J-7_Pricing Sheet_ SEA ATCT and Base Building.docx
DOCX document 23 KB Posted
- Solicitation number
- 697DCK-24-R-00423
About this file
This document is a pricing sheet for the modernization of the SEA ATCT and Base Building located at the Seattle-Tacoma International Airport in SeaTac, WA. It provides a detailed cost breakdown by work item, including labor, materials, and totals for each item. The pricing sheet includes a project subtotal, profit, overhead, and grand total for the ATCT/Base Building project. It also includes two bid alternates for replacement of the chemical feed system and Victaulic pipe fittings, with similar cost breakdowns. The related federal contract opportunity is for the SEA ATCT and S46 TRACON Major Mechanical Upgrades, to be procured by the Department of Transportation Federal Aviation Administration Southwestern Region.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I - SECTION B
SUPPLIES/SERVICES & PRICE/COST
Revised July 25, 2024
The contractor must furnish all materials, labor, supervision, equipment, etc. to modernize the SEA ATCT and Base Building located at the Seattle–Tacoma International Airport in SeaTac, WA in strict conformance to the solicitation/contract including the project Specifications and its attached drawings at the following prices:
Item Description $Labor $Materials $Labor & Materials
| 1 | General Requirements | ______________ _____________ ________________ | |||
| 2 | Existing Conditions | ______________ _____________ ________________ | |||
| 3 | Concrete | ______________ _____________ ________________ | |||
| 4 | Metals | ______________ _____________ ________________ | |||
| 5 | Thermal and Moisture | ______________ _____________ ________________ | |||
| 6 | Finishes | ______________ _____________ ________________ | |||
| 7 | Plumbing | ______________ _____________ ________________ | |||
| 8 | HVAC | ______________ _____________ ________________ | |||
| 9 | Electrical | ______________ _____________ ________________ | |||
| 10 | Electronic Safety & | ||||
| Security | ______________ _____________ ________________ | ||||
| 11 | Earthwork | ______________ _____________ ________________ | |||
| 12 | Exterior Improvements | ______________ _____________ ________________ | |||
| 13 | 1-Year Service | ||||
| Maintenance | ______________ | _____________ | _______________ | ||
| 14 | Subtotals | ______________ _____________ ________________ |
| 15 | PROJECT SUBTOTAL FOR LABOR AND MATIERALS: | $________________ | ||
| 16 | PROFIT APPLIED TO LINE 15: | ________% $________________ | ||
| 17 | OVERHEAD AND G&A APPLIED TO LINE 15: | ________% $________________ | ||
| 18 | PROJECT GRAND TOTAL (Total of lines 15, 16, 17): | $________________ |
Please indicate Grand Total cost for each asset, including labor and materials, profit, and overhead.
| 19 | ATCT/Base Building | $________________ | |
| 20 | PROJECT GRAND TOTAL (Same as line 18) | $________________ |
SCHEDULE OF ALTERNATES
SCHEDULE OF ALTERNATES (Updated on July 25, 2024)
BID ALTERNATE - 1
Provide bid alternate pricing for replacement of Chemical Feed System.
Item Division Description $ Labor $ Materials $ Labor & Materials
21 Chemical Feed System
| 22 BID ALTERNATE SUBTOTAL FOR LABOR AND MATERIALS: | $ | ||
| 23 PROFIT APPLIED TO LINE 34: | % | $ | |
| 24 OVERHEAD AND G&A APPLIED TO LINE 34: | % | $ | |
| 25 PROJECT GRAND TOTAL (Total of lines 22, 23, & 24): | $ |
BID ALTERNATE - 2
Provide bid alternate pricing for replacement of Victaulic Pipe Fittings.
Item Division Description $ Labor $ Materials $ Labor & Materials
26 Chemical Feed System
| 27 BID ALTERNATE SUBTOTAL FOR LABOR AND MATERIALS: | $ | ||
| 28 PROFIT APPLIED TO LINE 34: | % | $ | |
| 29 OVERHEAD AND G&A APPLIED TO LINE 34: | % | $ | |
| 30 PROJECT GRAND TOTAL (Total of lines 27, 28, & 29): | $ |