Q&A_11-07-19.pdf
PDF 68 KB Posted
- Solicitation number
- 69056719B000017
About this file
This document contains questions and answers related to a federal solicitation for road rehabilitation work on Glacier National Park's Many Glacier Road. The solicitation seeks bids for repair of three simple span bridges along 12 miles of road, including minor concrete repair and waterproofing of two slab bridges and replacement of timber girders on a horse bridge. The estimated price range for the project is between $15-20 million and work must be completed by Fall 2021. The document provides clarification on issues such as trailer pad locations, topsoil pH requirements, culvert replacement timelines, asphalt testing procedures, load limits on bridges, and other technical questions from interested contractors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Opening Summary_Many Glacier_R1.pdf | ||
| Q&A_11-20-19.pdf | ||
| Q&A_11-18-19.pdf | ||
| Amendment A004.pdf | ||
| Amendment A003.pdf | ||
| glac01404_XS_Signoff.pdf | ||
| Prebid Meeting.pptx | PPTX presentation | |
| Amendment A002.pdf | ||
| Q&A_11-15-19.pdf | ||
| Amendment_A001.pdf | ||
| Q&A_11-05-19.pdf | ||
| Q&A_11-04-19.pdf | ||
| Q&A_10-31-19.pdf | ||
| IFB_Many_Glacier.pdf | ||
| Plan_Request.pdf | ||
| plans_glac01404.pdf | ||
| Physical_Data_Many_Glacier.zip | ZIP file | |
| Draft_Weed_Free_SCR_Many_Glacier.pdf | ||
| ManyGlacierMaterialSourcesResearchEfforts_(08_30_2019).pdf | ||
| PROJECT_DESCRIPTION_R1.pdf | ||
| PROJECT_DESCRIPTION.pdf | ||
| Prelim_Letter_.pdf | ||
| Pre_AD_set_glac01404_Plans_Signoff_R1.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT NPS GLAC 14(4) & MT Glacier 14(1) Rehabilitate Many Glacier Road & Many Glacier Road
# General Technical Question Answer Date
1 X
Per section 637.02, the government housing trailer pads are located at Glacier National Park Hudson’s Bay District. Could you please provide the exact location of these trailer pads?
Approximate GPS Coordinates for the trailer pads are 48°44’14.50” N, 113°25’39.33” W;
and 48°44’13.85” N, 113°25’37.78” W.
10/31/19
2 X
The required pH for furnished topsoil is between 6.0 and 8.0 per Subsection 713.01.
Since the pH for the existing topsoil on the project is between 5.5 and 5.8; can the specified pH for furnished topsoil be modified to match the existing topsoil pH, and reduce the cost of imported topsoil to be furnished?
This will be addressed under a forthcoming amendment.
11/4/19
3 X
Per Section 108.01 (c), the work at Sta: 716+46 is to be performed from March 1st to June 15th.
Section 108.01(g), indicates the culvert replacement work can not be done after the third Monday in May. Please clarify if this work be completed between the third Monday in May to June 15th?
This will be addressed under a forthcoming amendment.
11/4/19
4 X
Subsection 107.10(d)(5) says that all topsoil loads need to be tarped. If the source of topsoil is determined to be weed free and was not required to be treated, will WFLHD still require the loads to be tarped?
Yes. Comply with the requirements of Subsection 107.10(d)(5)
11/4/19
Check General or Technical
5 X
Per Section 108.01 (c), the work is to be done between March 1st and June 15th of any given year. Is it the intent of the contract to have the Contractor perform the work at this station during the high water period?
Perform work according to the requirements of Subsection 108.01(c).
11/4/19
6 X Can you please tell me the date, time and location for the pre‐bid meeting for this project?
See Pre‐bid Meeting information shown on Page A‐2c of the Notice to Bidders.
11/5/19
7 X
Will a Material Transfer Vehicle (Shuttle Buggy) be required on this project for asphalt? If so will it also be required in the parking lots and turn lanes?
A material transfer vehicle is not required for this project.
11/5/19
8 X
How will asphalt compaction testing be performed for the 1” wedge and leveling section? Testing compaction for a 1” lift is usually impossible to get accurate results.
See Subsection 403.09 and follow ASTM D 2950 as specified.
11/5/19
9 X
Section 104.05 states that loads over 21 feet long will require a pilot car with a permit and advance notice. Would this apply to belly dump loads of material entering the park? We will have hundreds of loads of material with belly dumps over 21’ long. Please clarify.
This will be addressed under a forthcoming amendment.
11/5/19
10 X
The physical data for the Akupini and Windy Creek bridges show a legal load of 36 tons for a Type 3S2 Truck. Is that the payload or the payload and the weight of the truck together?
A typical loaded Type 3S2 truck would be closer to 46 tons gross weight. If the gross weight of 36 tons is the max allowed it would increase the amount of truck loads by as much as 50%.
Please clarify the max load allowed over the bridges.
Yes, regarding the 3S2 truck, the structure load rating details shown in the bridge inspection reports is the truck with total weight and axle loads including truck and payload. This is standard legal load rating vehicle from the AASHTO Manual for Bridge Evaluation for load rating purposes. The bridge is not posted for restricted load, and is open to legal hauling. Any overload or permit vehicles will need to be evaluated for capacity.
11/5/19
11 X
Section 108.01 paragraph f limits the work at Many Glacier Hotel look road, parking lot, and horse pedestrian/bridge: and Entrance Station construction work to September 21st , 2020 to May 28th 2021. Paragraph g limits all culvert replacement work from the third Monday in September to the third Monday in May of any year.
The temperature specification for beginning asphalt paving must be at least 55 degrees F. In looking at historical temperatures it appears that the temperature may not be within asphalt paving ranges during the times specified, and if it is the allowable paving temperature window will be extremely short during the day. Can the paving low temperature specification be reduced for paving within those timeframes?
This has been an issue on other FHWA projects.
We’re not sure where you’re seeing the 55 degree F temperature specification for paving. Weather limitations for paving are shown in Subsection 401.07, and will not be changed.
11/5/19
12 X
Per the Ordinance 117 Permit, the work will not, during either its construction or during the life of the project:
‐create a public nuisance Is night time construction traffic and/or work considered a public nuisance to the local residents?
Information regarding the Ordinance 117 Permit is scheduled to be discussed at the Pre‐Bid Meeting.
11/7/19
13 X
If the adjacent landowners complain the night time construction traffic and/or work is in violation of the conditions of the Ordinance 117 Permit, what measures will WFLHD require the Contractor to take? Will the additional measures and costs be considered a change in conditions of the Contract?
Bid according to the contract. Requests for change will be evaluated after contract award.
11/7/19
14 X Can you please post the 10‐year historical weather data that WFLHD used to determine construction date parameters?
This information will not be provided. 11/7/19
15 X
Per FAR 52.236‐4, Hydrological data consisting of flow rates, water surface elevations, velocities, and hydraulic permit information may be inspected at Western Federal Lands Highway Division, Contracts Section, 610 East Fifth Street, Vancouver, Washington 98661.
Can WFLHD post the hydrological information that is pertinent to the drainages affected by the work on this project or provide a web address to access this information?
See Physical Data Files glac01404_HydraulicsReport_Final.pdf and mt‐a3700141_HydraulicsReport_Final.pdf that have been provided.
11/7/19
16 X
Per Section 108.01(e), winter shutdown is December 16th and startup is March 31st. If the Contractor is unable to perform work up to December 16th shutdown, will an extension of time be given for weather delays? If the Contractor is unable to start work on March 31st, will an extension of time be given for weather delays?
See Subsection 108.03. 11/7/19
17 X
Can WFLHD please clarify Section 104.05(a)(2)?
Will each truck or piece of equipment be required to have and escort car in front of them at all times except for specified closure periods?
When are the high traffic times?
This will be addressed under a forthcoming amendment.
11/7/19
18 X Is there a cost for the Park travel permits?
This will be addressed under a forthcoming amendment.
11/7/19
19 X
Would WFLHD allow the work on Many Glacier Hotel Loop Road, parking lot, and the horse bridge to be completed in smaller phases past the May 28th deadline?
Bid according to the contract. Work in this area cannot be performed beyond the May 28th deadline.
11/7/19
20 X At the pre‐bid meeting, will the Contractors be given the opportunity to ask questions regarding the plans and specifications?
No. Submit general information and/or technical information questions according to the Block 9 directions show on Page A‐5 of the solicitation.
11/7/19
21 X
Will the Contractor be able to limit traffic to one lane during daytime hours between the third Monday in May to the third Monday in September utilizing pilot cars and flaggers in accordance to MUTCD regulations?
Yes. 40 minute maximum cumulative delays (day) are allowed under Subsection 156.07(i)(2)(a).
22 X
Will WFLHD allow culvert replacement work to be completed from the third Monday in May to third Monday in September utilizing one lane traffic control?
No. Culvert replacement work is restricted from the third Monday in May to third Monday in September of any given year according to Subsection 108.01(g).