This is a solicitation for a firm fixed price purchase order to perform drydocking repairs and an ABS Intermediate Survey on the T.S. KENNEDY, a training ship owned by the Massachusetts Maritime Academy. The work includes a USCG Drydock Exam, Internal Structural Exam, Tailshaft Inspection, and ABS Intermediate Survey for a non-ESP cargo ship over 15 years of age. Additional work includes tail shaft examination, line shaft bearing inspection, hull blasting and coating, ultrasonic thickness gauging, tank cleaning and inspections, propeller and stern tube bearing replacement, and crop and renewal of various steel structures and foundations in the engine room. The period of performance is from March 1 to May 1, 2020, with the ship available for drydocking transit on February 26 and to be returned to active service by May 1. A site visit will be held on December 17, 2019, and questions are due by December 20. The complete solicitation will be posted on or about December 6, 2019.

View the file

Other files

File Type Posted
6933A220Q000005 - Orig Attachment 1 Quote Pricing Sheet.xlsx XLSX spreadsheet
SHAFTING WRENCHES 1-2.pdf PDF
AUX MACH RM SW SERVICE SYS DIA- 540TV-001-524-20(E).pdf PDF
540TV-001-167-02 (ALL SHEETS).pdf PDF
SHAFTING DETAILS COUPLING C3-100-S43-1-2.pdf PDF
Interspeed 6400NA.pdf PDF
E-Program Files-AN-ConnectManager-SSIS-TDS-PDF-Intershield_300V_eng_usa_A4_20150204.pdf PDF
540TV-583-01E Fire & Safety Plan.pdf PDF
Approved Coatings Spreadsheet3.pdf PDF
18027 KENNEDY SHELL CONNECTIONS.PDF PDF
6933A220Q000005 T.S. KENNEDY FY-20 Drydocking Repairs.pdf PDF
540TV-001-835-09 WELDING SEQUENCE.pdf PDF
128-Shaft Alignment Guide_e.pdf PDF
DRW and Ref materials listed in the SOW.xlsx XLSX spreadsheet
SEA CHESTS C3-100 S48-23-1 REV 4.pdf PDF
Hydrotorque Origional Parts Outfitting.pdf PDF
540TV-001-321-01 REV. W ELECTRICAL LOAD ANALYSIS.pdf PDF
Internzational Interline 925.pdf PDF
Hinge DRW Figure 43A.pdf PDF
SHAFTING DETAILS COUPLING C3-100-S43-1-3.pdf PDF
TS Kennedy Tanks Log 5-29-2015 start of tank request.xls XLS spreadsheet
6933A220Q000005 - Attachment 1 Quote Pricing Sheet.xlsx XLSX spreadsheet
RUDDER STOCK CARRIER & BEARINGS C3-100-S22-1-3.pdf PDF
Intergard 264 (2).pdf PDF
Approved Coatings Spreadsheet2.pdf PDF
INTERLAC 665.pdf PDF
540TV-001-801-01 - General Arrangement.pdf PDF
Interfine 5703.pdf PDF
AUX SEA CHESTS PORT SIDE 1-3.pdf PDF
Detail of echo sounder.docx DOCX document
RRF Coatings Guidelines[Apr 2000].pdf PDF
Pages from SVR_Part_4_e-Jan18 2.pdf PDF
ARRGT. OF SHAFTING C3-1--S43-1-1.pdf PDF
156-s11-5-5 All sheets.pdf PDF
Interthane 990 Marine.pdf PDF
KDY CAPACITY PLAN.pdf PDF
TS Kennedy Valve Tracking.xlsx XLSX spreadsheet
172-S48-23-03BC - 48-23-3BC - OVERBOARD DISCHARGE SHELL EXPANSION & LIST OF SEA VALVES.pdf PDF
Docking Plan C3-100 S7-0-1BC.pdf PDF
ds-80.pdf PDF
TANK CAPACITY CURVES C3-100 S29-1-3 BC.pdf PDF
System Requirements.pdf PDF
SHELL EXP. AFT 1-5 C3-100-S11-1-2 .pdf PDF
1208-S33-2 KENNEDY navlab vestibule.pdf PDF
TG Gland seal Reg.pdf PDF
WELDING SEQUENCE C3-100-S29-6-3.pdf PDF
Suggested Sources AB removal.docx DOCX document
SHELL EXP. FWD 1-4 C3-100-S11-1-1.pdf PDF
RUDDER 1-4.pdf PDF
Surface Prep.pdf PDF
Show 40 more

Latest 50 of 68 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

028200-1

TABLE OF CONTENTS

PAGE

TABLE OF CONTENTS

ASBESTOS ABATEMENT

PART 1 - GENERAL

1.1 Introduction

1.2 Description of the Abatement Work

1.3 Definitions

1.4 Regulations and References

1.5 Submittals

1.6 Daily Reports

1.7 Product Handling

PART 2 - PRODUCTS

2.1 Materials

2.2 Equipment

PART 3 - EXECUTION

3.1 Controlled Access to Site

3.2 Worker and Visitor Protection

3.3 Abatement Work Area Entry and Exit Procedures

3.4 Respiratory Protection

3.5 Air Monitoring; Stop Action and Clearance Levels

3.6 Initial Isolation of Abatement Work Area

3.7 Preparation of Abatement Work Area and Temporary Enclosures

3.8 Construction of Worker/Equipment Decontamination and Waste

Load-Out Enclosures

3.9 Air Circulation Inside Containment Barrier

3.10 Placement of Air Filtration System Units

3.11 Pressure Differential Isolation

3.12 Pre-Abatement Inspection, Testing, and Approval

3.13 Maintenance of Containment Barrier and Enclosures

3.14 Removal of Asbestos-Containing Materials (ACM) - General

3.15 Requirements for Specific ACM and Methods - Fireproofing/

Soundproofing on Scratch Coat or Wire Lath

3.16 Requirements for Specific ACM and Methods - Vinyl Asbestos Tile

(VAT) and Mastic

3.17 Requirements for Specific ACM and Methods - Roofing

3.18 Requirements for Specific ACM and Methods - Gypsum Wallboard

Joint Compound

3.19 Requirements for Specific ACM and Methods - Duct Insulation Mastic

3.20 Requirements for Specific ACM and Methods - Contaminated Soils

3.21 Requirements for Specific ACM and Methods - Contaminated Carpeting

3.22 Requirements for Specific ACM and Methods - Removal of

Asbestos-Containing Transite Panels.

3.23 Requirements for Specific ACM and Methods - Glove-Bag Removal

Method

3.24 Requirements for Specific ACM Methods: Negative Pressure Glove

Box Systems

3.25 Requirement for Specific ACM Methods: Water Spray Process System

3.26 Requirement for Specific ACM Methods: Mini Enclosure

3.27 Requirements for Specific ACM and Methods - Dry-Removal of

Electrical Equipment

3.28 Post Removal: Cleaning and Clearance

3.29 Post Clearance: Application of Lockdown Encapsulant To Base Material

3.30 Containment Barrier Removal

3.31 Waste Disposal

3.32 Job Close-Out

ASBESTOS ABATEMENT

PART 1 - GENERAL TC "PART 1 - GENERAL" \f C \l "1" 1.1 Introduction TC "1.1 Introduction" \f C \l "2" 1.1.1 Perform all planning, administration, execution, and cleaning necessary to safely remove asbestos-containing or contaminated materials.

1.1.2 Approval of or acceptance by the Contracting Officer’s Technical Representative (COTR) of various construction activities or methods proposed by Contractor does not constitute an assumption of liability either by the COTR or Maritime Administration(MARAD) for adequacy or adverse consequences of said activities or methods.

1.2 Description of the Abatement Work TC "1.2 Description of the Abatement Work" \f C \l "2"

1.2.1 The asbestos abatement shall also include, but not be limited to the following:

(a) Notification to regulatory agencies

(b) Regulatory permits, licenses and approvals

(c) Worker health and safety program

(d) Air monitoring

(e) Construction of temporary containment barrier/decontamination enclosures

(f) Preparation for abatement operations

(g) Removal of existing asbestos-containing material

(h) Transport and disposal of asbestos-containing material

(i) Decontamination and cleaning

(j) Application of lockdown encapsulants

(k) Removal of temporary containment barrier/decontamination enclosures

(l) Final job close-out

1.2.2 Summary Listing of Work Locations and Approximate Quantity: The Contractor shall review all contract documents and make a site visit to make his/her own determination about quantity values prior to applying for the required federal, state, or local permits from agencies having authority or jurisdiction.

1.2.3 Drawings and Other Information: Drawings of the project area(s) and the reference location(s) within the building may be provided upon request to assist in the Contractor's planning of the abatement work effort for protection of occupants and contents.

1.2.4 Other Work Not Included: Concurrently with this contract, the MARAD reserves the right to collect and analyze samples or retain an independent testing laboratory to provide supplemental sampling services. These services will in no way relieve the Contractor from compliance liability or from providing the testing required by these specifications or any other requirements of other agencies with jurisdiction authority.

1.3 Definitions TC "1.3 Definitions" \f C \l "2" 1.3.1 Abatement: Procedures to control or eliminate fiber release from asbestos-containing building materials, to include encapsulation, enclosure and removal.

1.3.2 Abatement Work Area (regulated area): An area established by the employer to demarcate areas where Class I, II, III and IV asbestos work is conducted, and any adjoining area where debris and waste from such asbestos work accumulate; and a work area within which airborne concentrations of asbestos, exceed or there is a reasonable possibility they may exceed the permissible exposure limit.

1.3.3 Airlock: A system of enclosures within the containment area consisting of two (2) doorways, curtained with polyethylene sheeting, at least 1 meter apart.

1.3.4 Air Filtration Units: A local exhaust unit, utilizing high-efficiency particulate air (HEPA) filtration and capable of maintaining a minimum negative pressure differential of 0.05 mm of water within the containment barrier with respect to that of the environment surrounding the containment barrier. The unit also cleans recirculated air or generates a constant air flow from adjacent areas into the abatement work area through the decontamination enclosure.

1.3.5 Air Monitoring: The process of measuring the fiber content of a specific volume of air during a stated period of time.

1.3.6 Air Pressure Monitoring: The process of measuring the air pressure differential between the containment barrier and the surrounding area using a micromanometer unit.

1.3.7 Amended Water: Water to which a surfactant (wetting agent) has been added to increase the ability of the liquid to penetrate asbestos containing materials (ACM).

1.3.8 ANSI: American National Standards Institute.

1.3.9 ASTM: American Society for Testing and Materials.

1.3.10 Asbestos: Asbestiform varieties of chrysotile, amosite, crocidolite, tremolite, anthophyllite, and actinolite.

1.3.11 Asbestos-Containing Material (ACM): Any material containing more than 1% asbestos by volume of any type or mixture of types.

1.3.12 Authorized Person: Any person authorized by the MARAD and required by work duties to be present in a regulated area.

1.3.13 Caulking: High-grade rubber base caulk for masonry and/or for other materials to be used or existing, as appropriate.

1.3.14. Class I Asbestos Work: Activities involving the removal of thermal systems insulation (TSI) and surfacing ACM and presumed asbestos containing materials (PACM).

1.3.15. Class II Asbestos Work: Activities involving the removal of ACM which is not TSI or surfacing material. This includes, but is not limited to, the removal of asbestos-containing wallboard, floor tile and sheeting, roofing and siding shingles, and construction mastics.

1.3.16. Class III Asbestos Work: Repair and maintenance operations, where ACM, including TSI and surfacing ACM and PACM, is likely to be disturbed.

1.3.17. Class IV Asbestos Work: Maintenance and custodial activities during which employees contact but do not disturb ACM or PACM and activities to clean up dust, waste and debris resulting from Class I, II and III activities.

1.3.18 Clean Room: An uncontaminated area or room which is part of the abatement worker/equipment decontamination enclosure, with provisions for storage of workers' or visitors' street clothing, protective equipment and uncontaminated materials and equipment. It may be used for changing clothes.

1.3.19 Competent Person: In addition to the definition in 29 CFR 1926.32 (f), one who is capable of identifying existing asbestos hazards in the workplace and selecting the appropriate control strategy for asbestos exposure, who has the authority to take prompt corrective measures to eliminate them, as specified in 29 CFR 1926.32 (f). In addition, the competent person shall have successfully completed training for Class I, Class II, Class III, and Class IV projects meeting the criteria set forth in the EPA Model Accreditation Plan (40 CFR 763) for project designer or supervisor, and operations and maintenance training.

1.3.20 Containment Barrier: A temporary enclosure constructed with fire-retardant plastic sheeting, suitable framing, tape (as defined in 1.3.52) and other adhesives within the abatement work area. This barrier serves to confine the asbestos abatement and decontamination work, and to contain the release of asbestos containing dust and debris through the action of pressure differential ventilation and air filtration systems. The only entrance is via the abatement worker/equipment decontamination enclosure.

1.3.21 COTR (Contracting Officer’s Technical Representative): An individual representing MARAD as the technical advisor to MARAD’s Contracting Officer. This individual may be an employee of MARAD or consultant.

1.3.22 Critical Barrier: Those portions of the containment barrier which represent the minimum structural components necessary to maintain the asbestos removal area in airtight isolation from the surrounding areas. Critical barriers shall be placed at floors, windows, ventilation louvers and other openings as necessary to achieve abatement work area isolation before putting up the double-layer plastic sheeting containment enclosure within which abatement work is performed. If a temporary plastic sheeting/stud wall must be erected, it shall be treated as a critical barrier. The double-layer plastic sheeting containment enclosure shall then be erected on that wall. Wrappings on lights, control boxes, etc., do not constitute part of the critical barrier.

1.3.23 Curtained Doorway: A minimum 2-flap passageway to allow access or egress from one room to another while permitting minimal air movement between the rooms of the decontamination enclosure system. It is constructed by placing 2-3 overlapping sheets of plastic sheeting at least three feet wide over an existing or temporarily framed doorway. The sheets shall be weighted at the bottom so that they close quickly after being released.

1.3.24 Decontamination Enclosure: A series of connected rooms with curtained doorways between each room, for the decontamination of the abatement workers and equipment/materials. A decontamination enclosure contains a minimum of three (3) separate rooms (typically with airlocks located between the rooms) consisting of an equipment room, shower room, and clean room. The system is constructed of an air-tight, impermeable, temporary barrier. Framing for enclosure shall be metal or fire retardant pressure impregnated wood.

1.3.25 Disposal Bag: A properly labeled minimum 0.15 mm thick, leak-tight plastic bag used for transporting asbestos waste from the abatement work area to an EPA-approved disposal site for ACM waste.

1.3.26 Disturbance: Contact which releases fibers from ACM or presumed asbestos-containing material (PACM) or debris containing ACM or PACM. This term includes activities that disrupt the matrix of ACM or PACM, render ACM or PACM friable, or generate visible debris. Disturbance includes cutting away small amounts of ACM and PACM, no greater than the amount which can be contained in one standard sized glove bag (as defined in 1.3.29) or waste bag in order to access a building component. In no event shall the amount of ACM or PACM so disturbed exceed that which can be contained in one glove bag or waste bag which shall not exceed 1.52 m in length and width.

1.3.27 Encapsulant: A material applied after the removal of ACM or to the ACM-edges of partially abated substrates which surrounds or embeds residual asbestos fibers in an adhesive matrix to prevent their release into the atmosphere. Encapsulation for purpose of final lockdown is not to be accomplished until after the project has passed final air clearance tests and the COTR has authorized removal of the containment.

1.3.28 Enclosure: Procedures necessary to completely enclose material containing asbestos behind airtight, impermeable, permanent barriers.

1.3.29 Equipment Room: A contaminated area or room which is part of the decontamination enclosure, with provisions for storage of contaminated clothing and equipment and cleaning supplies for decontamination of equipment. Airlocks are required at all entrances to the equipment room.

1.3.30 EPA: United States Environmental Protection Agency.

1.3.31 Excursion Limit: Airborne concentration of asbestos in excess of 1.0 fiber per cubic centimeter of air (1 f/cc), as averaged over a sampling period of thirty minutes.

1.3.32 Fiber: A particulate form of asbestos, 5 micrometers or longer, with a length-to-width ratio of at least 3 to 1.

1.3.33 Fixed Object: A unit of equipment or furniture in the abatement work area which cannot be removed from the abatement work area.

1.3.34 Glove Bag: A pouch, typically constructed of a minimum 0.15 mm thick, 1.5 m x 1.5 m (maximum), transparent polyethylene or polyvinylchloride plastic, with inward projecting sleeve gloves to abate ACM in a sealed micro-environment with designated inlets for amended water and sealant application, and a HEPA filtered vacuum unit attachment. The pouch has capacity for tool storage and to hold removed ACM.

1.3.35 GFCI (Ground Fault Circuit Interrupter): A type of ground fault protection in areas where personnel are at high risk of receiving electrical shocks (for example, in damp locations); makes use of a device designed to trip at a ground current in the milliampere range, i.e., very much below currents that are normally harmful.

1.3.36 HEPA Filter: A High Efficiency Particulate Air (HEPA) filter capable of trapping and retaining 99.97% of all mono-dispersed particles 0.3 micrometer in diameter or larger.

1.3.37 HEPA-Filtered Vacuum Cleaner: HEPA-filtered vacuuming equipment with a filter system capable of collecting and retaining asbestos fibers.

1.3.38 Holding Area: A chamber between the washroom and uncontaminated area in the equipment decontamination enclosure system.

1.3.39 Impermeable Waste-Disposal Containers: Suitable to receive and retain any asbestos-containing or contaminated material until disposal at an approved site. The containers shall be labeled in accordance with OSHA Regulation 29 CFR 1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-tight.

1.3.40 Lockdown: The process of applying encapsulant as a finishing coat to abated surfaces after project has successfully passed final air clearance tests and the COTR has authorized removal of containment.

1.3.41 Movable Object: A unit of equipment or furniture in the abatement work area which can be removed from the abatement work area.

1.3.42 MSHA: Mine Safety and Health Administration:

1.3.43 Negative Exposure Assessment (NEA): A demonstration by the contractor, which complies with the criteria in OSHA 29 CFR 1926.1101(f)(2)(iii), that employee exposures during an operation are expected to be consistently below the permissible exposure limits (PELs). Such assessment is to be used to justify level of respiratory protection to be used on the job.

1.3.44 NESHAPS: National Emissions Standard for Hazardous Air Pollutants.

1.3.45 N.E.C.: National Electrical Code.

1.3.46 NIOSH: National Institute for Occupational Safety and Health.

1.3.47 OSHA: Occupational Safety and Health Administration.

1.3.48 PACM: Presumed Asbestos-Containing Material, meaning thermal system insulation and surfacing material found in buildings constructed no later than 1980.

1.3.49 PEL: Permissible Exposure Limit. An occupational limit of exposure to a chemical substance or physical agent.

1.3.50 Personal Monitoring: Sampling of asbestos fiber concentrations within the breathing zone of an employee. Breathing zone is defined as a radius of 150 mm to 250 mm around the employee's head.

1.3.51 Personal Protective Equipment: Equipment which may consist of coveralls, shoes, gloves, helmet, goggles, and respirator used for protection against asbestos exposure.

1.3.52 Plastic Sheeting: Fire retardant Polyethylene sheet material of specified thickness used for protection of walls, floors, etc., and critical barriers in the abatement work area.

1.3.53 Protection Factor: The ratio of the ambient concentration of an airborne substance to the concentration of the substance inside the respirator at the breathing zone of the wearer. The protection factor is a measure of the degree of protection provided by a respirator to the wearer.

1.3.54 Respirator: A device designed to protect the wearer from the inhalation of harmful atmospheres and approved by NIOSH or MSHA for a specific category of use.

1.3.55 MARAD IH – Maritime Administration’s Industrial Hygienist: An individual serving as the Maritime Administration’s hygienist. This individual may be an employee or consultant.

1.3.56 Surfactant: A chemical wetting agent added to water to decrease surface tension and improve material penetration.

1.3.57 Tape: Glass fiber or other tape capable of sealing joints of adjacent sheets of plastic (0.15 mm polyethylene) and for attachment of plastic sheets to finished or unfinished surfaces of dissimilar materials under both dry and wet conditions, including use of amended water. Minimum tape width shall be 51 mm.

1.3.58 Warning Labels and Signs: As required by OSHA regulations 29 CFR 1910.1001 and 1926.58.

1.3.59 Waste Water Filters: Discharged liquids shall pass through a primary filter and the output shall be particles 20 microns or smaller. The secondary filter shall have output particles 5 microns or smaller.

1.3.60 Wet Cleaning: The process of eliminating asbestos contamination from building surfaces and objects by using cloths, mops, or other cleaning tools which have been dampened with amended water.

1.4 Regulations and References TC "1.4 Regulations and References" \f C \l "2" 1.4.1 Regulations: Contractor shall comply with the most current edition of all federal, state, county, and city codes and ordinances as they apply to the location(s) in which the work is performed. Make available for review at the site one copy of all applicable federal, state, county and city regulations governing the abatement work, including but not limited to:

1.4.1.1

Occupational Safety and Health Administration (OSHA), U.S. Department of Labor

(a)

29 CFR 1910 (General Industry) and 29 CFR 1926 (Construction) Occupational Safety and Health Standards

(b)

29 CFR 1910.1001 and 29 CFR 1926.1101 Asbestos

(c)

29 CFR 1910.134 Respiratory Protection (d)

29 CFR 1910.1200 Hazard Communication

1.4.1.2

U. S. Department of Transportation

49 CFR 171 Subchapter C, Hazardous Materials Regulations

(b)

49 CFR 172 Subchapter C, Shipping Container Specifications

1.4.1.3 U.S. Environmental Protection Agency (a) 40 CFR 763, Toxic Substances Control Act; particularly Subpart E, Asbestos Containing Materials in Schools

(b) 40 CFR 61, Sub-parts A and M, National Emission Standard for Hazardous Air Pollutants (NESHAPS)

1.4.1.4

District of Columbia Law Title 20 DCMR Section 800. District of Columbia Department of Health.

1.4.1.5

New York City Department of Environmental Protection.

1.4.1.6

New York State Department of Health; New York State Department of Environmental Conservation; New York State Department of Labor.

1.4.1.7

Virginia Department of Labor and Industry; Virginia Department of Professional and Occupational Regulation; Virginia Department of Environmental Quality.

1.4.1.8

Maryland Department of the Environment; Maryland Occupational Safety and Health.

1.4.1.9

Arizona Department of Environmental Quality.

1.4.1.10 Hawaii Department of Health.

1.4.1.11 Florida Department of Environmental Protection.

1.4.1.12 Massachusetts Department of Environmental Protection.

1.4.1.13 American National Standards Institute (ANSI), 1430 Broadway, New York, New York 10018. Telephone (212)354-3300

(a)

ANSI Publication Z88.2 Practices for Respiratory Protection

1.4.1.14

American Society for Testing and Materials (ASTM), 1916 Race Street, Philadelphia, PA 19103. Telephone (215) 299-5400

(a)

ASTM Standard P-189 Specification for Encapsulants for Friable Asbestos Containing Building Materials Proposal

1.4.1.15

Compressed Gas Association, Inc. New York. Pamphlet G-7 "Compressed Air for Human Respiration", Specification G-7.1 Commodity Specification for Air"

1.4.1.16

Canadian Standard Association (CSA), Rexdal, Ontario, Standard Z180.1, "Compressed Breathing Air".

1.5 Submittals TC "1.5 Submittals" \f C \l "2" 1.5.1 Reference the primary statement of work , for additional requirements.(If any exist.)

1.5.2 Contractor's Work Plan: The Contractor shall submit a Contractor's Work Plan for asbestos abatement work within 15 calendar days after contract award to the COTR for approval. Approval of the Plan is required prior to beginning abatement work. The Plan shall be on 220 mm x 280 mm paper in a binder indexed by the subjects listed below(as applicable for the work being performed). Detail the procedures, instructions, and reports used to assure compliance with the contract documents.

1.5.2.1

Barchart Schedule: Provide barchart scheduling of the abatement work by daily and/or weekly increments for each abatement work area and individual decontamination enclosure system. The time line is to include all work, both on and off the job site, for the entire contract period.

1.5.2.2

Notices: The contractor shall notify federal, state, and local regulatory agencies in writing immediately upon contract award and a minimum of 10 days in advance of any asbestos related work. Notifications shall be made by the Contractor as required by USEPA National Emission Standards for Hazardous Air Pollutants (NESHAPS) Asbestos Regulations (40 CFR 61, Subpart M)). Submit copies of notifications and documentation to the COTR. If a project consists of multi-phases, with distinct start and stop dates, these shall be declared on the EPA Notice or individual notices shall be filed for each phase.

1.5.2.3

Permits and Licenses: Maintain current licenses and obtain applicable permits as required by federal and applicable state or local jurisdictions for the removal, transporting, disposal or other regulated activity relative to the abatement work of this contract. Submit copies of all state and local licenses and permits necessary to carry out the abatement work of this contract.

All asbestos containing waste is to be transported by an entity maintaining a current "Industrial waste hauler permit" specifically for asbestos-containing materials, as required for transporting of waste asbestos-containing materials to a disposal site.

(b) Notices of Violations: Submit copies of all Notices of Violations issued to the contractor and its sub-contractors within the last three (3) years by federal, state, and local regulatory agencies.

1.5.2.4

Sequence of Work: Narrative description of the proposed sequencing of asbestos work and breakdown of abatement work areas requiring separate or individual decontamination enclosures. Include how enclosure systems will be erected and dismantled. Include how re-useable equipment will be cleaned for re-use before relocation or removal from the site. Include how waste disposal containers will be cleaned and removed from the abatement work area.

1.5.2.5

Abatement Work Area Layout Sketch: Layout sketch of decontamination enclosure systems and abatement work area. Describe assembly of construction, materials to be used and location of notices to be posted on the job site. Indicate which areas will be sealed off (and by what means). Show locations of facilities and equipment such as showers, lockers, storage, etc. Show locations of all filtration devices to be used, their exhaust, and calculations to determine the number of these devices needed to provide the minimum 4 air changes per hour in the abatement work area. These requirements shall be coordinated with the COTR and facility representative

1.5.2.6

Isolation of Abatement Work Areas: Methods to isolate/restrict access to abatement work areas. Include how access will be controlled, how building HVAC ventilation systems will be isolated from abatement area. Include how security and fire systems will be maintained within the containment. Include plans for electrical lock-out and dedicated electrical systems. These requirements shall be coordinated with the COTR and facility representatives.

1.5.2.7

Transportation and Disposal: Details of hauling equipment, materials and contaminated debris from inside the building. Submit written identification of licensed hauler and landfill location.

1.5.2.8

Personnel Organization and Responsibilities: The Contractor shall provide a list of all project personnel, both on-site and in the offices, and a statement of their responsibilities and authority for work on this project.

1.5.2.9

Personal Protective Equipment: Details of personal protective equipment and use, storage and maintenance at job site.

1.5.2.10

Posted Notices and Warning Signs: Submit copies of notices to be posted at the job site, as required by EPA and OSHA regulation for asbestos abatement activities.

1.5.2.11

Materials and Equipment Product Data: Submit manufacturer's literature and written information for all materials and equipment, including NFPA test report of flame resistant materials, and material safety data sheets for all chemical-content supplies. Contractor shall not change materials or equipment without approval of a new submittal to the COTR.

1.5.2.12

Contractor Monitoring Services: Before start of asbestos work, submit to the COTR the name of the contractor's industrial hygiene consultant and analytical laboratory for air monitoring.

1.5.2.13

Superintendent/Competent Person: Before start of asbestos work, submit to the COTR the name of job site supervisor who must meet the following requirements as a minimum. Furnish documentation that the General Superintendent:

(a) has a minimum of five (5) years on-the-job experience as a supervisor of asbestos abatement projects (b) is a competent per Section 1.3.15 of this document.

(c) is certified as an Asbestos Abatement Supervisor in accordance with 40 CFR Part 763.

(d) is fluent in the English language and all other primary languages spoken by the abatement work crew.

1.5.2.14

Workers' Specialized Training: Submit training course descriptions, locations, and dates. Submit to the COTR a written affidavit before start of asbestos removal as proof that all employees have had instruction on the hazards of asbestos exposure; and on all aspects of work procedures and personal protection and area protective measures as required and/or recommended by OSHA and EPA and other applicable guide documents. The affidavit shall include course name, designation, installation, place, date taken, and student names.

(a)

Training shall be in accordance with 29 CFR 1926.1101.

(b)

Course certification shall be in accordance with EPA as required by 40 CFR 763.

(c)

Workers should have a minimum of one (1) year experience as an asbestos worker.

1.5.2.15

Respiratory Program: Submit a written respiratory program as defined in OSHA 1926.1101 and in these specifications. Submit type of NIOSH/MSHA certified respiratory equipment intended for each operation required by this project. Selection criteria must meet 29 CFR 1926.1101 (h) (2). When a Type "C" supplied positive pressure air respiratory system is required by the abatement work, submit drawing showing assembly of components into a complete supplied air respiratory system. Include diagram showing location of compressor, filter banks, backup air supply tanks, hose line connections in abatement work area(s), routing of air lines to abatement work area(s) from compressor.

1.5.2.16

Negative exposure assessment data submitted to justify respiratory selection must be less than 12 months old and closely resemble the current project following criteria set forth in 29 CFR 1926.1101 (f) (2) (iii).

1.5.2.17

Emergency Preparedness: Submit an emergency plan to COTR for approval. The emergency plan shall address responses to fire, accident, power failure, pressure differential system failure, supplied air system failure, or any other event that may requiremodification or abridgement of decontamination or abatement work area isolation procedures. Show exit routes from the work locations of the nearest manual pull stations, telephone number of the Massachuetes Maritime Acadamy MMA security office, name of the designated employee responsible for fire protection, fire hazards inherent to the project and measures taken for prevention. All employees shall be familiar with the emergency plan and have initialed the plan after reading it, know how to activate the fire alarm, and trained in the use of portable fire extinguishers. One on-site employee shall be designated as responsible for fire protection. The plan shall be available at the job site in all primary languages of the abatement work crew. In addition, the following emergency information shall be posted at all entrances to the abatement work area:

(a)

Exit route map

(b)

Phone number of Massachuetes Maritime Acadamy (MMA) security office

1.6 Daily Reports TC "1.6 Daily Reports" \f C \l "2" 1.6.1 The Contractor shall correspond with the COTR for all matters related to this construction project, unless otherwise directed.

1.6.2 All correspondence with MARAD shall be in the English language, signed and dated by the Contractor.

1.6.3 Reference General Conditions (Construction Contract Clauses) for Supplementary Conditions for the Contract.

1.6.4 The Contractor shall maintain daily logs and reports of job-site activities and personnel exposure monitoring at the site and shall provide copies to the COTR for inspection upon request.

1.6.5 The Contractor shall maintain daily reports using MARAD’s CONTRACTOR DAILY CONSTRUCTION REPORT. Reports shall be numbered consecutively and all sections shall be completed or noted as ‘not applicable.’ Each day’s report shall contain detailed remarks including but not limited to progress on the job, problems discovered, and discussions MARAD’s COTR. Reports shall be submitted to the COTR each day for the previous work day.. Copies shall be maintained at the jobsite and made available to the COTR upon request.

1.6.6 Reporting Unusual Events: When an event of unusual and significant nature occurs at site (examples: failure of pressure differential system, rupture of temporary enclosures, equipment or power failure, high airborne fiber reading), prepare and submit a special report listing chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information.

1.6.7 Accident Reporting: Report all accidents to Massachuetes Maritime Acadamy (MMA) Security Office first, then to the COTR. Prepare reports of significant accidents, at site and anywhere else work is in progress. Record and document data and actions; comply with industry standards. For this purpose, a significant accident is defined to include events where personal injury is sustained, property loss of substance is sustained, or where the event posed a significant threat of loss or personal injury. Report shall be submitted to the COTR for review and forwarding as appropriate.

1.6.8 Waste Manifest-Asbestos: At completion of hauling and disposal of each load, submit a copy of waste manifest, chain of custody form, and landfill receipt to the COTR. Waste manifest to be submitted shall be signed by the contractor, waste transporter, and the disposal facility. A copy of all manifests will be included in the post-job submittal.

1.6.9 Waste Manifest-Hazardous Waste: Any hazardous waste generated as a result of asbestos abatement activities will be disposed of by a Certified Hazardous Waste Disposal Contractor. A copy of the Hazardous Waste Manifest generated by this disposal is to be submitted to the COTR, for review and forwarding as appropriate. A copy of all manifests will be included in the post-job submittal.

1.7 Product Handling TC "1.7 Product Handling" \f C \l "2" 1.7.1 Deliver all materials in the original packages, containers, or bundles bearing the name of the manufacturer and the brand name.

1.7.2 Store all materials subject to damage off the ground, away from wet or damp surfaces, and under cover sufficient to prevent damage or contamination.

1.7.3 Remove from the premises all damaged or deteriorated materials. Dispose of materials that become contaminated with asbestos in accordance with applicable regulatory standards and these specifications.

PART 2 - PRODUCTS TC "PART 2 - PRODUCTS" \f C \l "1" 2.1 Materials TC "2.1 Materials" \f C \l "2" 2.1.1 Caulking: High-grade rubber base caulk for masonry and/or for other materials.

2.1.2 Encapsulant: Product shall be rated as acceptable for use intended when field tested in accordance with ASTM Proposed Specification P-189 “Specification for Encapsulants for Friable Asbestos Containing Building Materials". Use only materials that have a flame spread index of 25 or less when dry, when tested in accordance with ASTM E-84.

2.1.3 Glove-Bag: 0.15 mm thick, 1500 mm x 1500 mm, transparent polyethylene or polyvinylchloride plastic with long sleeve gloves, designated inlets for HEPA vacuum attachment, and storage pouch.

2.1.4 Impermeable Waste-Disposal Containers: Suitable to receive and retain any asbestos-containing or contaminated material until disposal at an approved site. The containers shall be labeled in accordance with OSHA Regulation 29 CFR 1910.1001 and 29 CFR 1926.1101. Containers must be both water-tight and air-tight.

2.1.5 Plastic Sheeting: Product Standard PS 17-69 and OSHA Regulation 29 CFR 1926.1101; Polyethylene plastic sheeting material 0.15 mm thickness for covering floors and walls, providing air locks, and sealing doors and windows; supply in appropriate widths to minimize seams. Must be flame-resistant material and must meet test criteria in NFPA 701. Reinforced sheeting is required for applications subject to wear and tear.

2.1.6 Surfactant (Wetting Agent): 50% polyoxyethylene ester and 50% polyoxyethylene ether, or approved equal, shall be mixed with water to provide a concentration of 2 ml surfactant to 1 liters of water, or manufacturer's recommended concentration.

2.1.7 Tape: Glass fiber or other tape capable of sealing joints of adjacent sheets of plastic sheeting and for attachment of plastic sheets to finished or unfinished surfaces of dissimilar materials under both dry and wet conditions, including use of amended water. Minimum tape width shall be 50 mm.

2.1.8 Warning Labels and Signs: As required by OSHA regulations 29 CFR 1910.1001 and 1926.58.

2.1.9 Waste Water Filters: Discharged liquids shall pass through a primary filter and the output shall be particles 20 microns or smaller. The secondary filter shall have output particles 5 microns or smaller.

2.2 Equipment TC "2.2 Equipment" \f C \l "2" 2.2.1 Air Filtration Units: Shall be factory-sealed and equipped with HEPA filters(final), pre-filters, instrumentation to monitor pressure differential, and safety and warning devices.

2.2.1.1

Provide units with electrical components approved by the National Electrical Manufacturers Association (NEMA) and Underwriter's Laboratories (UL).

2.2.1.2

Access to the units for replacement of all air filters shall be from intake end. Provide units with pre-filters and intermediate filters installed either on or in the intake grid of the unit and held in place with special housings or clamps. The filter media shall be completely sealed on all edges with a structurally rigid frame with a continuous rubber gasket.

2.2.1.3

HEPA Filters: Provide units equipped with HEPA filters. Filters shall be individually tested and certified by the manufacturer.

2.2.1.4

Pre-filters: Provide a two-stage pre-filtration to extend the life of the primary HEPA filter. The first-stage pre-filter is a low-efficiency type effective for particles 100 micrometers and larger. The second-stage (or intermediate) filter has a medium efficiency effective for particles down to 5 micrometers.

2.2.1.5

Instrumentation: Provide units equipped with a magnehelic gauge or manometer to measure the pressure drop across filters and to indicate when filters have become loaded and need to be changed. A table indicating the usable air-handling capacity for various static pressure readings on the magnehelic gauge affixed near the gauge for reference, or the magnehelic reading indicating at what point the filters should be changed, noting cubic feet per minute (CFM) air delivery at that point. Provide an elapsed time meter to show the total accumulated hours of operation.

2.2.1.6

Safety and Warning Devices: Provide units with the following safety and warning devices:

Warning lights to indicate normal operation, too high a pressure drop across the filters (i.e., filter overloading), and too low of a pressure drop (i.e., rupture in HEPA filter or obstructed discharge)

(b)

GFCIs.

(c)

Audible alarm if unit shuts down due to operation of safety systems.

(d)

Electrical overload protection sized for the equipment. The motor, fan, fan housing, and cabinet are to be grounded.

2.2.2 Respirators and Respirator Systems 2.2.2.1

Product Data: Must possess NIOSH and MSHA approval for each component in an assembly and/or for entire assembly.

PART 3 - EXECUTION TC "PART 3 - EXECUTION" \f C \l "1" 3.1 Controlled Access to Site TC "3.1 Controlled Access to Site" \f C \l "2" 3.1.1 Access to the abatement work area shall be restricted to contractor's workers and authorized visitors as defined in these specifications.

3.1.2 Authorized visitors shall have access to the work site at all times following notification to COTR. Contractor shall supply protective clothing and equipment for visitors as necessary, except for respirators which are to be provided by the visitor in accordance with Section 3.4 of this document.

3.1.3 Contractor shall prominently post signs at all potential entry points to the abatement work area which clearly state: "Restricted Area Under Construction-Admittance by Special Permission Only - Protective Clothing Required Beyond This Point". Immediately inside entry point and outside critical barriers post a warning sign meeting specifications of OSHA 29 CFR 1910 and 1926. Suggested format is a sign of minimum size 508 mm by 356 mm displaying the following legend:

DANGER

ASBESTOS

CANCER AND LUNG DISEASE HAZARD

AUTHORIZED PERSONNEL ONLY

RESPIRATORS AND PROTECTIVE CLOTHING ARE

REQUIRED IN THIS AREA

3.1.4 All workers and authorized visitors shall enter the abatement work area only through the abatement worker/equipment decontamination enclosure, in accordance with Section 3.3 of this document.

3.1.5 All workers and authorized visitors, before entering the abatement work area, shall read and be familiar with all posted regulations, personal protection requirements, and emergency procedures and exit routes.

3.1.6 Contractor shall maintain a daily job site personnel log listing names and social security numbers of individuals who entered the abatement work area, and the times of entering and leaving the area.

3.2 Worker and Visitor Protection TC "3.2 Worker and Visitor Protection" \f C \l "2" 3.2.1 No eating, drinking, smoking, or chewing gum is permitted within the abatement work area. The CONTRACTOR shall designate a "break area" where these activities, except for smoking, are permitted. Smoking is prohibited at Massacheutes Maritime Acadamy facilities and onboard the vessel.

3.2.2 Workers and Visitors shall be fully protected with respirators and protective clothing during any work which may disturb asbestos-containing materials and result in fiber release. Full protection is not required during pre-abatement inspections of the containment, while work is not being conducted.

3.2.3 Protective Clothing and Equipment: Provide workers and visitors with sufficient sets of protective full body clothing, to include full body coveralls with hood, boots (for workers) and footwear coverings (for workers and visitors), and gloves. Provide eye protection and hard hats as required by applicable safety regulations. Contaminated non-disposal clothing and footwear shall be left in the equipment room until the end of the asbestos abatement work, at which time such items shall be disposed of as asbestos waste, or shall be thoroughly cleaned of all asbestos or asbestos-containing material. Contractor shall have at least three (3) sets of disposable protective full body clothing for COTR and authorized visitors for each work day. Provide storage facilities for visitors and workers for removed street clothing in the clean room.

3.2.3.1

Boots: Provide workers non-skid type work boots with protective shields as required by OSHA. Paint uppers of boots with red waterproof enamel paint as a permanent marking that the boots have been exposed to ACM abatement work areas. These boots are to be handled as asbestos-contaminated materials.

3.2.3.2

Hard Hats: Provide hard hats that meet ANSI Z89.1 for use where work is overhead, scaffolding is being used, or as otherwise required by OSHA. Label hats with same warning labels as required for ACM disposal bags.

3.2.3.3

Goggles: Provide goggles that meet ANSI Z87.1 as required by OSHA.

3.2.3.4

Gloves: Provide disposable work gloves for use in the abatement work area.

3.2.3.5

Coveralls with Hood: Provide disposable coveralls with hoods for use in the abatement work area.

3.2.3.6

Respirators: Provide workers with personally issued and marked respirator equipment approved by NIOSH/MSHA and, in accordance with these specifications, suitable for the asbestos exposure level in the abatement work area. Where respirators with disposable filters are employed, provide sufficient filters for replacement as necessary by the abatement worker, or as required by the applicable regulation. Authorized visitors must provide their own respirators, with fresh filters or cartridges as necessary, to enter the abatement work area. These are minimum requirements. Section 3.4 of this document is to be consulted for more detail.

3.3 Abatement Work Area Entry and Exit Procedures TC "3.3 Abatement Work Area Entry and Exit Procedures" \f C \l "2" 3.3.1.

Each time the abatement work area is entered remove all street clothes in the Clean Room of the Decontamination Enclosure and put on new disposable coveralls, new head cover, and a clean respirator. Proceed through shower room to equipment room and put on work boots.

3.3.2 Each time the abatement work area is exited, the following procedures shall be followed:

3.3.2.1

Before leaving the regulated area, employees and authorized visitors shall remove all gross contamination and debris from their protective clothing.

3.3.2.2.

Personnel exiting the regulated area shall remove their protective clothing and equipment (except respirators) in the equipment room and deposit the clothing in labeled impermeable bags or containers.

3.3.2.3

Personnel shall remove their respirators in the shower room, washing and rinsing them.

3.3.2.4

Personnel shall shower thoroughly before entering the clean room.

3.3.2.5

After showering, employees shall enter the clean room before changing into street clothes.

3.4 Respiratory Protection TC "3.4 Respiratory Protection" \f C \l "2" 3.4.1 Contractor is hereby advised that asbestos has been determined by the U.S. Government to be a CANCER-CAUSING AGENT. Provide workers with respirators [which, as a minimum, meet the requirements of OSHA 29 CFR 1926.1101] and protective clothing during all phases of the abatement work and until final air tests are accepted by COTR.

3.4.2 The Contractor shall select respirators from among those jointly approved as being acceptable for protection by the MSHA and the NIOSH under the provisions of 30 CFR Part 11.

3.4.3 The Contractor shall select and provide respirators, at no cost to the employee and shall ensure that the employee uses the respirator provided.

3.4.4 Instruct and train each worker involved in asbestos abatement or maintenance and repair of asbestos-containing materials in proper respiratory use and require that each worker always wear in the abatement work area a respirator, properly fitted on the face. The respirator shall be worn from the start of any operation which may cause airborne asbestos fibers until the abatement work area is completely decontaminated.

3.4.5 Allow an individual to use only those respirators for which training and fit-testing have been provided. Require that each time an air-purifying respirator is put on it be checked for fit with a positive and negative pressure fit test in accordance with the manufacturer's instructions or ANSI Z88.2.

3.4.6 For all jobs that involve the removal of thermal system insulation (TSI) or surfacing materials (OSHA definition of Class I work) the employer shall provide respirator protection in accordance with 29 CFR 1926.1101 (h) Table 1 - Respiratory Protection for Asbestos Fibers. This level of respiratory protection shall be maintained until the employer can produce a negative exposure assessment.

3.4.7 For all other abatement work, use respiratory protection appropriate for the fiber level encountered in the abatement work area or as required for other toxic or oxygen-deficient situations encountered. The level of respiratory protection which supplies an airborne fiber level inside the respirator, at the breathing zone of the wearer, at or below the permissible exposure limit (PEL) is the minimum level of protection allowed. (Table

1, Respiratory Protection for Asbestos Fibers, 29 CFR 1926.1101) Do not use single-use, disposable, or quarter-face respirators.

3.4.8 Authorized visitors are responsible for providing their own respirator and replacement filters and cartridges, with the exception of Type C which shall be provided by Contractor, and for having been previously and properly trained fit-tested, for the respirator used.

3.4.9 For use with air-purifying respirators, provide, at a minimum, HEPA type filters certified by NIOSH and MSHA for protection against asbestos fibers. In addition, a chemical cartridge may be added, if required for protection against chemicals used on this job.

3.4.10 For use with powered air purifying respirators, supply a sufficient quantity of HEPA filters approved for asbestos, so workers can change filters at any time that flow through the face piece decreases to the level at which the manufacturer recommends filter replacement.

3.4.11 For supplied-air respirator systems, provide equipment capable of producing air used for breathing in Type "C" supplied air respiratory systems that meets or exceeds standards set for C.G.A. Type 1, Gaseous Air, Grade D. (See 1.5.2.15) System must be certified by NIOSH/MSHA as an approved Type "C" respirator assembly operating in pressure demand mode with a positive pressure face-piece including as a minimum the following:

· Auxiliary backup system

· Escape air supply

· Backup air supply

· Warning Alarm Device

· Compressor Shut Down

· Compressor Motor (electric)

· Compressor Location (outside building)

· Air Intake

· After-Cooler

3.5 Air Monitoring; Stop Action and Clearance Levels TC "3.5 Air Monitoring; Stop Action and Clearance Levels" \f C \l "2" 3.5.1 This section describes that may be performed by MARAD. MARAD will not be performing air monitoring to meet Contractor's OSHA requirements for personal sampling or any other purpose.. The Contractor is to conduct air monitoring required by OSHA for Contractor personnel.

3.5.2 Analytical Methods: The following methods will be used by the MARAD in analyzing filters used to collect air samples. Minimum sample volumes will be 1200 liters for clearance samples.

3.5.2.1

Phase Contrast Microscopy (PCM) - will be performed using the OSHA Reference Method, Appendix A to 29 CFR 1926.1101, or NIOSH Method 7400.

3.5.2.2

Transmission Electron Microscopy (TEM) - will be performed using the analysis method set forth in the AHERA regulation 40 CFR Part 763 Appendix A, or NIOSH Method 7402, whichever is deemed more appropriate by MARAD in each case.

3.5.3 Before Start of Work: The MARAD will secure abatement work area air samples to establish a base line fiber level in each homogeneous abatement work area before start of work. All samples will be taken at the same time to ensure identical environmental conditions.

3.5.4 Daily: From start of abatement work through project decontamination, the MARAD may be taking samples on a daily basis inside and outside each abatement work area.

3.5.5 All Clearance Air Samples will be taken using aggressive sampling techniques.

3.5.6 Stop Action: If any air sample taken outside of the abatement work area exceeds 0.01 f/cc by PCM, or 70 structures per mm2 by TEM, depending on sampling method used, immediately and automatically stop all work except corrective action. PCM air samples will be re-analyzed by TEM to determine whether the high outside-of-work-area results were due to asbestos or non-asbestos fibers. The MARAD and the abatement contractor will determine the source of the high reading. The contractor will correct the condition, as appropriate.

3.5.7 Abatement Work Area Final Clearance Levels:

3.5.7.1 The MARAD standard for abatement work area final clearance in all occupied areas for removing the containment and re-occupancy is 70 structures per mm2 by TEM using the analysis method set forth in the AHERA regulation 40 CFR Part 763 Appendix A.

3.5.7.2 The MARAD standard for abatement work area final clearance in un-occupied areas, or at the case-by-case discretion of the MARAD, is less than 0.01 fibers per cubic centimeter of air using PCM methods specified in NIOSH 7400.

3.5.7.3 Final air clearance requirements of specific state and local regulations that exceed the requirements of 3.5.7.1 and 3.5.7.2 will be utilized (e.g., in the District of Columbia, at least two PCM samples per 2,500 square feet of floor are required).