way traffic during nighttime without delays if winter weather is expected on the CO-92 route. CO-92 is not plowed by CDOT during the night. Coordinate with the CO for effective dates.
For all times not shown in the table, limit construction caused delays to public traffic to a maximum of 30 minutes per passage through the project.
For emergency openings due to Interstate 70 closure, limit delays to public traffic to a maximum of 30 minutes per passage through the project.
Add the following:
(k) Limit the length of area affected as approved by the CO. See Subsection 108.01 for limitations on work.
Section 157. — SOIL EROSION AND SEDIMENT CONTROL
Delete the entire Section and substitute the following:
Section 157. — SOIL EROSION CONTROL, SEDIMENT CONTROL, AND POLLUTION
PREVENTION
Description
157.01 This work consists of preparing and managing a Stormwater Pollution Prevention Plan (SWPPP) including non-stormwater pollution prevention. This work also consists of implementing the SWPPP including but not limited to furnishing, constructing, and maintaining soil erosion and sediment control devices to eliminate or minimize pollutants in stormwater discharges from the project.
Material
157.02 Conform to the following Subsections:
Backfill material 704.03 Concrete masonry unit 725.07(c) Fertilizer 713.03 Fiber rolls and socks 713.12 Floating turbidity curtains 713.21 Gravel bags 713.13 Mulch 713.05 Plastic lining 725.12 Prefabricated filter insert 713.20 Riprap 705.02 Rock mulch 705.07 Sandbags 713.14 Sediment filter bags 713.19 Seed 713.04 Separation and stabilization geotextile and geotextile filter 714.01(a) Silt fence 713.16
Sheet and Description
B9-B12 B13-B14 B15 B16 B17-B19 B20 B21-B22 B23 S2
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
A0020 15101-0000 MOBILIZATION LPSM ALL
A0040 15214-2000 SURVEY AND STAKING, RETAINING WALL LPSM All ALL
A0060 15215-1000 SURVEY AND STAKING, APPROACH ROAD EACH 4 4
A0080 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE EACH 29 1 30
A0100 15225-0000 SLOPE, REFERENCE, AND CLEARING AND
GRUBBING CONTROL MILE 2.392 2.392
A0120 15236-2000 SURVEY CONTROL, GRADE FINISHING MILE 4.510 4.510
A0140 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
A0160 15401-0000 CONTRACTOR TESTING LPSM ALL
A0180 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0200 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL) LPSM ALL See SCR Section 157
A0220 15701-0000 SOIL EROSION CONTROL (NON-STORMWATER See SCR Section 157
CONTROL) LPSM ALL
A0240 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL) LPSM ALL See SCR Section 157
A0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN LPSM ALL See SCR Section 157
A0280 15802-0000 WATERING FOR DUST CONTROL LPSM ALL
A0300 20101-0000 CLEARING AND GRUBBING ACRE 31.0 2.0 33.0
A0320 20301-0300 REMOVAL OF BOX CULVERT EACH 1 1
A0340 20301-0700 REMOVAL OF DELINEATOR EACH 80 80
A0360 20301-1100 REMOVAL OF GATE EACH 4 4
A0380 20301-1900 REMOVAL OF PIPE CULVERT EACH 29 1 30
A0400 20301-2400 REMOVAL OF SIGN EACH 45 5 50
A0420 20302-0700 REMOVAL OF FENCE LNFT 17,064 436 17,500
A0440 20302-1200 REMOVAL OF GUARDRAIL LNFT 4,763 37 4,800
A0460 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER LNFT 1,503 47 1,550
A0480 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 1) SQYD 28 2 30
A0500 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 2) SQYD 28 2 30
A0520 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 3) SQYD 5.0 5.0
A003 A0540 20401-0000 ROADWAY EXCAVATION CUYD 111,946 8,054 120,000
A0560 20402-0000 SUBEXCAVATION CUYD 2,000 2,000
A0580 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1 CUYD 531 29 560
A0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3 CUYD 129 6 135
A0620 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4 CUYD 340 20 360
A0640 25112-2400 PARTIALLY GROUTED RIPRAP, METHOD B, See Special 251-B
CLASS 4 CUYD 1,160 60 1,220
A0660 25201-1000 SPECIAL ROCK EMBANKMENT,
MECHANICALLY-PLACED CUYD 1,800 1,800
A0680 25210-0000 ROCKERY SQFT 4,560 240 4,800
A0700 25305-1000 REVET MATTRESS, GALVANIZED OR ALUMINIZED
COATED SQYD 288 12 300
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A -O ct -2
:0 P
M
Remarks and/or Determination of Estimated
Quantity Pay Item Description Unit
Estimated Quantities
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t
STATE PROJECT
B1 FLAP US50(1) Little Blue
Creek CanyonCO
SHEET
NUMBER
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
A0720 25701-1000 CONTRACTOR FURNISHED GEOSYNTHETIC
REINFORCED SOIL (GRS) RETAINING WALL
DESIGN LPSM All ALL
A0740 26001-0000 ROCK BOLT LNFT 820 As Directed By The CO
A0760 26002-0000 ROCK DOWEL LNFT 4,700 As Directed By The CO
A0780 26201-0000 GEOSYNTHETIC REINFORCED SOIL (GRS)
RETAINING WALL SQFT 51,400 2,600 54,000
A0800 30101-0000 AGGREGATE BASE (CLASS 6) TON 36,297 1,703 38,000
A0860 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX,
1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM
SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL TON 13,457 643 14,100
A0880 40105-3000 ANTISTRIP ADDITIVE, TYPE 3 TON 134.6 5.4 140.0
A0920 40601-0000 FOG SEAL TON 20.4 1.6 22.0
A0940 41102-1000 PRIME COAT, METHOD 1 SQYD 49,000 2,000 51,000
A0960 41105-0000 BLOTTER TON 75
A0980 41201-0000 TACK COAT TON 21.4 1.6 23.0
A1000 41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK) SQYD 549 549 Contract Quantity
A1020 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1 SQYD 2,500 2,500
A1040 55221-0000 REPAIR CONCRETE (CDOT DECK PATCHING) CUYD 4.2 0.8 5.0
A1060 55222-0000 REPAIR CONCRETE (CURB) LPSM All ALL
A1080 55603-1000 REMOVE AND RESET BRIDGE RAILING LPSM All ALL
A1100 56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE) SQYD 549 549 Contract Quantity
A1120 60103-0240 CONCRETE, HEADWALL FOR 54-INCH PIPE Includes Wingwalls
CULVERT EACH 5 5
A1140 60201-0600 18-INCH PIPE CULVERT (CMP) LNFT 89 11 100
A1160 60201-0800 24-INCH PIPE CULVERT (CMP) LNFT 168 12 180
A1180 60201-1000 36-INCH PIPE CULVERT (CMP) LNFT 1,247 53 1,300
A1200 60201-1200 48-INCH PIPE CULVERT (CMP) LNFT 300 20 320
A1220 60201-1300 54-INCH PIPE CULVERT (CMP) LNFT 446 54 500
A1240 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT
(CMP) EACH 2 2 4
A1260 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
(CMP) EACH 4 2 6
A1280 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT
(CMP) EACH 15 2 17
A1300 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT
(CMP) EACH 5 2 7
A1320 60210-1300 END SECTION FOR 54-INCH PIPE CULVERT
(CMP) EACH 1 1
A1340 60212-1000 ELBOW, 36-INCH EACH 3 3
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (2
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B2 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
A1360 60212-1200 ELBOW, 48-INCH EACH 1 1
A1380 60403-0000 INLET (TYPE D) EACH 15 1 16
A1400 60403-0000 INLET (VANE GRATE INLET) EACH 1 1
A1420 60501-0000 STANDARD UNDERDRAIN SYSTEM LNFT 2,500 2,500
A1440 60602-0900 PIPE ANCHOR ASSEMBLY, 36-INCH (CMP) EACH 2 2
A1460 60901-1200 CURB, CONCRETE, 14-INCH DEPTH LNFT 700 35 735
A1480 60908-1000 PAVED DITCH, ASPHALT SQYD 311 14 325
A1500 61701-4100 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS A LNFT 44 6 50
A1520 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A
STEEL POSTS LNFT 6,775 225 7,000
A1540 61702-0000 TERMINAL SECTION (TYPE 3K) EACH 1 1
A1560 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT EACH 1 1
A1580 61702-1600 TERMINAL SECTION, TYPE MGS FLARED EACH 2 2
A1600 61702-1700 TERMINAL SECTION, TYPE MGS-BAT EACH 1 1
A1620 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3S) LNFT 100 100
A1640 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3G) LNFT 50 50
A1660 61801-0000 CONCRETE BARRIER (TYPE 9 SINGLE SLOPE
BARRIER) LNFT 760 20 780
A1680 61901-0000 FENCE (SNOW FENCE) LNFT 1,150 50 1,200
A1700 61901-0000 FENCE (WILDLIFE FRIENDLY) LNFT 17,012 788 17,800
A1720 61902-0000 GATE EACH 5 5
A1740 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY HOUR 100
A1760 62201-0350 BACKHOE HOUR 40
A1780 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED
CAPACITY HOUR 80
A1800 62201-2750 MOTOR GRADER HOUR 60
A1820 62201-3000 HYDRAULIC EXCAVATOR HOUR 200
A1840 62301-0000 GENERAL LABOR HOUR 80
A1860 62302-0100 SPECIAL LABOR, SLOPE SCALING HOUR 1,100 As Directed By The CO
A1880 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES HOUR 60
A1900 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES HOUR 100
A1920 62405-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH SQYD 67,137 3,863 71,000
A1940 62510-2000 SEEDING, HYDRAULIC METHOD ACRE 12.8 0.7 13.5
A1960 62515-2000 MULCHING, HYDRAULIC METHOD ACRE 12.8 0.7 13.5
A1980 62632-0000 PLANTINGS (WILLOW STAKES) LPSM All ALL See Sheet D10
A2000 62901-1100 ROLLED EROSION CONTROL PRODUCT, TYPE 4 SQYD 13,000 13,000 See SCR Section 629
A2020 63301-0000 SIGN SYSTEM EACH 42 3 45
A2040 63309-0100 DELINEATOR, TYPE 1 EACH 130 130
A2060 63309-0200 DELINEATOR, TYPE 2 EACH 5 5
A2080 63309-0300 DELINEATOR, TYPE 3 EACH 85 85
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (3
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B3 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
A2100 63326-0000 MUMBLE STRIP MILE 2.2 0.3 2.5
A2120 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID MILE 4.28 0.12 4.40
A2140 63412-0700 RECESSED PAVEMENT MARKINGS, TYPE D, SOLID MILE 4.27 0.13 4.40
A2160 63501-1000 TEMPORARY TRAFFIC CONTROL, TRAFFIC
CONTROL SUPERVISOR LPSM All ALL
A2180 63501-3500 TEMPORARY TRAFFIC CONTROL, PUBLIC See SCR Section 110
INFORMATION PROGRAM LPSM All ALL
A2200 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE
TYPE 3 EACH 20 20
A2220 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE EACH 1,015 35 1,050
A2240 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM EACH 425 25 450
A2260 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT
TYPE B EACH 38 38
A2280 63502-2000 TEMPORARY TRAFFIC CONTROL, PORTABLE
CHANGEABLE MESSAGE SIGN EACH 10 10
A2300 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION EACH 4 4
A2320 63502-3100 TEMPORARY TRAFFIC CONTROL, TRAFFIC
SIGNAL SYSTEM EACH 1 1
A2340 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE
BARRIER LNFT 6,000 6,000
A2360 63503-1000 TEMPORARY TRAFFIC CONTROL, PLASTIC FENCE LNFT 1,000 1,000
A2380 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION
SIGN SQFT 4,000 4,000
A2400 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT
MARKINGS MILE 21.5 1.5 23.0
A2420 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER HOUR 32,750 1,250 34,000
A2440 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR HOUR 4,750 250 5,000
A2460 65101-1000 DRAPED ROCKFALL PROTECTION, WIRE MESH SQYD 8,310 790 9,100
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (4
SUMMARY OF QUANTITIES - Schedule A
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B4 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
B0020 15101-0000 MOBILIZATION LPSM ALL
B0040 15214-2000 SURVEY AND STAKING, RETAINING WALL LPSM All ALL
B0060 15215-1000 SURVEY AND STAKING, APPROACH ROAD EACH 14 14
B0080 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE EACH 37 3 40
B0100 15225-0000 SLOPE, REFERENCE, AND CLEARING AND
GRUBBING CONTROL MILE 4.419 4.419
B0120 15236-2000 SURVEY CONTROL, GRADE FINISHING MILE 8.564 8.564
B0140 15301-0000 CONTRACTOR QUALITY CONTROL LPSM ALL
B0160 15401-0000 CONTRACTOR TESTING LPSM ALL
B0180 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
B0200 15701-0000 SOIL EROSION CONTROL (EROSION CONTROL) LPSM ALL See SCR Section 157
B0220 15701-0000 SOIL EROSION CONTROL (SEDIMENT CONTROL) LPSM ALL See SCR Section 157
B0240 15701-0000 SOIL EROSION CONTROL (NON-STORMWATER See SCR Section 157
CONTROL) LPSM ALL
B0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN LPSM ALL See SCR Section 157
B0280 15802-0000 WATERING FOR DUST CONTROL LPSM ALL
B0300 20101-0000 CLEARING AND GRUBBING ACRE 60.1 1.9 62.0
B0320 20301-0300 REMOVAL OF BOX CULVERT EACH 1 1
B0340 20301-0700 REMOVAL OF DELINEATOR EACH 155 155
B0360 20301-1100 REMOVAL OF GATE EACH 4 4
B0380 20301-1900 REMOVAL OF PIPE CULVERT EACH 34 1 35
B0400 20301-2400 REMOVAL OF SIGN EACH 66 4 70
B0420 20302-0700 REMOVAL OF FENCE LNFT 17,064 436 17,500
B0440 20302-1200 REMOVAL OF GUARDRAIL LNFT 10,325 75 10,400
B0460 20302-1300 REMOVAL OF GUARDRAIL, CONCRETE BARRIER LNFT 1,503 47 1,550
B0480 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 1) SQYD 28 2 30
B0500 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 2) SQYD 28 2 30
B0520 20303-0200 REMOVAL OF BRIDGE DECK (CDOT CLASS 3) SQYD 5.0 5.0
A003 B0540 20401-0000 ROADWAY EXCAVATION CUYD 143,735 7,265 151,000
B0560 20402-0000 SUBEXCAVATION CUYD 2,000 2,000
B0580 25101-0100 PLACED RIPRAP, METHOD A, CLASS 1 CUYD 531 29 560
B0600 25101-0300 PLACED RIPRAP, METHOD A, CLASS 3 CUYD 212 13 225
B0620 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4 CUYD 340 20 360
B0640 25112-2400 PARTIALLY GROUTED RIPRAP, METHOD B, See Special 251-B
CLASS 4 CUYD 1,160 60 1,220
B0660 25201-1000 SPECIAL ROCK EMBANKMENT,
MECHANICALLY-PLACED CUYD 1,800 1,800
B0680 25210-0000 ROCKERY SQFT 4,560 240 4,800
B0700 25305-1000 REVET MATTRESS, GALVANIZED OR ALUMINIZED
COATED SQYD 288 12 300
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (5
SUMMARY OF QUANTITIES - Schedule B
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B5 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
B0720 25701-1000 CONTRACTOR FURNISHED GEOSYNTHETIC
REINFORCED SOIL (GRS) RETAINING WALL
DESIGN LPSM All ALL
B0740 26001-0000 ROCK BOLT LNFT 820 As Directed By The CO
B0760 26002-0000 ROCK DOWEL LNFT 4,700 As Directed By The CO
B0780 26201-0000 GEOSYNTHETIC REINFORCED SOIL (GRS)
RETAINING WALL SQFT 51,400 2,600 54,000
B0820 30101-0000 AGGREGATE BASE (CLASS 6) TON 68,446 3,554 72,000
B0840 30401-5900 FULL DEPTH RECLAMATION, METHOD 2,
12-INCH DEPTH MILE 0.682 0.018 0.700
B0860 40101-5600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX,
1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM
SIZE AGGREGATE, 0.3 TO <3 MILLION ESAL TON 29,725 1,275 31,000
B0900 40105-3000 ANTISTRIP ADDITIVE, TYPE 3 TON 297.2 12.8 310.0
B0940 40601-0000 FOG SEAL TON 46.2 1.8 48.0
B0960 41102-1000 PRIME COAT, METHOD 1 SQYD 108,754 4,246 113,000
B0980 41105-0000 BLOTTER TON 160
B1000 41201-0000 TACK COAT TON 47.0 2.0 49.0
B1020 41301-0000 ASPHALT PAVEMENT MILLING (BRIDGE DECK) SQYD 549 549 Contract Quantity
B1040 41801-1000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1 SQYD 2,500 2,500
B1060 55221-0000 REPAIR CONCRETE (CDOT DECK PATCHING) CUYD 4.2 0.8 5.0
B1080 55222-0000 REPAIR CONCRETE (CURB) LPSM All ALL
B1100 55603-1000 REMOVE AND RESET BRIDGE RAILING LPSM All ALL
B1120 56901-0000 CONCRETE OVERLAY (POLYESTER CONCRETE) SQYD 549 549 Contract Quantity
B1140 60103-0240 CONCRETE, HEADWALL FOR 54-INCH PIPE Includes Wingwalls
CULVERT EACH 5 5
B1160 60201-0600 18-INCH PIPE CULVERT (CMP) LNFT 200 20 220
B1180 60201-0800 24-INCH PIPE CULVERT (CMP) LNFT 216 34 250
B1200 60201-1000 36-INCH PIPE CULVERT (CMP) LNFT 1,749 151 1,900
B1220 60201-1200 48-INCH PIPE CULVERT (CMP) LNFT 300 20 320
B1240 60201-1300 54-INCH PIPE CULVERT (CMP) LNFT 446 54 500
B1260 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT
(CMP) EACH 6 2 8
B1280 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT
(CMP) EACH 6 2 8
B1300 60210-1000 END SECTION FOR 36-INCH PIPE CULVERT
(CMP) EACH 21 2 23
B1320 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT
(CMP) EACH 5 2 7
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (6
SUMMARY OF QUANTITIES - Schedule B
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B6 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
B1340 60210-1300 END SECTION FOR 54-INCH PIPE CULVERT
(CMP) EACH 1 1
B1360 60212-1000 ELBOW, 36-INCH EACH 3 3
B1380 60212-1200 ELBOW, 48-INCH EACH 1 1
B1400 60403-0000 INLET (TYPE D) EACH 19 1 20
B1420 60403-0000 INLET (VANE GRATE INLET) EACH 1 1
B1440 60501-0000 STANDARD UNDERDRAIN SYSTEM LNFT 2,500 2,500
B1460 60602-0900 PIPE ANCHOR ASSEMBLY, 36-INCH (CMP) EACH 2 2
B1480 60704-0000 CLEANING CULVERT IN PLACE EACH 2 2
B1500 60901-1200 CURB, CONCRETE, 14-INCH DEPTH LNFT 700 35 735
B1520 60908-1000 PAVED DITCH, ASPHALT SQYD 311 14 325
B1540 61701-4100 GUARDRAIL SYSTEM CRG, TYPE 2, CLASS A LNFT 44 6 50
B1560 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A
STEEL POSTS LNFT 11,587.5 412.5 12,000.0
B1580 61702-0000 TERMINAL SECTION (TYPE 3K) EACH 1 1
B1600 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT EACH 1 1
B1620 61702-1600 TERMINAL SECTION, TYPE MGS FLARED EACH 10 10
B1640 61702-1700 TERMINAL SECTION, TYPE MGS-BAT EACH 1 1
B1660 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3G) LNFT 50 50
B1680 61707-0000 STRUCTURE TRANSITION RAILING (TYPE 3S) LNFT 100 100
B1700 61801-0000 CONCRETE BARRIER (TYPE 9 SINGLE SLOPE
BARRIER) LNFT 760 20 780
B1720 61901-0000 FENCE (STEEL SNOW FENCE) LNFT 1,150 50 1,200
B1740 61901-0000 FENCE (WILDLIFE FRIENDLY) LNFT 17,012 788 17,800
B1760 61902-0000 GATE EACH 5 5
B1780 62201-0200 DUMP TRUCK, 8 CUBIC YARD MINIMUM CAPACITY HOUR 120
B1800 62201-0350 BACKHOE HOUR 80
B1820 62201-0950 WHEEL LOADER, 3 CUBIC YARD MINIMUM RATED
CAPACITY HOUR 120
B1840 62201-2750 MOTOR GRADER HOUR 80
B1860 62201-3000 HYDRAULIC EXCAVATOR HOUR 240
B1880 62301-0000 GENERAL LABOR HOUR 120
B1900 62302-0100 SPECIAL LABOR, SLOPE SCALING HOUR 1,100 As Directed By The CO
B1920 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES HOUR 80
B1940 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES HOUR 120
B1960 62405-0200 PLACING CONSERVED TOPSOIL, 3-INCH DEPTH SQYD 129,890 6,110 136,000
B1980 62510-2000 SEEDING, HYDRAULIC METHOD ACRE 23.8 2.2 26.0
B2000 62515-2000 MULCHING, HYDRAULIC METHOD ACRE 23.8 2.2 26.0
B2020 62632-0000 PLANTINGS (WILLOW STAKES) LPSM All ALL See Sheet D10
B2040 62901-1100 ROLLED EROSION CONTROL PRODUCT, TYPE 4 SQYD 13,000 13,000 See SCR Section 629
-O ct -2
:0 P
M
MileStone: Amendment A003 Amendment Review Date: 10/15/20 Report Date: 10/15/20
N
C O
\u s5
(1
R o a d w a y\
S u p p o rt
C
FT
\p ro cu re m en t& a cq u is it io n s\
A S tr u ct u re
E x\
[C O
FL
A P U
S (1
S O
Q A .x ls m
]S h ee t (7
SUMMARY OF QUANTITIES - Schedule B
A M E N D
Line Item No.
Pay Item Number
Pay Item Description Unit
Estimated Quantities
Remarks and/or Determination of Estimated
Quantity
STATE PROJECT
B7 FLAP US50(1) Little Blue
Creek CanyonCO
Grading Summary
Drainage Summary
Surfacing Summary
Guardrail Summary
Permanent Signing
Summary
Permanent Pavement Marking
Summary
Temporary Traffic Control
Summary
Miscellaneous Summaries
Bridge General Notes
Allowance Bid
Schedule
B2060 63301-0000 SIGN SYSTEM (FLASHING BEACON) EACH 1 1
B2080 63301-0000 SIGN SYSTEM EACH 70 5 75
B2100 63309-0100 DELINEATOR, TYPE 1 EACH 230 230
B2120 63309-0200 DELINEATOR, TYPE 2 EACH 40 40
B2140 63309-0300 DELINEATOR, TYPE 3 EACH 120 120
B2160 63326-0000 MUMBLE STRIP MILE 7.0 0.5 7.5
B2180 63402-0700 PAVEMENT MARKINGS, TYPE D, SOLID MILE 7.76 0.14 7.90
B2200 63402-0800 PAVEMENT MARKINGS, TYPE D, BROKEN MILE 0.57 0.