SMR4 Attachment J-06 - GSIP Draft.pdf
PDF 446 KB Posted
- Solicitation number
- 693KA7-23-R-00002
About this file
This document is a Generic Site Implementation Plan (GSIP) for the Federal Aviation Administration's (FAA) Airport Surface Detection Equipment, Model 3 (ASDE-3) Surface Movement Radar (SMR) Replacement program. The GSIP provides details on the SMR4 system, including its functional and physical description, as well as the roles and responsibilities of the various FAA organizations involved in the implementation.
Key details include:
- The SMR4 will replace the aging ASDE-3 SMRs at up to 34 locations in the National Airspace System.
- The contract will include a base period and two option periods to acquire and install the SMR4 systems.
- The program includes activities such as program management, quality assurance, configuration management, system design, installation, testing, training, and logistics support.
- The FAA has established a Safety Management System and identified one new hazard related to ice buildup that will be mitigated by including antenna heaters.
- Coordination will be required with various FAA stakeholders, including Air Traffic, Engineering Services, and the System Support Center.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Aviation Administration (FAA)
Generic Site Implementation Plan (GSIP)
Airport Surface Detection Equipment, Model 3 (ASDE-3) Surface Movement
Radar (SMR) Replacement
Version 0
DRAFT
October 25, 2024
NOTE: The GSIP (Attachment J-6) is provided to the Contractor for Site Survey and Site Engineering Report (SER) Contract Data Requirements List IM02 (CDRL IM02) planning and development purposes. The Section C – Statement of Work (SOW) will take precedence in the case of any conflict.
Contents
SECTION 1: SCOPE/BACKGROUND
SECTION 2: SYSTEM DESCRIPTION
2.1. Functional Description
2.2. Physical Description
SECTION 3: ROLES AND RESPONSIBILITIES
3.1. Program Office (PO)
3.2. Engineering Services (ES)
3.3. District Offices
3.4. Project Implementer (PI)
3.5. National Airway System Engineering (NASE)
3.6. Service Center, Planning and Requirements Group
3.7. System Support Center (SSC)
3.8. Air Traffic (AT)
SECTION 4: LOGISTICS SUPPORT
SECTION 5: OPERATIONS SUPPORT/LIFECYCLE SUSTAINMENT
SECTION 6: DESIGN REQUIREMENTS
6.1. Local Site Adaptation
6.2. Environmental and Occupational Safety & Health (EOSH)
SECTION 7: SAFETY MANAGEMENT SYSTEM (SMS) REQUIREMENTS
SECTION 8: IMPLEMENTATION REQUIREMENTS
8.1. Physical Space and Integration
8.2. Implementation Coordination - Communications
SECTION 9: RISK MANAGEMENT
SECTION 10: APPENDICES
10.1. APPENDIX A. POINTS OF CONTACTS
10.2. APPENDIX B. LIST OF REFERENCES
10.3. APPENDIX C. LIST OF ACRONYMS
10.4. APPENDIX D. STANDARD SYSTEM CONFIGURATIONS
10.5. APPENDIX E. SAFETY RISK MANAGEMENT DOCUMENTATION
SIR 693KA7-25-R-00001
Surface Movement Radar Model 4 (SMR4)
Section J, Attachment J-06
SECTION 1: SCOPE/BACKGROUND
The ASDE-3 SMR Replacement program is replacing aging ASDE-3 SMRs (SMR3) in the National Airspace System (NAS), and upon Joint Resource Council (JRC) approval at Final Investment Decision (FID), will execute the acquisition plans. The SMR3 used at Airport Surface Detection Equipment - Model X (ASDE-X) and Airport Surface Surveillance Capability (ASSC) airports are beyond the manufacturer’s end-of-life expectancy and have obsolescence and supportability issues.
At an additional seventeen (17) ASDE-X airports, there are two (2) Surface Movement Radar- Raytheon (SMRr) and seventeen (17) Surface Movement Radar-Improved (SMRi) systems; two
(2) airports have a dual configuration SMRi. The planned completion date for replacing the two
(2) SMRr systems with SMRi systems is 2025. The Surface Surveillance Portfolio Board approved a Service Life Expectancy Program (SLEP) to replace the SMRr with the SMRi transceivers on December 17, 2019. A 2018 Diminishing Manufacturing Sources and Material Shortages (DMSMS) study indicated that the SMRi Transceiver Assembly/Cabinet could be sustained until 2035 after SLEP completion. The SMR3 Replacement program includes an option to replace the SMRi systems.
The activities required to plan and implement Surface Movement Radar, Model 4 (SMR4) include the following:
• Program Management
• Quality Assurance
• Configuration Management
• Environmental and Occupational
Safety and Health (EOSH)
• System Design
• Systems Engineering
• Service and Support
• Integrated Logistics Support
• Development of Technical Data
• Test and Evaluation
• Training
• System Production
• Site Implementation
• Transfer and Data Rights
There are fifty-three (53) SMRs in the NAS. Thirty-four (34) are SMR3 and nineteen (19) are SMRi. The plan is to replace the existing fifty-three (53) beyond end-of-life expectancy SMRs with a new SMR solution.
• Thirty-four (34) SMR3 systems across eighteen (18) ASDE-X airports, nine (9) ASSC airports, and three (3) support facilities. Four (4) ASDE-X airports have a dual SMR3 configuration.
• Nineteen (19) SMRi systems are located at seventeen (17) ASDE-X airports. Two airports have a dual SMRi configuration.
The Program Office (PO) will use an SMR4 vendor to perform implementation activities that will be monitored by the PO and Engineering Services (ES).
The scope includes vendor modifications to the form, fit, or function of a Commercial Off-The- Shelf (COTS) SMR to meet interface and other FAA requirements. The contract will include a base period and two option periods to perform the work:
• Base Period:
o Acquire and install seven (7) First Article SMRs o Development for interfaces, maintainability, and performance o System testing o Development of training o Logistics and depot support
• Option Period 1: acquire and install a minimum of four (4) and a maximum 27 Production SMR Systems
• Option Period 2: acquire and install a minimum of four (4) and a maximum 19 Production SMR Systems
Key milestones are the Base Period Completion, Option Period 1 Completion, and Option Period 2 Completion.
SECTION 2: SYSTEM DESCRIPTION
SMR4 is a subsystem of the FAA Surface Surveillance Systems, ASDE-X and ASSC.
2.1. Functional Description
SMR4 will perform the following functions:
• Perform Initialization and Startup
• Detect Non-Cooperative Targets o Transmit o Receive
• Process Signal o Perform Target Processing o Perform Clutter Processing
• Provide Data Outputs o Processed Digital Video o Radar Target Reports o Operational Status Reports
• Provide Monitor and Control Capabilities o Provide Status o Provide Control
2.2. Physical Description
The following is a summary of commercial SMR equipment1:
• Antenna and Motor
• Waveguide
• Transceiver
1 In accordance with JO 6000.50E, SMR4 equipment list will be included in the GSIP after contract award, and prior to starting the first keysite.
• Radar Data Processor
• Antenna Control
• Maintenance Terminal
• Power Supplies
• Ethernet Network Components
SECTION 3: ROLES AND RESPONSIBILITIES
The FAA SMR4 Implementation Team consists of the organizations, roles, and responsibilities shown below.
3.1. Program Office (PO)
Within the Program Management Office (PMO), the PO, Program Manager, Project Lead, and Implementation Lead coordinates and monitors the program and provides direction to ensure that program milestones and goals are met.
3.2. Engineering Services (ES)
The PO has discussed the following list of activities that ES will perform to support this project:
• Participate and provide operational support during site surveys
• Provide a Resident Engineer (RE) to be the FAA’s onsite Technical Onsite
Representative (TOR) when the vendor is working within FAA facilities o Escort in FAA facilities and on Airport Operations Area (AOA)
• Provide current As-Built drawings to PO for SMR3 facilities
• Conduct structural analysis of air traffic control tower for the SMR4
• Review and comment on vendor design / construction / installation drawings
• Participate in project review and status meetings for each implementation
• Coordinate outages and downtime with System Support Center (SSC) and Air Traffic
Control (ATC)
• Remove SMR3 cables, as required
• Conduct Operational Risk Management (ORM) with SSC and ATC
• Complete site prep for new equipment. Site prep includes providing equipment room power, ground plates, cable trays, minor building/wall modifications, and equipment mounts, if needed
• Participate in Contractor Acceptance Inspections (CAI), Site Acceptance Testing (SAT), and Joint Acceptance Inspections (JAI)
• Incorporate facility red-line drawings into FAA repository
3.3. District Offices
The AJW District Offices coordinate with SSC Field Offices.
3.4. Project Implementer (PI)
The SMR4 PIs are the PO and Engineering Services. PO provides monitoring and direction as specified in Section 3.1. Engineering Services has responsibilities identified in Section 3.2. The vendor is responsible for installing and interfacing the SMR4 to the ASDE-X and ASSC systems at FAA facilities.
The PIs are responsible for:
• Site Surveys
• Coordinating and preparing Project Risk Plans (PRP)
• Developing and coordinating Engineering packages
• Monitoring risk mitigation and EOSH/hazardous material compliance activities
• Assessing safety and security of onsite activities
• Participating in CAI/JAI
• Managing project execution within agreed upon scope, schedule, and budget.
3.5. National Airway System Engineering (NASE)
NASE leads the Optimization Team. The responsibilities of NASE are to:
• Optimize the SMR4 system’s adaptation settings to site specific conditions
• Conduct vehicle runs and software adaptations to verify optimum system performance
• Provide engineering support after commissioning including investigation of reported failures from operational sites
3.6. Service Center, Planning and Requirements Group
Planning and Requirements Group, which includes the Program Planning Manager (PPM) or Program Implementation Manager (PIM), is responsible to:
• Create, track, and coordinate the Project Baseline Scope (PBS) and Project Scope Agreement (PjSA)
• Manage the Corporate Work Plan (CWP) updates
• Coordinate and finalize the PBS
• Transfer the project to the PI
• Provide TOR for onsite support for site access and construction activities
• Participate in site surveys
• Perform site preparation
• Review and approve engineering designs
• Manage the initial funding and funding adjustments in coordination with the PO
• Coordinate outage planning and execution with operational groups
• Coordinate among Service Area groups, such as Engineering Services, Operations
Engineering Support Group (OESG), Technical Services Operations Group (TSOG) and District Offices.
3.7. System Support Center (SSC)
The SSC responsibilities include:
• Participate in site surveys
• Participate in Government inspections and testing activities, including JAI
• Provide overall operational risk management guidance
• Review and approve PRP
• Prepare, coordinate, and approve Operational Risk Management Plans (ORMP)
• Participate in the Program/Project document review process
• Review and approve engineering designs
• Submit requirements into CWP
• Designate the equipment locations to account for space availability
• Support coordination of system outages
• Perform partial JAI walk-through of the site preparation and equipment installation
• Provide judgment of the site readiness to commission the equipment
• Perform formal JAI for system acceptability
3.8. Air Traffic (AT)
The local AT manager’s responsibilities are to:
• Assess impact to air traffic operations and work with the RE, TOR, and/or SSC Manager to mitigate these impacts
• Support ORM assessments
• Support coordination of system outages
• Support commissioning/acceptance activities
• Provide judgment of the site readiness to commission equipment.
SECTION 4: LOGISTICS SUPPORT
The PO will provide Integrated Logistics Support (ILS) that includes site spares, site consumables, depot spares, support, and test equipment through Interim Contractor Depot Level Support (ICDLS) services using the SMR4 vendor. The vendor will transition logistics support to the FAA Logistics Center when directed by the PO.
The PO will develop site specific disposition plans for SMR3 equipment.
SECTION 5: OPERATIONS SUPPORT/LIFECYCLE
SUSTAINMENT
The vendor will support and sustain SMR4 until completion and acceptance of CAI. After CAI, the FAA takes ownership of the operational SMR4. The FAA Logistics Center and NASE will be responsible for operations support and lifecycle sustainment.
SECTION 6: DESIGN REQUIREMENTS
The SMR4 SOW and System Specification Document requires compliance with FAA Orders and Directives for design and implementation of systems in the NAS.
6.1. Local Site Adaptation
SMR4 will replace SMR3 at existing locations and towers. No additional real estate, obstruction analysis, or flight procedure considerations are required for the operational SMR. Cranes or helicopter lifts will be required to remove SMR3 and lift SMR4 equipment into position. FAA AJW-L500 is responsible for acquiring lifts, cranes, FAA Form 7460, and other approvals as needed.
6.2. Environmental and Occupational Safety & Health (EOSH)
The PO will address the following EOSH requirements:
• Environmental, Disposal
• Seismic Activity
• Electrical Safety
• Fire Life Safety
• Occupational Noise
• Fall Protection
• Signage, labeling, and materials handling instructions.
SECTION 7: SAFETY MANAGEMENT SYSTEM (SMS)
REQUIREMENTS
The ADSE-3 SMR Replacement project conducted a Safety Risk Management Panel on March 10, 2021. The panel was comprised of stakeholders representing AJW, National Air Traffic Controllers Association (NATCA), Professional Aviation Safety Specialist (PASS), and Subject Matter Experts (SMEs) in air traffic operations, technical operations, and safety. The acting Director of FAA Safety and Technical Training (AJI) 3 approved the Safety Risk Management Document (SRMD) on September 27, 2022. A copy of the signed SRMD is available on the Surface Surveillance Portfolio Knowledge Services Network (KSN) site.
The SRM panel identified one new hazard associated with the project. The panel determined ice buildup to be a persistent cause of the SMR being removed from service at certain locations, which is a critical fault for the entire ASDE system (refers to complete ASDE-X or ASSC), resulting in a loss of surveillance. The hazard is rated with a likelihood of D, Extremely Remote (0 events /40,000,000 operations), and a hazard risk of 2D, Medium. The hazard is mitigated by a safety requirement to include an antenna heater for locations prone to icing.
SECTION 8: IMPLEMENTATION REQUIREMENTS
The vendor will provide sizes and system integration requirements for SMR4 prior to the completion of On-Site Development Test (OSDT) and key site implementation. The vendor will perform a site survey and design for each site and deliver a SER that details required site preparation. The SER will address environmental and EOSH requirements. The vendor will develop a Construction Drawing Package for each site based on the existing facility.
8.1. Physical Space and Integration
Existing infrastructure, including commercial power requirements, grounding, bonding and lightning protection systems, and Heating, Ventilating, and Air Conditioning (HVAC) requirements, must be considered for the new equipment. Site surveys will identify the specific local requirements.
8.2. Implementation Coordination - Communications
The PO and ES will coordinate with local site personnel. Site personnel include AT and Technical Operations Managers and Airway Transportation System Specialists (ATSS) that are responsible for supporting surveillance facilities. In addition, coordination will take place with the site’s NATCA and PASS representatives.
SECTION 9: RISK MANAGEMENT
The ASDE-3 SMR Replacement program risk, issue, and opportunity process are established in accordance with the PO Risk, Issue, and Opportunity (RIO) Management Plan (PO-PLN-0002, Revision 1, dated June 15, 2014) and Attachment J-11 - Surface Surveillance Program Standard Operating Procedure (SOP) RIO Management Plan, Version 2, dated February 1, 2024. The objective is to identify RIOs and manage them effectively to support the overall success of the project. The RIO Manager is responsible for implementing this process. The Surface Surveillance Portfolio RIO Management SOP will be used for the PRP.
There is a single RIO Board that supports all projects in the Surface Surveillance Portfolio. It is referred to as the Surface Surveillance RIO Board. This board is conducted the 2nd Thursday of each month. The Surface Surveillance RIO Board Chair is currently the Surface Surveillance Project Management and Acquisition Lead. All FAA stakeholders involved in the SMR3 Replacement Program are encouraged to attend the RIO Board. The primary stakeholder organizations include:
• PO
• ES
• FAA Second Level Engineering
• FAA Logistics Center
• AT
The SMR3 Replacement Program team implements a robust RIO Management Process. The RIOs identified during this process are stored on the Surface Surveillance Portfolio KSN site.
SECTION 10: APPENDICES
10.1. APPENDIX A. POINTS OF CONTACTS
Name Role Organization Phone E-Mail
10.2. APPENDIX B. LIST OF REFERENCES
Lists of references are available in the documents where they are specified as applicable and referenced in the requirements.
10.3. APPENDIX C. LIST OF ACRONYMS
Acronym Term
AJI FAA Safety and Technical Training AJW FAA Technical Operations AOA Airport Operations Area ASDE-3 Airport Surface Detection Equipment, Model 3 ASDE-X Airport Surface Detection Equipment, Model X ASSC Airport Surface Surveillance Capability AT Air Traffic ATC Air Traffic Control ATSS Airway Transportation System Specialists CAI Contractor Acceptance Inspections CDRL Contract Data Requirements List CWP Corporate Work Plan COTS Commercial Off-The-Shelf DMSMS Diminishing Manufacturing Sources and Material Shortages EOSH Environmental and Occupational Safety & Health ES Engineering Services FAA Federal Aviation Administration FID Final Investment Decision GSIP Generic Site Implementation Plan HVAC Heating, Ventilating, and Air Conditioning ICDLS Interim Contractor Depot Level Support ILS Integrated Logistics Support JAI Joint Acceptance Inspections JRC Joint Resource Council KSN Knowledge Services Network NAS National Airspace System NASE National Airway System Engineering NATCA National Air Traffic Controllers Association OESG Operations Engineering Support Group ORM Operational Risk Management ORMP Operational Risk Management Plan OSDT On-Site Development Test PASS Professional Aviation Safety Specialist PBS Project Baseline Scope PjSA Project Scope Agreement
Acronym Term PI Project Implementer PIM Program Implementation Manager PMO Program Management Office PO Program Office PPM Program Planning Manager PRP Project Risk Plans RE Resident Engineer RIO Risk, Issue, and Opportunity SAT Site Acceptance Testing SER Site Engineering Report SLEP Service Life Expectancy Program SME Subject Matter Expert SMR Surface Movement Radar
SMR3 ASDE-3 SMR
SMR4 Surface Movement Radar, Model 4 SMRi Surface Movement Radar-Improved SMRr Surface Movement Radar-Raytheon SMS Safety Management System SOP Standard Operating Procedure SOW Statement of Work SSC System Support Center SRMD Safety Risk Management Document TOR Technical On-site Representatives TSOG Technical Services Operations Group
10.4. APPENDIX D. STANDARD SYSTEM CONFIGURATIONS
System configurations will be provided after OSDT, prior to key site implementation.
10.5. APPENDIX E. SAFETY RISK MANAGEMENT DOCUMENTATION
A copy of the signed SRMD is available on the Surface Surveillance Portfolio KSN site. The Safety Requirement excerpt from the SRMD is below.
| Section 1: SCOPE/BACKGROUND |
| Section 2: SYSTEM DESCRIPTION |
| 2.1. Functional Description |
| 2.2. Physical Description |
| Section 3: ROLES AND RESPONSIBILITIES |
| 3.1. Program Office (PO) |
| 3.2. Engineering Services (ES) |
| 3.3. District Offices |
| 3.4. Project Implementer (PI) |
| 3.5. National Airway System Engineering (NASE) |
| 3.6. Service Center, Planning and Requirements Group |
| 3.7. System Support Center (SSC) |
| 3.8. Air Traffic (AT) |
| Section 4: LOGISTICS SUPPORT |
| Section 5: OPERATIONS SUPPORT/LIFECYCLE SUSTAINMENT |
| Section 6: DESIGN REQUIREMENTS |
| 6.1. Local Site Adaptation |
| 6.2. Environmental and Occupational Safety & Health (EOSH) |
| Section 7: SAFETY MANAGEMENT SYSTEM (SMS) REQUIREMENTS |
| Section 8: IMPLEMENTATION REQUIREMENTS |
| 8.1. Physical Space and Integration |
| 8.2. Implementation Coordination - Communications |
| Section 9: RISK MANAGEMENT |
| Section 10: APPENDICES |
| 10.1. APPENDIX A. POINTS OF CONTACTS |
| 10.2. APPENDIX B. LIST OF REFERENCES |
| 10.3. APPENDIX C. LIST OF ACRONYMS |
| 10.4. APPENDIX D. STANDARD SYSTEM CONFIGURATIONS |
| 10.5. APPENDIX E. SAFETY RISK MANAGEMENT DOCUMENTATION |