This is a pre-proposal conference presentation for an Architecture and Engineering (A&E) Services Indefinite Delivery/Indefinite Quantity (IDIQ) multiple award contract solicitation (6973GH-26-R-00130) issued by the FAA Mike Monroney Aeronautical Center.

The solicitation uses Qualifications Based Selection (QBS) in accordance with AMS T3.8.2-18, with no pricing information required in initial proposals—only SF-330 submissions will be evaluated on qualifications. Three types of A&E services are defined: Type A (planning, concept studies, field surveys, feasibility determination), Type B (construction documents and construction administration), and Type C (additional services including full-time observation, special inspections, and commissioning services). The current contract awarded 70 taskings worth $13.8 million across five A&E firms. Major projects featured include the $33 million CAMI WiWaves Research Facility (45,000 sf with 8,000 sf wave tank), $8.3 million VTOL Performance and Analysis Range hangar, $7.2 million Hangar 9 renovation, $16 million Headquarters renovation, and several other facility improvements totaling over $90 million in planned capital projects. Questions must be submitted by September 10, 2026 at 2:00 PM CST, with proposals due September 24, 2026 at 4:00 PM CST. Award evaluation uses a rating scale (4.0 Excellent through 0.0 Unacceptable) based on qualifications factors outlined in Section M, with cost/price deferred until after QBS evaluation for selected firms. Offerors must comply with all Statement of Work requirements, follow proposal instructions precisely, tab information according to the exact numerical outline, and sign the solicitation and all amendments to avoid proposal deficiencies.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Architecture and Engineering (A&E) Services Solicitation

6973GH-26-R-00130

Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award

Pre-Proposal Conference

26 August 2026, 11:00am

FAA - Mike Monroney Aeronautical Center

Agenda

1. Opening Remarks

2. Program Background

3. Statement of Work

4. Acquisition Strategy – Sections L and M

5. Milestones

6. Keys to Developing a Good Proposal

7. Pricing (Section B)

Opening Remarks

▪ Contracting Officer – Stephanie Riddle

▪ Contract Specialist – Charity Daniel

▪ Program Management – Tracy Hartman

▪ Participant List Roll Call

▪ “At the Center” Video - 4-minute overview of the programs at the MMAC

A&E IDIQ Overview

▪ Five A&E Firms on current contract

▪ Three Types of Services: Types A, B, & C

Type A: Planning, Concept Studies, Field Surveys, Fact Finding Type B: Design Docs for Construction, Construction Administration Type C: Additional services, inspections, testing and other services beyond those listed in Type A and B

▪ 70 Taskings worth $13.8M awarded on last 5-year contract

Program Background

CAMI WiWaves Research Facility

▪ $33M Research Facility, New Constrcution

▪ ~45,000 sf with an 8,000 sf Wave Tank

Mobile System Test Bed (vehicle facility)

▪ $3.6M New construction

▪ ~5,300 sf

VTOL - Performance and Analysis Range

• $8.3M New construction

• Hangar and support building, street extension and site utility extensions

Solar Array Phase 2

▪ $4.8M new construction

▪ Site, infrastructure, switchgear, array

ARB Renovation (in design)

▪ Renovation of 145,000 sf building

▪ New envelope and stair tower

▪ New HVAC, electrical system, & lighting

Hangar 9 Renovation

▪ $7.2M

▪ Renovation of 248,000 sf building, including renovation of offices, restrooms, and hangar lighting.

Headquarters Renovation

▪ $16M

▪ Renovation of 170,000 sf building, including replacement of HVAC ductwork, controls, VAVs, electrical switchgear, MCC, and branch panels.

Type A Services:

Are generally preliminary and investigative in nature. All items listed in this section are not automatically required as part of Type A Services. Only items necessary to accomplish the project requirements described in the project Statement of Work are required. Type A Services may include, but are not limited to the following:

1. Development of program requirements

2. Field surveys and investigations

3. Determination of project feasibility

4. Preparation of concept drawings and project schedule milestones

5. Preparation of drawings of an existing or new facility, where current drawings are not available

6. Subsurface investigations (Soil Borings/Geotechnical Services)

7. Architectural, Structural, Civil, Electrical, and Mechanical investigations of an existing building, where current information is not available and to verify accuracy of existing record documents

Statement of Work

Type A Services (continued)

8. Surveys (topographic, boundary, utility locations; sizes and capacities)

9. Preparation of models, color renderings, photographs, or other presentation materials

10. Travel and per diem associated with directed trips exceeding 25 miles from the A/E’s local office

11. Economic analysis, budget, and cost estimates

12. Preparation of electronic media

13. Conversion of printed drawings to electronic media

14. Consolidation of existing drawings and planned project drawings into one electronic record set per facility or system

15. Engineering calculations

16. Energy and water audits, life cycle cost analysis per CFR 435

17. Master planning

Type A Services (continued)

18. Topographical surveys, utility surveys, excavations, soil borings, soil analysis, chemical tests, laboratory tests, pressure tests, electrical tests, corrosion and cathodic protection tests, and any other tests required for a complete design of each project

19. Preparation of “AS-BUILT” drawings in approved electronic media not associated with Type B services

Type B Services Provide construction documents for competitive bidding and associated construction administration.

Work under Type B Services must include the following elements in fulfillment of the requirements described in the project Statement of Work:

1. Site investigations; review and/or coordination meetings

2. Preparation of construction drawings and project schedule milestones

3. Preparation of construction specifications

4. Construction cost estimates

5. Energy and water audits with updates per design modifications

6. Design analysis required for each discipline

7. Preparation of construction documents in approved electronic media format

8. Submission of construction documents to local, city, and state code enforcement officials for review and permitting

Type B Services (continued)

9. Attendance at City of Oklahoma City Planning, Council, and similar meetings to present and/or respond to questions regarding permit applications

10. Construction Administration (CA) will consist of the elements listed below as part of all Type B Service taskings. Additional CA services beyond these listed in this section may be included as Type C Services:

a. Review and approval or other appropriate action of contractor’s submittals such as shop drawings and product data and samples, but only for the limited purpose of checking for conformance with information given and the design concept as expressed in the contract documents

b. Visit the site at intervals appropriate to the stages of construction to maintain familiarity with the progress and quality of the work completed, and to determine if the work is being performed in a manner indicating that is in accordance with the Contract Documents

i. Unless otherwise specified, site visits shall occur at an interval not to exceed one month

ii. Additional site visits may be required based on work being performed and rate of progress

Type B Services (continued)

c. Preparation and processing of Addenda, Requests for Information (RFI), Requests for Proposal

(RFP), requests for change orders with supporting documentation, cost estimates, and project data as necessary.

d. Preparation of a set of record “AS-BUILT” drawings to be delivered in hardcopy and electronic media showing significant changes in the work made during construction based on marked-up prints, drawings, and other data furnished by the contractor to the A&E.

e. Participation in Pre-Bid Meetings, Pre-Construction Meetings, Progress Meetings, Field Inspections, concrete reinforcing inspections, above-ceiling inspections, in-wall inspections, roof inspections, systems Testing, Pre-Final and Final Inspections.

i. Pre-Bid Meetings, Pre-Construction Meetings, and selected Progress Meetings may be attended virtually, depending on the status of the project.

ii. All inspections/site observations will be conducted in-person.

Type C Services Include additional construction administration services, inspections, testing and other services beyond that listed in Type B. All the items listed in this section are not automatically required as part of Type C Services. Only the items necessary to accomplish the project requirements described in the project Statement of Work are required. Type C Services may include, but are not limited to the following:

1. Additional Construction Administrative Services for full-time on-site Observation of daily construction activities. This will be based upon the Construction Inspector hourly rates schedule.

2. Extensive/full-time supervision and/or inspection of construction above and beyond those provided under Type B services

3. Special Inspections and Tests as required by International Building Code 2015, Chapter 17

4. Commissioning services commencing with the start of the design process and follow on through construction administration. These services may include:

a. Developing a commissioning plan

Type C Services (continued)

b. Design phase commissioning

c. Construction phase commissioning

d. Develop specific equipment and system functional performance test procedures.

e. Review Commissioning documentation for completeness and compliance with contract requirements.

f. Review, approve, and coordinate system start-ups and Owner training.

g. Issue a final Commissioning Report.

5. Other services as specified

Acquisition Strategy - Section L

▪ Qualifications Based Selection (QBS) assessment for award IAW

AMS T3.8.2-18

▪ Offer shall be compliant with “all” requirements stated in Statement of Work

▪ Please note that no proposed pricing is to be provided at this time. An evaluation based on qualifications will be completed based on the submission of the offeror’s SF-330

▪ Non-conformance with the instructions provided in the ITO may result in an unfavorable proposal evaluation

Acquisition Strategy - Section M

▪ Evaluation Factors For Award, 2.1.3

▪ Rating & Score based on (4.0 Excellent / 3.0 Good / 2.0 Satisfactory /

1.0 Marginal / 0.0 Unacceptable)

▪ Evaluation process will not take price into consideration - Section 2.7 Cost / Price

Milestones

EVENT DATE TIME

Pre-Solicitation Conference 26 Aug 26 11:00 A.M. CST

Questions From Offerors 10 Sept 26 2:00 P.M. CST

Receipt of Proposals 24 Sept 26 4:00 P.M. CST

Estimated Award TBD

▪ Demonstrate a thorough understanding of requirements and inherent risks

▪ Demonstrate sufficient resources to meet the requirements

▪ Support your statements with facts, analysis and substantiating data to illustrate that you have valid and practical solutions for all requirements

▪ Substantiate, don’t simply make claims:

– Tell the who, what, when, where, how, how often, etc.

▪ Do not repeat the language in the Statement of Work (SOW), just reference the section of the SOW to which you are referring

Keys to Developing a Good Proposal

▪ Understand the Solicitation requirements

▪ Understand the SOW

▪ Understanding the evaluation criteria will help you know where to place emphasis in your proposal

▪ Follow the proposal instructions – provide the requested information.

▪ Tab the information

– Don’t make us have to guess or search for answers

– Follow the exact numerical outline in the instructions

▪ Don’t make changes to the SOW and submit a new version

– Document stands as written

– Don’t submit a Contractor’s Statement of Work (CSW)

▪ Don’t make changes to the Solicitation and submit a new version

– Document stands as written and amended by CO only

Typical Proposal Shortfalls

▪ Proposal instructions are not followed

- Information is not provided in the way it was requested.

- Too little or too much information

▪ Statements in the proposal are not well supported

▪ Proposals are not well organized

- Does not follow proposal instruction's structure

▪ Deficiencies – preclude award

- Information provided does not support claims of compliance.

- Proposal is non-compliant to the requirements.

▪ Not signing the Solicitation and all amendments

Pricing (Section B)

▪ No proposed pricing is to be provided at this time IAW AMS T3.8.2-18

▪ Section B – Supplies or Services and Costs/Prices

- No pricing information to be included in the initial proposal of the model contract

▪ Section L – Instructions, Conditions, and Notices to Respondents for Proposal Preparation

5.1 General Instructions

The following instructions for Cost/Price information will be required for those firms contacted upon completion of the QBS evaluation and to the Offeror who is deemed responsible in accordance with the Acquisition Management System (AMS), whose proposal conforms to the solicitation’s requirements (to include all stated terms, conditions, representations, and certifications) and is judged, based on the evaluation factors, to represent the highest qualified to the Government

Summary

▪ This briefing/training was designed to give you an overview of what the Government expects to see in your proposal

▪ The formal solicitation is the only document that should be relied upon in determining the Government’s requirements

▪ Submit questions to the CS; questions and answers will be posted to SAM.GOV

Slide 1
Slide 2
Slide 3
Slide 4:
Slide 5
Slide 6:
Slide 7:
Slide 8:
Slide 9
Slide 10
Slide 11:
Slide 12:
Slide 13:
Slide 14:
Slide 15:
Slide 16:
Slide 17:
Slide 18:
Slide 19:
Slide 20:
Slide 21:
Slide 22:
Slide 23:
Slide 24
Slide 25:
Slide 26:
Slide 27:

File details come from the government source that posted it. Updated .