570-17-210.OPC.IFC.DWG.20210618Part-9of10.pdf

PDF 9 MB Posted

Attached to
Z2DA--REMODEL EMERGENCY DEPARTMENT FOR OBSERVATION BEDS | 570-17-210
Solicitation number
36C26121R0066
Issued by

View the file

Other files

File Type Posted
36C26121R0066 0005.docx DOCX document
36C26121R0066 0004.docx DOCX document
Site Visit Sign-in Sheet--12.1.2021.pdf PDF
Site Visit Sign-in Sheet--11.10.2021.pdf PDF
36C26121R0066--Responses to Pre-Proposal RFIs (1-17)--Complete--12.6.2021.pdf PDF
Specification 11 73 00-rev01-12.03.2021.pdf PDF
36C26121R0066 0003.docx DOCX document
36C26121R0066--Responses to Pre-Proposal RFIs (1-17).pdf PDF
36C26121R0066 0002.docx DOCX document
36C26121R0066--Responses to Pre-Proposal RFIs (1-10).pdf PDF
ACM Report.pdf PDF
36C26121R0066 0001.docx DOCX document
570-17-210.OPC.IFC.DWG.20210618Part-7of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-1of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-8of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-10of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-3of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-6of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-2of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-5of10.pdf PDF
570-17-210.OPC.IFC.DWG.20210618Part-4of10.pdf PDF
Factor 6 - Divisional Construction Costs.pdf PDF
REQUEST FOR INFORMATION (RFI) FORM--36C26121R0066.docx DOCX document
Factor 4 - Past Performance (Questionnaire).docx DOCX document
570-17-210.OPC.IFC.Specification.R2.20210618Part-4.pdf PDF
570-17-210.OPC.IFC.Specification.R2.20210618Part-2.pdf PDF
Factor 2 - Key Personnel Qualifications Resumes.xlsx XLSX spreadsheet
570-17-210.OPC.IFC.Specification.R2.20210618Part-3.pdf PDF
VHA_DIRECTIVE_1193_D_2021_08_13--Vaccination_Program.pdf PDF
General Decision Number CA20210018 10.08.2021.pdf PDF
Responsibility - Contractor Certification Regarding Safety and Environmental.pdf PDF
Site_Visit_MAP.pdf PDF
Factor 1 - Prime Contractor Project Experience.xlsx XLSX spreadsheet
570-17-210.OPC.IFC.Specification.R2.20210618Part-1.pdf PDF
36C26121R0066_2.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BOPC.6BOPC.5.ABOPC.5BOPC.4BOPC.3BOPC.2BOPC.1

BOPC.A

BOPC.A.1

BOPC.B

BOPC.C

BOPC.D

BOPC.E

BOPC.F

BOPC.G

EF-1

1-EF-ED

(BELOW)

12"ø EXH

14"x10" SA

24"x18" SA

B1

MH102

D1

MH102

F1

MH102

(E)26"ø EXH26"ø EXH

1-GH-41-GH-3

(E )1

"x

E X

H

36"ø EXH

NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

KEY PLAN

A B

D C

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:5

:3

A

M

MH102

MECHANICAL PLAN - ROOF LEVEL

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

GENERAL SHEET NOTES

A. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-CONSTRUCTION TAB

REPORT FOR THE EQUIPMENT AND ASSOCIATED SYSTEMS SHOWN ON THE

CONSTRUCTION DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT DRAWINGS

FROM THE OWNER. TEST AND BALANCE CONTRACTOR SHALL VISIT SITE PRIOR TO

CONSTRUCTION AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND DEVELOP

THEIR TEST AND BALANCE FORMS INCLUDING DRAWINGS SHOWING EQUIPMENT

LOCATIONS, AIR DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF THERE

ARE LOCATIONS WHERE THE DRAWINGS DO NOT REFLECT FIELD CONDITIONS, THE

TEST AND BALANCE CONTRACTOR SHALL INCLUDE THE AIRFLOW AND WATERFLOW

READINGS ON THE FORMS AND LOCATE THE EQUIPMENT AND/OR AIR DEVICE ON

THE DRAWINGS. REFER TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

B. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE UTILIZED TO

ESTABLISH NEW HVAC SYSTEM PERFORMANCE AND BALANCE DATA FOR THE

RENOVATION. DATA SHALL BE FORWARDED TO THE PROJECT ENGINEER FOR

REVIEW AND COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR NEW

WORK ASSOCIATED WITH THE FACILITY RENOVATION.

C. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

D. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION WARRANTY

REQUIREMENTS FOR ANY MODIFICATIONS TO ROOFING TO ENSURE NO VIOLATIONS

OCCUR OF THE WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED ROOFING

INSPECTOR MEETING THE REQUIREMENTS OF THE INSTALLED ROOF. ALL

WARRANTY VIOLATIONS WILL BE REQUIRED TO BE CORRECTED PRIOR TO CLOSE

OUT. ROOFS AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

E. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED

WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED

AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF

CAULKING MATERIAL.

F. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING, AND CONDUIT PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL PROVIDE

NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

G. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.

CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR

TO NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY

FROM CONSTRUCTION DOCUMENTS.

H. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT LOCATIONS WITH ALL TRADES

PRIOR TO INSTALLATION.

I. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS

BETWEEN ALL DISSIMILAR METALS.

J. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO

COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND

RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.

K. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW EXPOSED EXTERIOR PIPE

PENETRATIONS AND SEAL COMPLETELY.

L. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE MODIFYING

SUBFLOORING.

M. SEE M-501 FOR LOW PRESSURE DUCT FITTING DETAILS.

N. SEE M-501 FOR DIFFUSER AND REGISTER CONNECTION DETAILS.

O. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

P. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES AND M-802 AND M-803

FOR CONTROL SEQUENCE.

Q. PROVIDE PRECONSTRUCTION TAB READINGS OF THE EXISTING SUPPLY AIR AND

RETURN AIR SERVING THE ROOMS IN THE AREA OF WORK. REBALANCE EXISTING

SUPPLY AND RETURN AIR SYSTEMS AFTER DEMOLITION IS COMPLETE.

R. TECHNICAL COORDINATION DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING

ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT

SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL

SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN,

CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN

THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND

VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND

REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING.

1 PROVIDE NEW OUTSIDE AIR INTAKE LOUVERED PENTHOUSE, MINIMUM 3' ABOVE ROOF AND MINIMUM 25'

FROM EXHAUST AIR OUTLETS. SEE M-702 FOR SCHEDULE.

2 PROVIDE NEW GENERAL EXHAUST FAN SERVING BASEMENT FLOOR, MINIMUM 10' ABOVE ROOF AND

MINIMUM 25' FROM AIR INTAKES. SEE M-702 FOR SCHEDULE. (LOCATION OPTION #1)

3 25' MINIMUM CLEARANCE FROM NEAREST FRESH AIR INTAKE

4 PROVIDE NEW SPECIAL EXHAUST FAN SERVING NEGATIVE PRESSURE TREATMENT ROOMS ON

BASEMENT FLOOR, MINIMUM 10' ABOVE ROOF AND MINIMUM 25' FROM AIR INTAKES. SEE M-702 FOR

SCHEDULE.

5 EXISTING ROOFTOP MECHANICAL EQUIPMENT TO REMAIN, PROTECT IN-PLACE.

6 EXISTING PHOTOVOLTAIC PANEL ARRAY TO REMAIN, PROTECT IN-PLACE.

7 FUTURE ROOFTOP AIR HANDLING UNIT AND PIPING CONSTRUCTED UNDER SEPARATE RENOVATE

SPECIALTY CLINIC PROJECT.

8 PROVIDE NEW 36" DIAMETER EXHAUST DUCT AND STACK FROM NEW AHU-3 WITH OUTLET MINIMUM 10'

ABOVE ROOF LEVEL.

1/8" = 1'-0" F4

MECHANICAL PLAN - ROOF

NTS

B1

PROPOSED EXHAUST DUCT (OPC & B1 CHASE BELOW)

NTS

D1

PROPOSED ROOF LEVELTOP EXHAUST DUCT (OPC & B1 CHASE)

NTS

F1

NEW INTAKE HOOD AND EXHAUST FAN LOCATIONS

KEYNOTES

Revisions: Date:

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE RESISTANT, OR BOTH

FIRE AND SMOKE RESISTANT ARE SHOWN GRAPHICALLY ON PLANS WITH

HATCH PATTERNS.

06/18/2021

BOPC.3BOPC.2

BOPC.1

BOPC.A

BOPC.A.1

BOPC.B

BOPC.B.1

BOPC.C

BOPC.D

F4/MP100D

VAV-1-2

CAV-1-7

CAV-1-2

CAV-1-5

CAV-1-4

VAV-1-1

TRAUMA RM LARGE

B1C07

EXAM AREA

B1C04

ENTRANCE

ELEVATOR

B-19

ALCOVE,

WHEELCHAIR/

STRETCHER/ LIFT

B1D

SOCIAL WORK

OFFICE

B1C01

EXAM AREA

B1C03

VESTIBULE

VESTIBULE

LINEN CART ALCOVE

POLICE DISPATCH

B1C02

PROCEDURE RM

B1C05

CHARTING ALCOVE

WHEELCH. SCALE

CORRIDOR

B1C-1A

TRAUMA RM SMALL

B1C06

TOILET

B1C08

CORRIDOR

B1C-8

CORRIDOR

B1C-5

NURSE STATION

B1C29A

CLINICAL CHARTING

RM

B1C29

CORRIDOR

B1C-7

AOD/ CHECK-IN

B1C30

INTERVENTION

(SECLUSION) ROOM

B1C28

WAITING

B1C-1

CAV-1-6

3/4" HWS

3/4" HWR

2" HWS

2" HWR

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWS

V-53 V-54

V-40

V-39

3/4" HWR

3/4" HWS

3/4" HWS

3/4" HWR

2" HWR

2" HWS

2" HWR

2" HWS

V-49 V-50

V-52 V-51

V-48

V-47

V-46

V-45

V-41 V-42

3/4" HWS

3/4" HWR

V-38

V-37

2 3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWS

C A

V -1

-8

C A

V -1

-9

VAV-1-6

V-29 V-30

3/4" HWS

3/4" HWR

V-31

V-32

3/4" HWR

3/4" HWS

V-34 V-33

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWS

V-35

V-36

3/4" HWS

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWR

3/4" HWS

V-56 V-55

V-43

V-44

3/4" HWS

3/4" HWR

V-47

V-48

3/4" HWS

3/4" HWR

F /M

P B

C A

V -1

-1

C A

V -1

-3

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWS

NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

KEY PLAN

A

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:5

:4

A

M

MP100A

MECHANICAL PIPING PLAN - LEVEL

B - AREA A

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

1/4" = 1'-0" F1

MECHANICAL PIPING PLAN - BASEMENT - AREA A

1 CONTRACTOR SHALL INSTALL NEW HOSE AND VALVE KIT SERVING NEW TERMINAL

UNITS, REFER TO DETAILS ON SHEET M-501.

2 PROVIDE NEW ISOLATION BALL VALVES, CONTRACTOR SHALL COORDINATE FINAL

VALVE NUMBERING WITH THE VA.

3 PROVIDE NEW HOT WATER SUPPLY AND RETURN PIPING TO NEW TERMINAL UNITS,

INSULATE PIPING PER SPECIFICATION SECTION 23 00 11. COORDINATE ALL ROUTING

WITH EXISTING TRADES PRIOR TO INSTALLATION.

4 PROVIDE NEW TERMINAL UNIT LOCATED IN CEILING SPACE. COORDINATE LOCATION

WITH MANUFACTURER'S MINIMUM REQUIRED SERVICE CLEARANCE AND OTHER

TRADES. TYPICAL FOR ALL UNITS.

GENERAL SHEET NOTES

A. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-CONSTRUCTION TAB

REPORT FOR THE EQUIPMENT AND ASSOCIATED SYSTEMS SHOWN ON THE

CONSTRUCTION DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT DRAWINGS

FROM THE OWNER. TEST AND BALANCE CONTRACTOR SHALL VISIT SITE PRIOR TO

CONSTRUCTION AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND DEVELOP

THEIR TEST AND BALANCE FORMS INCLUDING DRAWINGS SHOWING EQUIPMENT

LOCATIONS, AIR DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF THERE

ARE LOCATIONS WHERE THE DRAWINGS DO NOT REFLECT FIELD CONDITIONS, THE

TEST AND BALANCE CONTRACTOR SHALL INCLUDE THE AIRFLOW AND WATERFLOW

READINGS ON THE FORMS AND LOCATE THE EQUIPMENT AND/OR AIR DEVICE ON

THE DRAWINGS. REFER TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

B. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE UTILIZED TO

ESTABLISH NEW HVAC SYSTEM PERFORMANCE AND BALANCE DATA FOR THE

RENOVATION. DATA SHALL BE FORWARDED TO THE PROJECT ENGINEER FOR

REVIEW AND COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR NEW

WORK ASSOCIATED WITH THE FACILITY RENOVATION.

C. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

D. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION WARRANTY

REQUIREMENTS FOR ANY MODIFICATIONS TO ROOFING TO ENSURE NO VIOLATIONS

OCCUR OF THE WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED ROOFING

INSPECTOR MEETING THE REQUIREMENTS OF THE INSTALLED ROOF. ALL

WARRANTY VIOLATIONS WILL BE REQUIRED TO BE CORRECTED PRIOR TO CLOSE

OUT. ROOFS AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

E. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED

WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED

AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF

CAULKING MATERIAL.

F. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING, AND CONDUIT PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL PROVIDE

NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

G. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.

CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR

TO NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY

FROM CONSTRUCTION DOCUMENTS.

H. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT LOCATIONS WITH ALL TRADES

PRIOR TO INSTALLATION.

I. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS

BETWEEN ALL DISSIMILAR METALS.

J. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO

COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND

RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.

K. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW EXPOSED EXTERIOR PIPE

PENETRATIONS AND SEAL COMPLETELY.

L. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE MODIFYING

SUBFLOORING.

M. SEE M-501 FOR LOW PRESSURE DUCT FITTING DETAILS.

N. SEE M-501 FOR DIFFUSER AND REGISTER CONNECTION DETAILS.

O. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

P. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES AND M-802 AND M-803

FOR CONTROL SEQUENCE.

Q. PROVIDE PRECONSTRUCTION TAB READINGS OF THE EXISTING SUPPLY AIR AND

RETURN AIR SERVING THE ROOMS IN THE AREA OF WORK. REBALANCE EXISTING

SUPPLY AND RETURN AIR SYSTEMS AFTER DEMOLITION IS COMPLETE.

R. TECHNICAL COORDINATION DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING

ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT

SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL

SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN,

CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN

THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND

VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND

REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING.

KEYNOTES

Revisions: Date:

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE RESISTANT, OR BOTH

FIRE AND SMOKE RESISTANT ARE SHOWN GRAPHICALLY ON PLANS WITH

BOPC.6BOPC.5.ABOPC.5BOPC.4

BOPC.A

BOPC.A.1

BOPC.B

BOPC.B.1

BOPC.C

BOPC.D

BOPC.E

F1/MP100A

F4/MP100D

VAV-1-12

VAV-1-17

VAV-1-18

CORRIDOR

B1C-1

WAITING

B1C-1

FEMALE RR

B1C32

MALE RR

B1C33

PAT TLT

B1C34J

NEW OBSERVATION

ROOM

B1C34G

PATIENT COMFORT

ROOM

BC127

CORRIDOR

B1C-9

NEW OBSERVATION

ROOM

B1C23

NEW OBSERVATION

ROOM

BC24

NEW OBSERVATION

ROOM

B1C21

HAC

BC50

CORRIDOR

B1C-6

PAT SHWR

B1C25B

CLEAN UTILITY

BC26

PAT TLT

B1C25A

HALL

B1C-6A

NEW NURSES

STATION

B1C34B

NEW NURSES

STATION

B1C34F

NEW OBSERVATION

ROOM

B1C34K

CORRIDOR

B1C-2

LINEN CLOSET

B1C41

ELEVATOR EQUIP RM

B1C40

ELEVATOR

S-5

ELEVATOR

S-6

HEAD NURSE

B1C37

CHIEF OF ER

B1C35

OBSERVATION/

TREATMENT RM

B1C14

CORRIDOR

B1C-4

SOILED UTILITY

B1C53

CLEAN UTILITY

B1C52

STF TLT

BC51

CORRIDOR

B1C-2

STAIR NO.4

B1C43

LINEN CLOSET

B1C42

HAC

B1C49

NEW OBSERVATION

ROOM

B1C34A

NEW OBSERVATION

ROOM

B1C34C

NEW OBSERVATION

ROOM

B1C34E

NEW STORAGE

B1C34H

NEW STORAGE

B1C34D

2" HWS

2" HWR

3/4" HWR

3/4" HWS

2" HWR

2" HWS

V-05 V-06

V A

V -1

-1

V A

V -1

-1

VAV-1-15

VAV-1-14VAV-1-13

VAV-1-8

VAV-1-9

VAV-1-11

V-11 V-12

2" HWS

2" HWR

3/4" HWS

3/4" HWR

2" HWS

2" HWR

4" HWS

4" HWR

V-01 V-02

V-08

V-07

F4/MP100C

VAV-1-6

2" HWS

2" HWR

3/4" HWR

3/4" HWS

3/4" HWS

3/4" HWR

3/4" HWR

3/4" HWS

3/4" HWS

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWS

3/4" HWR

3/4" HWR

3/4" HWS

V-19 V-20V-22

V-21V-23 V-24

V-26 V-25

V-28 V-27

V-29 V-30

VAV-1-2

3/4" HWS

3/4" HWR

V-17 V-18

V-15 V-16

3/4" HWS

3/4" HWR

3/4" HWS

3/4" HWR

2" HWS

2" HWR

3/4" HWS

3/4" HWR

V-09

V-10

V-13 V-14

V-04

V-03 3/4" HWS

3/4" HWR

NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

KEY PLAN

B

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:5

:5

A

M

MP100B

MECHANICAL PIPING PLAN - LEVEL

B - AREA B

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

1/4" = 1'-0" F4

MECHANICAL PIPING PLAN - BASEMENT - AREA B

1 CONTRACTOR SHALL INSTALL NEW HOSE AND VALVE KIT SERVING NEW TERMINAL

UNITS, REFER TO DETAILS ON SHEET M-501.

2 PROVIDE NEW HOT WATER SUPPLY AND RETURN CONNECTIONS WITH ISOLATION

VALVES, MAIN BRANCH TO SERVE TERMINAL UNIT REHEAT COILS ON THE BASEMENT

LEVEL.

3 PROVIDE NEW ISOLATION BALL VALVES, CONTRACTOR SHALL COORDINATE FINAL

VALVE NUMBERING WITH THE VA.

4 PROVIDE NEW HOT WATER SUPPLY AND RETURN PIPING TO NEW TERMINAL UNITS,

INSULATE PIPING PER SPECIFICATION SECTION 23 00 11. COORDINATE ALL ROUTING

WITH EXISTING TRADES PRIOR TO INSTALLATION.

5 PROVIDE NEW TERMINAL UNIT LOCATED IN CEILING SPACE. COORDINATE LOCATION

WITH MANUFACTURER'S MINIMUM REQUIRED SERVICE CLEARANCE AND OTHER

TRADES. TYPICAL FOR ALL UNITS.

GENERAL SHEET NOTES

A. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-CONSTRUCTION TAB

REPORT FOR THE EQUIPMENT AND ASSOCIATED SYSTEMS SHOWN ON THE

CONSTRUCTION DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT DRAWINGS

FROM THE OWNER. TEST AND BALANCE CONTRACTOR SHALL VISIT SITE PRIOR TO

CONSTRUCTION AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND DEVELOP

THEIR TEST AND BALANCE FORMS INCLUDING DRAWINGS SHOWING EQUIPMENT

LOCATIONS, AIR DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF THERE

ARE LOCATIONS WHERE THE DRAWINGS DO NOT REFLECT FIELD CONDITIONS, THE

TEST AND BALANCE CONTRACTOR SHALL INCLUDE THE AIRFLOW AND WATERFLOW

READINGS ON THE FORMS AND LOCATE THE EQUIPMENT AND/OR AIR DEVICE ON

THE DRAWINGS. REFER TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

B. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE UTILIZED TO

ESTABLISH NEW HVAC SYSTEM PERFORMANCE AND BALANCE DATA FOR THE

RENOVATION. DATA SHALL BE FORWARDED TO THE PROJECT ENGINEER FOR

REVIEW AND COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR NEW

WORK ASSOCIATED WITH THE FACILITY RENOVATION.

C. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

D. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION WARRANTY

REQUIREMENTS FOR ANY MODIFICATIONS TO ROOFING TO ENSURE NO VIOLATIONS

OCCUR OF THE WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED ROOFING

INSPECTOR MEETING THE REQUIREMENTS OF THE INSTALLED ROOF. ALL

WARRANTY VIOLATIONS WILL BE REQUIRED TO BE CORRECTED PRIOR TO CLOSE

OUT. ROOFS AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

E. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED

WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED

AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF

CAULKING MATERIAL.

F. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING, AND CONDUIT PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL PROVIDE

NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

G. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.

CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR

TO NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY

FROM CONSTRUCTION DOCUMENTS.

H. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT LOCATIONS WITH ALL TRADES

PRIOR TO INSTALLATION.

I. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS

BETWEEN ALL DISSIMILAR METALS.

J. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO

COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND

RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.

K. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW EXPOSED EXTERIOR PIPE

PENETRATIONS AND SEAL COMPLETELY.

L. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE MODIFYING

SUBFLOORING.

M. SEE M-501 FOR LOW PRESSURE DUCT FITTING DETAILS.

N. SEE M-501 FOR DIFFUSER AND REGISTER CONNECTION DETAILS.

O. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

P. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES AND M-802 AND M-803

FOR CONTROL SEQUENCE.

Q. PROVIDE PRECONSTRUCTION TAB READINGS OF THE EXISTING SUPPLY AIR AND

RETURN AIR SERVING THE ROOMS IN THE AREA OF WORK. REBALANCE EXISTING

SUPPLY AND RETURN AIR SYSTEMS AFTER DEMOLITION IS COMPLETE.

R. TECHNICAL COORDINATION DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING

ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT

SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL

SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN,

CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN

THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND

VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND

REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING.

KEYNOTES

Revisions: Date:

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE RESISTANT, OR BOTH

FIRE AND SMOKE RESISTANT ARE SHOWN GRAPHICALLY ON PLANS WITH

FD

BOPC.6BOPC.5.ABOPC.5BOPC.4

BOPC.D

BOPC.E

BOPC.F

BOPC.G

F1/MP100A

F4/MP100D

1-AHU-4

1-AHU-3

NEW OBSERVATION

ROOM

B1C23

NEW OBSERVATION

ROOM

BC24

LINEN CLOSET

B1C41

OBSERVATION/

TREATMENT RM

B1C14

CORRIDOR

B1C-4

SOILED UTILITY

B1C53

CLEAN UTILITY

B1C52

STF TLT

BC51

CORRIDOR

B1C-2

STAIR NO.4

B1C43

LINEN CLOSET

B1C42

MECHANICAL ROOM

B1C17

AREAWAY

HAC

B1C49

CT SCANNER

B1C46

EQUIP STOR

B1C44

3/4" HWR

3/4" HWS

V A

V -1

-1

VAV-1-15

VAV-1-6

4" CHS

4" CHR

4" HWS

4" HWR

3/4" HWR

3/4" HWS

4" HWR

4" HWS

4" CHS

4" CHR

1 1/2" HWR

1 1/2" HWS

3" CHS

3" CHR

1 1/4" CD

4" HWS

4" HWR

6" CHR

4" CHS

4" HWS

4" HWR

6" CHR

6" CHS

2" HWS

2" HWR

2" MPS

3/4" CD

4" HWS

4" HWR

4" CHR

4" CHS

F4/MP100B

1 1/2" MPS

3/4" CD

1-AHU-3

NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

KEY PLAN

C

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:5

:0

A

M

MP100C

MECHANICAL PIPING PLAN - LEVEL

B - AREA C

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

1/4" = 1'-0" F4

MECHANICAL PIPING PLAN - BASEMENT - AREA C OPTION 2

1 CONTRACTOR SHALL INSTALL NEW HOSE AND VALVE KIT SERVING NEW TERMINAL

UNITS, REFER TO DETAILS ON SHEET M-501.

2 PROVIDE NEW HOT WATER SUPPLY AND RETURN PIPING TO NEW TERMINAL UNITS,

INSULATE PIPING PER SPECIFICATION SECTION 23 00 11. COORDINATE ALL ROUTING

WITH EXISTING TRADES PRIOR TO INSTALLATION.

3 AHU CONDENSATE DRAIN PIPING, SLOPE PIPING 1/8”/FT MINIMUM. DROP DOWN TO

DISCHARGE OVER EXISTING FLOOR DRAIN BELOW WITH A MINIMUM OF TWO PIPE

DIAMETERS AIR GAP ABOVE FLOOR DRAIN RIM. SECURE PIPING TO FLOOR WITH

UNI-STRUT CHANNEL.

4 PROVIDE NEW TERMINAL UNIT LOCATED IN CEILING SPACE. COORDINATE LOCATION

WITH MANUFACTURER'S MINIMUM REQUIRED SERVICE CLEARANCE AND OTHER

TRADES. TYPICAL FOR ALL UNITS.

GENERAL SHEET NOTES

A. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-CONSTRUCTION TAB

REPORT FOR THE EQUIPMENT AND ASSOCIATED SYSTEMS SHOWN ON THE

CONSTRUCTION DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT DRAWINGS

FROM THE OWNER. TEST AND BALANCE CONTRACTOR SHALL VISIT SITE PRIOR TO

CONSTRUCTION AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND DEVELOP

THEIR TEST AND BALANCE FORMS INCLUDING DRAWINGS SHOWING EQUIPMENT

LOCATIONS, AIR DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF THERE

ARE LOCATIONS WHERE THE DRAWINGS DO NOT REFLECT FIELD CONDITIONS, THE

TEST AND BALANCE CONTRACTOR SHALL INCLUDE THE AIRFLOW AND WATERFLOW

READINGS ON THE FORMS AND LOCATE THE EQUIPMENT AND/OR AIR DEVICE ON

THE DRAWINGS. REFER TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

B. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE UTILIZED TO

ESTABLISH NEW HVAC SYSTEM PERFORMANCE AND BALANCE DATA FOR THE

RENOVATION. DATA SHALL BE FORWARDED TO THE PROJECT ENGINEER FOR

REVIEW AND COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR NEW

WORK ASSOCIATED WITH THE FACILITY RENOVATION.

C. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

D. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION WARRANTY

REQUIREMENTS FOR ANY MODIFICATIONS TO ROOFING TO ENSURE NO VIOLATIONS

OCCUR OF THE WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED ROOFING

INSPECTOR MEETING THE REQUIREMENTS OF THE INSTALLED ROOF. ALL

WARRANTY VIOLATIONS WILL BE REQUIRED TO BE CORRECTED PRIOR TO CLOSE

OUT. ROOFS AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

E. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED

WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED

AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF

CAULKING MATERIAL.

F. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING, AND CONDUIT PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL PROVIDE

NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

G. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.

CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR

TO NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY

FROM CONSTRUCTION DOCUMENTS.

H. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT LOCATIONS WITH ALL TRADES

PRIOR TO INSTALLATION.

I. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS

BETWEEN ALL DISSIMILAR METALS.

J. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO

COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND

RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.

K. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW EXPOSED EXTERIOR PIPE

PENETRATIONS AND SEAL COMPLETELY.

L. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE MODIFYING

SUBFLOORING.

M. SEE M-501 FOR LOW PRESSURE DUCT FITTING DETAILS.

N. SEE M-501 FOR DIFFUSER AND REGISTER CONNECTION DETAILS.

O. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

P. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES AND M-802 AND M-803

FOR CONTROL SEQUENCE.

Q. PROVIDE PRECONSTRUCTION TAB READINGS OF THE EXISTING SUPPLY AIR AND

RETURN AIR SERVING THE ROOMS IN THE AREA OF WORK. REBALANCE EXISTING

SUPPLY AND RETURN AIR SYSTEMS AFTER DEMOLITION IS COMPLETE.

R. TECHNICAL COORDINATION DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING

ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT

SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL

SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN,

CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN

THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND

VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND

REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING.

KEYNOTES

Revisions: Date:

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE RESISTANT, OR BOTH

FIRE AND SMOKE RESISTANT ARE SHOWN GRAPHICALLY ON PLANS WITH

FD

BOPC.3BOPC.2BOPC.1

BOPC.D

BOPC.E

BOPC.F

BOPC.G

F4/MP100B

F4/MP100C

F1/MP100A

VAV-1-3

VAV-1-4

1-AHU-4

1 1

EF-1-11 EF-1-10

STAIR

B1C21

OBSERVATION/

TREATMENT RM

B1C09 OBSERVATION/

TREATMENT RM

B1C10

OBSERVATION/

TREATMENT RM

B1C11

OBSERVATION/

TREATMENT RM

B1C12

OBSERVATION/

TREATMENT RM

B1C13

CORRIDOR

B1C-4

TELEPHONE CLOSET

B1C15

ELECTRIC CLOSET

B1C16

MECHANICAL ROOM

B1C17

AREAWAY

TRANSFORMER RM

B1C17A

ON-CALL RM

B1C18

TOILET

B1C19

STAFF LOUNGE

B1C20

LOCKER RM

B1C20A

3/4" HWR

3/4" HWS

3/4" HWS

3/4" HWR

V A

V -1

-5

3/4" HWS

3/4" HWR

V-60 V-59

V-58 V-57

3/4" HWR

3/4" HWS

3/4" HWS

3/4" HWR

FPH-31 FPH-32

VAV-1-7

NORTH

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

KEY PLAN

D

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:5

:1

A

M

MP100D

MECHANICAL PIPING PLAN - LEVEL

B - AREA D

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

1/4" = 1'-0" F4

MECHANICAL PIP PLAN - BASEMENT - AREA D

1 CONTRACTOR SHALL INSTALL NEW HOSE AND VALVE KIT SERVING NEW TERMINAL

UNITS, REFER TO DETAILS ON SHEET M-501.

2 PROVIDE NEW ISOLATION BALL VALVES, CONTRACTOR SHALL COORDINATE FINAL

VALVE NUMBERING WITH THE VA.

3 PROVIDE NEW HOT WATER SUPPLY AND RETURN PIPING TO NEW TERMINAL UNITS,

INSULATE PIPING PER SPECIFICATION SECTION 23 00 11. COORDINATE ALL

ROUTING WITH EXISTING TRADES PRIOR TO INSTALLATION.

4 PROVIDE NEW TERMINAL UNIT LOCATED IN CEILING SPACE. COORDINATE

LOCATION WITH MANUFACTURER'S MINIMUM REQUIRED SERVICE CLEARANCE AND

OTHER TRADES. TYPICAL FOR ALL UNITS.

GENERAL SHEET NOTES

A. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-CONSTRUCTION TAB

REPORT FOR THE EQUIPMENT AND ASSOCIATED SYSTEMS SHOWN ON THE

CONSTRUCTION DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT DRAWINGS

FROM THE OWNER. TEST AND BALANCE CONTRACTOR SHALL VISIT SITE PRIOR TO

CONSTRUCTION AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND DEVELOP

THEIR TEST AND BALANCE FORMS INCLUDING DRAWINGS SHOWING EQUIPMENT

LOCATIONS, AIR DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF THERE

ARE LOCATIONS WHERE THE DRAWINGS DO NOT REFLECT FIELD CONDITIONS, THE

TEST AND BALANCE CONTRACTOR SHALL INCLUDE THE AIRFLOW AND WATERFLOW

READINGS ON THE FORMS AND LOCATE THE EQUIPMENT AND/OR AIR DEVICE ON

THE DRAWINGS. REFER TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

B. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE UTILIZED TO

ESTABLISH NEW HVAC SYSTEM PERFORMANCE AND BALANCE DATA FOR THE

RENOVATION. DATA SHALL BE FORWARDED TO THE PROJECT ENGINEER FOR

REVIEW AND COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR NEW

WORK ASSOCIATED WITH THE FACILITY RENOVATION.

C. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

D. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION WARRANTY

REQUIREMENTS FOR ANY MODIFICATIONS TO ROOFING TO ENSURE NO VIOLATIONS

OCCUR OF THE WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED ROOFING

INSPECTOR MEETING THE REQUIREMENTS OF THE INSTALLED ROOF. ALL

WARRANTY VIOLATIONS WILL BE REQUIRED TO BE CORRECTED PRIOR TO CLOSE

OUT. ROOFS AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

E. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED AND/OR SMOKE RATED

WALLS AND ASSEMBLIES INDICATED ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS SHALL BE CAULKED

AIRTIGHT TO THE ADJACENT STRUCTURE BY MEANS OF U.L. APPROVED FIRE PROOF

CAULKING MATERIAL.

F. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING, AND CONDUIT PIPING

WITH STRUCTURAL, MECHANICAL, AND ELECTRICAL SYSTEMS AND SHALL PROVIDE

NECESSARY OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

G. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND FIELD VERIFICATION

WHERE FEASIBLE. ACTUAL CONDITIONS MAY DIFFER FROM THOSE INDICATED.

CONTRACTOR SHALL FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR REMOVED. CONTRACTOR

TO NOTIFY ARCHITECT SHOULD CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY

FROM CONSTRUCTION DOCUMENTS.

H. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT LOCATIONS WITH ALL TRADES

PRIOR TO INSTALLATION.

I. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS REQUIRED AT CONNECTIONS

BETWEEN ALL DISSIMILAR METALS.

J. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS REQUIRED TO

COMPLETE THIS PROJECT, THE CONTRACTOR SHALL PATCH AND PAINT AND

RETURN TO MATCH EXISTING CONDITIONS AND FINISHES.

K. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW EXPOSED EXTERIOR PIPE

PENETRATIONS AND SEAL COMPLETELY.

L. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE MODIFYING

SUBFLOORING.

M. SEE M-501 FOR LOW PRESSURE DUCT FITTING DETAILS.

N. SEE M-501 FOR DIFFUSER AND REGISTER CONNECTION DETAILS.

O. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

P. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES AND M-802 AND M-803

FOR CONTROL SEQUENCE.

Q. PROVIDE PRECONSTRUCTION TAB READINGS OF THE EXISTING SUPPLY AIR AND

RETURN AIR SERVING THE ROOMS IN THE AREA OF WORK. REBALANCE EXISTING

SUPPLY AND RETURN AIR SYSTEMS AFTER DEMOLITION IS COMPLETE.

R. TECHNICAL COORDINATION DRAWINGS OF COMPLETE ASSEMBLIES, REFLECTING

ACCURATE PROJECT CONDITIONS, SHALL BE SUBMITTED WITH EQUIPMENT

SELECTIONS TO ENSURE SPACE ALLOWANCES ARE REFLECTED IN THE ACTUAL

SPACE AVAILABLE. WHERE SIZE DEVIATIONS DIFFER FROM THE BASIS OF DESIGN,

CONTRACTOR SHALL HIGHLIGHT THE DIFFERENCES FOR AE/COR REVIEW WITHIN

THE SUBMITTAL. CONTRACTOR SHALL PROVIDE INSTALLATION ROUTE AND

VERIFICATION THAT ACCESS POINTS, PLACEMENT ROUTE, SUPPORTS, AND

REQUIRED EQUIPMENT CLEARANCES ARE IDENTIFIED ON THE ROUTE DRAWING.

KEYNOTES

Revisions: Date:

PARTITION RATING GRAPHICS:

4 HR FIRE BARRIER

3 HR FIRE BARRIER

2 HR FIRE & SMOKE BARRIER

2 HR FIRE BARRIER

2 HR FIRE BARRIER/SHAFT

1 HR FIRE & SMOKE BARRIER

1 HR FIRE BARRIER

1 HR FIRE BARRIER/SHAFT

SMOKE PARTITION (NON RATED)

NON RATED

PARTITION RATING GRAPHIC DESIGNATION: PRIORITY

1 HIGHEST

5 LOWEST

PARTITIONS REQUIRED TO BE SMOKE RESISTANT, FIRE RESISTANT, OR BOTH

FIRE AND SMOKE RESISTANT ARE SHOWN GRAPHICALLY ON PLANS WITH

M

IN

IM

U

M

ROOF TOP UNIT

LAP VERTICAL

MEMBRANE

LAYERS OVER

CURB

OVERLAP

HORIZONTAL

MEMBRANE LAYERS

AT CANT OR CRICKET

SECURE LEVELED PRE-

FABRICATED ROOF CURB TO

FIRE TREATED NAILER

SECURED TO ROOF DECK.

REFER TO AHU SCHEDULE

NOTE 7 ON SHEET M-701.

OPENING FRAMING,

SEE STRUCTURAL

DRAWINGS

DUCTWORK, SEE

MECHANICAL

DRAWINGS

SEAL ALL FASTENERS

THROUGH CAP, SEAL

CAP TO CURB

20 30

RISE

PLAN

NOTES

1. ANGLE A=30 MAXIMUM WHEN AIR FLOWS IN

DIRECTION OF ARROS. (SUPPLY AIR)

2. ANGLE A=15 WHEN AIR FLOWS IN OPPOSITE

DIRECTION OF ARROS (R.A. OR EXHAUST)

20°

A°

A°

A°

A°

3.73xH

FBFT

FT FB

A°A°

A°

A°

PLAN VIEW PLAN VIEW PLAN VIEW

TRANSITION

w/ EQUIPMENT

ELEVATION

PLAN

DUCT OFFSET

FT FB

FBFT

A°

A° A°

A°

ELEVATION ELEVATION ELEVATION BRANCH DUCT

PLAN

45° W

1/2 W

(4"MIN.)

PLAN A

A

B

C

(1) NECK DIA. MIN.

PROVIDE QUADRANT

LOCKING HAND DAMPER

WITH ACCESS DOOR

WHERE SHOWN ON PLANS

BRANCH

DUCT

BRANCH MAIN

FIXED CEILINGS

SECTION A

FLEX DUCT. DIAMETER

EQUALTO DIFFUSER NECK

SIZE (MAX. LENGTH 4'-0")

SPIN IN FITTING

W/HAND DAMPER

SECTION B

LAY-IN CEILINGS

PLAN B

RIGID DUCT WHERE

RUN-OUT EXCEEDS 4'-0"

PROVIDE HAND DAMPER

WITH ACCESS DOOR

WHERE SHOWN

ON PLANS

SHEET METAL

PLENUM

RIGID DUCT WHERE

RUN-OUT EXCEEDS 4'-0"

FLEX. DUCT FOR LAY-IN

CEILING APPLICATION

EXHAUST / DUCTED RETURN

GRILLE. SEE FLOOR PLAN

FOR SIZE, TYPE, AND LOCATION

SECTION C

RETURN/EXHAUST REGISTER

FOR LAY-IN AND FIXED CEILINGS

PLAN C

(E) WALL OR

CEILING

10 GAUGE STEEL PIPE

SLEEVE THROUGH

WALL

CONDUIT OR STEEL

PIPE, INSULATED WHERE

OCCURS

SEAL SLEEVE WITH UL RATED

SEALANT TO MATCH RATING OF

WALL OR CEILING. MAINTAIN

REQUIRED MINIMUM CONTACT OF

SEALANT AND CLEARANCES OF

PIPE IN PENETRATION

PROVIDE ESCUTCHEON PLATE AT

ALL EXPOSED PENETRATIONS

UL Listed System No. C-AJ-2001

AIR FLOW

HWS

7 14

1 2

METAL STRAP SUPPORT FROM STRUCTURE (TYPICAL)

MANUAL AIR VENT ON COIL OR HWR PIPING

FACTORY FABRICATED SOUND ATTENUATOR

HOT WATER COIL

VALVE ACTUATOR

HIGH VELOCITY FLEXIBLE SUPPLY DUCT 12" MIN., 24" MAX.

DRAIN

TEMPERATURE-PRESSURE FITTING (TYP.)

LOW VELOCITY DUCTWORK TO DISTRIBUTION

REFER TO PLANS FOR PIPE SIZES

2-WAY CONTROL VALVE, NORMALLY CLOSED. FAIL TO COOL

BALL VALVE (TYP)

UNION (TYP)

REDUCER (TYP)

HIGH VELOCITY RIGID SUPPLY DUCT, 3 FT. MINIMUM STRAIGHT RUN PRIOR

TO TERMINAL UNIT CONNECTION. SEE SCHEDULE FOR VALVE AND DUCT SIZES

FLOW BALANCING VALVE, OR FLOW LIMITING VALVE, SEE SPECIFICATIONS

TRANSITION FROM 2" LARGER DUCT DIAMETER THAN VALVE CONNECTION SIZE

HWR

METAL STRAP SUPPORT FROM STRUCTURE. (TYPICAL)

MANUAL AIR VENT ON COIL OR HWR PIPING

FACTORY FABRICATED SOUND ATTENUATOR

HOT WATER COIL

VALVE ACTUATOR

HIGH VELOCITY FLEXIBLE SUPPLY DUCT 12" MIN., 24" MAX.

DRAIN

TEMPERATURE-PRESSURE FITTING (TYP.)

LOW VELOCITY DUCTWORK TO DISTRIBUTION

REFER TO PLANS FOR PIPE SIZES

3-WAY CONTROL VALVE

BALL VALVE (TYP)

UNION (TYP)

REDUCER (TYP)

HIGH VELOCITY RIGID SUPPLY DUCT, 3 FT. MINIMUM STRAIGHT RUN PRIOR TO

TERMINAL UNIT CONNECTION. SEE SCHEDULE FOR VALVE AND DUCT SIZE

FLOW BALANCING VALVE, SEE SPEC. SECTION 15080

STRAINER

TRANSITION FROM 2" LARGER DUCT DIAMETER THAN VALVE CONNECTION

AIR FLOW

C

HWR

NC

NO

HWS

1 2

22-1/2 2-PIECE

ELBOW

A

R R R

A A

30 2-PIECE

ELBOW

45 ELBOW

(3" THRU 8")

45 3-PIECE

ELBOW

60 3-PIECE

ELBOW

90 ELBOW

(3" THRU 8")

90 5-PIECE

ELBOW

CONCENTRIC REDUCER

RL=A-B (MIN)

ECCENTRIC REDUCER

RL=2(AB)

LATERAL TEE LATERAL CROSS REDUCING

LATERAL TEE

RL=A-B (MIN)

REDUCING

LATERAL CROSS

A

R

A

R

A

RL

B A

RL

B

A A

R R

A

L

C C

A L

D

A

C

RL B

L

A L

C

RL B

D

A

C

L L RL

A

C

B

C

A

L

A

C

B

L RL

COMBINATION TEE REDUCING

COMBINATION TEE

SPUN TEE REDUCING

SPUN TEE

CONICAL LATERAL REDUCING

CONICAL LATERAL

TANGENTIAL TEE

TYPE: ONE TAP

L=C+2"

TYPE: TWO TAPS

L=C+D+4"

CONICAL TEE

L=C+4"

REDUCING

CONICAL TEE

L=C+4" X=(C/2)+2"

5"MIN.

5"MIN.

L=LARGER OF

(C OR D)+4"

CONICAL CROSS

L=1.414 C+5"

(MAX)

Q=(A/2)+.707C+3"

(MAX)

H=.707A+.5C+3"

(MAX)

5"MIN.5"MIN.

NOTE: SEE SPECIFICATIONS FOR DUCT MATERIALS AND CONSTRUCTION

L

Q

A 1"

1" 4"

H C

L

Q

A 1"

4" H

C 1"

RL

B

1"

A

1" 1"

L

1"

C D

C

A

L

5"MIN.

C

A

L RL

B

C

A L

D

NTS

E8

ROOF LEVEL CURB DETAIL

NTS

F8

LOW PRESSURE DUCT FITTINGS

NTS

C8

DIFFUSER AND REGISTER CONNECTION

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:4

:3

A

M

M-501

MECHANICAL DETAILS

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS K. LUKE

ISSUED FOR

CONSTRUCTION

NTS

F4

MECHANICAL EQUIPMENT - DRAIN CONNECTION

NTS

F1

STEAM HUMIDIFIER - PIPING CONNECTIONS

NTS

D1

PIPE PENETRATION AT EXTERIOR WALL

NTS

C1

SINGLE DUCT VAV TERMINAL UNIT WITH REHEAT COIL - 2 WAY VALVE

NTS

C4

SINGLE DUCT VAV TERMINAL UNIT WITH REHEAT COIL - 3 WAY VALVE

NTS

F6

MEDIUM PRESSURE AND ROUND DUCT FITTINGS

Revisions: Date:

FILL OPENING WITH

GROUTOR SEALANT

DEPENDING UPON

BUILDING MATERIALS

PENETRATED

PIPE SLEEVE OR

SHEET METAL SLEEVE

SEAL ALL AROUND

WITH RESILIENT

NON-HARDENING

SEALER-TYP BUILDING WALL OR FLOOR

1/2" TO 5/8" ANNULAR

SPACE-PACK SPACE

WITH FIBERGLASS

MATERIAL

PIPE OR ELECTRICAL CONDUIT

5 FT

6 8 10

9 1110 12

-1312 14 -16 -

1614 17 2219 23

2725 28 3230

20 241814 16128 1064 532 2 1/21 1/21 1 1/4THRU 3/4

7 7

7 98

SIDE VIEW TRAPEZE HANGER FOR UP TO

1000 LB. UNIFORM LOAD

ADJUSTABLE CLEVIS HANGER TYPE 1 - SEE SPECIFICATIONS ADJUSTABLE CLEVIS HANGER TYPE 43 - SEE SPECIFICATIONS

MAXIMUM PIPE/TUBING SUPPORT SPACING

NOTE: FOR TRAPEZE HANGER TAKE SPACING OF SMALLEST SIZE ON TRAPEZE.

NOM. SIZE

PIPE

TUBING

IN.

FT.

FT.

M A

X

PROVIDE INSULATION

SHIELD & INSERT FOR

ALL PIPING (8" MIN.)

BAND

1-5/8" 12 GAUGE

CHANNEL OR

2"x2"x1/4"

ANGLE

1/2" DIA. HANGER

RODS WITH

36" MAX. SPACING

ON EACH CHANNEL

WELD

SADDLE

INSULATION SHIELD

AT HANGER

PROVIDE HIGH

COMPRESSIVE

STRENGTH INSULATION (9

PSF MIN. DENSITY) UNDER

INSULATION SHIELD

INSULATION (VAPOR

BARRIER TYPE IS

REQUIRED FOR LOW

TEMPERATURE PIPE)

HANGER ROD

NOTES:

SEE SPECIFER FOR

DETAILED HANGER

REQUIREMENTS

NOTE:

USE KINETIC, OR EQUIVALENT FOR

ALL SEISMIC RESTRAINTS. SEE

SPECIFICATIONS SECTION 15200.

CABLE ALIGNMENT (MAX ALLOWABLE)

PLAN VIEW

SEE CALCULATIONS FOR MAXIMUM ROD

LENGTH BEFORE REINFORCING IS REQUIRED

ANCHOR BOLTS NOT

SUPPLIED BY KNC

OPTIONAL 2 OR

4 BOLT BRACKET

MIN1

FLOW

1 MAX

CABLE CHIPS

BY KNC

THIMBLE

SUPPLIED BY KNC

3/8 (1/4 CABLE) DIAMETER ROD

UP TO 7/8 (3/8-1/2 CABLE)

NUTS FOR ATTACHMENT, NOT

SUPPLIED BY KNC

GR 8 CABLE

HARDWARE BY

KNC

1/2" TO 1" BOLT WITH

WASHERNOT SUPPLIED

BY KNC

NO RESTRAINT

REQUIRED

IF DUCT AREA < 6 SQ. FT HVAC DUCT

ATTACHMENT HARDWARE BY KNC

CABLE ANCHOR

BRACKET BY

KNC

ISOLATED OR

NON-ISOLATED

ISOLATED OR

NON-ISOLATED

12" MAX

12" MAX

NO RESTRAINT REQUIRED

IF ROD UNDER 12" LONG

NO RESTRAINT REQUIRED

IF ROD UNDER 12" LONG

SWIVEL REQ

FOR 2000 IBC SWIVEL REQ

FOR 2000 IBC

FLOW FLOW

F L O

W

NOTE:

USE KINETIC, OR EQUIVALENT FOR ALL SEISMIC

RESTRAINTS. SEE SPECIFICATIONS SECTION 15200.

PERPENDICULAR ALIGNMENT

(MAX ALLOWABLE)

PLAN VIEW

MIN1

SEE CALCULATIONS FOR MAXIMUM ROD LENGTH

BEFORE REINFORCING IS REQUIRED

ANCHOR BOLTS NOT SUPPLIED BY KNC

OPTIONAL 2 OR

4 BOLT BRACKET

3/8 (1/4 CABLE) DIA ROD UP TO 7/8

(3/8-1/2 CABLE) NUTS FOR

ATTACHMENT - NOT SUPPLIED BY KNC

GR 8 HARDWARE

CABLE

1/2" TO 1" BOLT

WITH WASHER NOT

SUPPLIED BY KNC

SUPPLIED BY KNC

AND CLIPS BY KNC

NO RESTRAINT

REQUIRED

IF PIPE SIZE < 2-1/2"

(1-1/2" IN MECH ROOMS)

HVAC DUCT

ISOLATED OR

NON-ISOLATED

ISOLATED OR

NON-ISOLATED

SYMMETRICAL

ABOUT CENTER

LINE

SYMMETRICAL

ABOUT CENTER

LINENO RESTRAINT

REQUIRED IF

ROD UNDER

12' LONG

NO RESTRAINT

REQUIRED IF

ROD UNDER

12' LONG

SWIVEL

REQUIRED

FOR 2000 IBC

SWIVEL

REQUIRED

FOR 2000 IBC

12" MAX

12" MAX

1 MAX

SUPPLY WATER SHALL BE CONNECTED

TO AIR LEAVING SIDE OF COIL

COLLECT ALL DRAINS, INSTALL HOSE

CONNECTION AND CAP

TEMP. AND PRESS. FITTING TYP.

PRESSURE GAUGE

THERMOMETER

UNION

AUTOMATIC TWO-WAY CONTROL VALVE

BUTTERFLY VALVE

MANUAL AIR VENT

1/2" GATE VALVE AND DRAIN

DASHED PIPING AND COILS INDICATE

TYPICAL PIPING REQUIREMENTS FOR

MULTIPLE COILS

FLOW CONTROL VALVE, SEE

SPECIFICATIONS SECT. 15080

CONNECTION

STRAINER WITH HOSE BIBB

GENERAL NOTES

1 PROVIDE MANUAL AIR VENTS AT ALL

HIGH POINTS IN SYSTEM.

2 SEE PLANS AND/OR PIPING

SCHEMATIC FOR PIPE SIZES.

3 TEMP./PRESS. FITTINGS INSTALLED

IN PIPING 2" AND SMALLER SHALL

BE INSTALLED IN ELBOW OR IN THE

BRANCH SIDE OF A 2" TEE.

COIL

COIL

AIR FLOW

HWS

HWR

6 12

SUPPLY WATER SHALL BE CONNECTED

TO AIR LEAVING SIDE OF COIL

COLLECT ALL DRAINS, INSTALL HOSE

CONNECTION AND CAP

TEMP. AND PRESS. FITTING TYP.

PRESSURE GAUGE

THERMOMETER

UNION

AUTOMATIC TWO-WAY CONTROL VALVE

BUTTERFLY VALVE

MANUAL AIR VENT

1/2" GATE VALVE AND DRAIN

DASHED PIPING AND COILS INDICATE

TYPICAL PIPING REQUIREMENTS FOR

MULTIPLE COILS

FLOW CONTROL VALVE, SEE SPECIFICATIONS

GENERAL NOTES

1. PROVIDE MANUAL AIR VENTS AT ALL HIGH

POINTS IN SYSTEM.

2. SEE PLANS AND/OR PIPING SCHEMATIC FOR

PIPE SIZES.

3. TEMP./PRESS. FITTINGS INSTALLED IN PIPING

2" AND SMALLER SHALL BE INSTALLED IN ELBOW

OR IN THE BRANCH SIDE OF A 2" TEE.

CHS

CHR

COIL

AIR FLOW

COIL

1" OVERLAP

ON ALL SIDES

OF DAMPER

AIRFLOW

1" OVERLAP

ON ALL SIDES

OF DAMPER

AIRFLOW

MULTIBLADE NON-AIRFOIL

(LOW VELOCITY APPLICATIONS

1500 FPM & LESS)

MULTIBLADE AIRFOIL

(HIGH VELOCITY APPLICATIONS

IN EXCESS OF 1500 FPM)

WALL OR FLOOR

SLEEVE - SEE MANUFACTURE'S INSTALLATION NOTES

MOUNTING ANGLES CONTINUOUS AROUND SLEEVE WITH MINIMUM 1" OVERLAP

SQUARE OR RECTANGULAR DAMPER FRAME FOR ROUND OR OVAL DUCTS,

PROVIDE DUCT TRANSITION

BREAKAWAY DUCT CONNECTION - SEE INSTALLATION NOTES

INSTALL DAMPER ASSEMBLY PER MANUFACTURER'S INSTALLATION INSTRUCTIONS

1/4" MINIMUM EXPANSION CLEARANCE - SEE MANUFACTURE'S INSTALLATION NOTES

APPROVED SEALING MATERIAL IN ACCORDANCE WITH MANUFACTURER'S

INSTALLATION INSTRUCTIONS

U.L. APPROVED DAMPER ACTUATOR ASSEMBLY WITH MOUNTING BRACKET,

ELECTRIC FUSE LINK, AND OPERATING JACK SHAFT LINKAGE. DAMPER

ACTUATOR SHALL BE MOUNTED ON DUCT OUTSIDE AIR STREAM\

INTEGRAL FACTORY WIRED FOR SINGLE POINT POWER CONNECTION, NO FLOW

SMOKE DETECTOR WITH BUILT-IN TEST SWITCH RATED FOR 0-3000 FPM, MOUNTED

INTERNALLY TO THE DAMPER SLEEVE

* FUSIBLE ROD IS NOT REQUIRED FOR SMOKE DAMPER APPLICATION

6" 6"6"6"

10 10

V A

R

IE

S

VARIES

LOWER BRACING

MAY RE REUIRED ON

TALLER FRAMES,

FOLLOW

MANUFACTURER’S

RECOMMENDATION

D11

D1+12"

STORM COLLAR

D+4"

ROOF FLASHING

D1=D+2"

D

/2

D

D+6"

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:4

:3

A

M

M-502

MECHANICAL DETAILS

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS K. LUKE

ISSUED FOR

CONSTRUCTION

NTS

C6

PIPE PENTRATION DETAIL

NTS

C8

PIPE SUPPORTS

NTS

F8

MISCELLANEOUS VALID RESTRAINT ARRANGEMENTS

NTS

F6

MISCELLANEOUS VALID RESTRAINT ARRANGEMENTS

NTS

F4

HOT WATER COIL PIPING SCHEMATIC WITH 2-WAY VALVE

NTS

C4

CHILLED WATER COIL PIPING SCHEMATIC

Revisions: Date:

NTS

F1

SMOKE DAMPER AND COMBINATION FIRE SMOKE DAMPER DETAIL

NTS

C1

TEMPORARY DUCT SUPPORT

NTS

A1

EXHAUST DUCT WEATHER HOOD

M

IN

B C

B C

V E

S T

IB

U

L E

C A

V -1

-1

E N

T R

A N

C E

C A

V -1

-3

C A

V -1

-4 B

C

-1

B C

-1

V A

V -1

-1 B

C

B C

B C

B C

-1 A

C A

V -1

-2

B C

B C

B C

C A

V -1

-5

B C

C A

V -1

-6

B C

C A

V -1

-7

B C

C A

V -1

-9

B C

C A

V -1

-8

B C

V A

V -1

-5

EXH

B C

B C

B C

-4

V A

V -1

-7

B C

B C

-9

B C

A

V A

V -1

-2

B C

V A

V -1

-1

B C

-5

B C

V A

V -1

-1

B C

V A

V -1

-6

B C

B C

-2 V

A V

-1 -1

V A

V -1

-1

B C

B C

B C

-1 V

A V

-1 -1

B C

B C

-3

B C

B C

V A

V -1

-1

AREA

WEL

L

SA

SA

SA

HWR

HWS

T

T

TT

T

T T TT T TTT

B C

V A

V -1

-4

T

B C

V A

V -1

-3

T T T T TT

BASEMENT FLOOR

BASEMENT FLOOR

STEEL

GRATING

STREET

CONCRETE

CURB

ROAD

FIRST FLOOR

SECOND FLOOR

THIRD FLOOR

ROOF

15 14 13 12 11

EXH

RA

R A

E X

H

O S

A

O S

A

E X

H

HWR

HWS

RA

EXH

3 45

NOTE: THIS SHEET IDENTIFIES THE HVAC MODIFICATION AND UPGRADES PROPOSED FOR THE BASEMENT LEVEL OF BUILDING OPC. THIS INCLUDES PROVIDING A NEW AIR HANDLING UNIT 3, NEW SPECIAL EXHAUST FAN EF-1 AND NEW GENERAL EXHAUST FAN EF-ED. THE NEW AIR HANDLING UNIT SHALL BE CAPABLE OF OPERATING IN EMERGENCY/100% OUTSIDE AIR MODE. THIS CONFIGURATION REQUIRES A NEW EXHAUST STACK ON THE SOUTH SIDE OF THE BUILDING

EXTERIOR TO MEET VA SAFETY REQUIREMENTS.

CHR

CHS

T

B C

T

B C

V A

V -1

-1

T

B C

T

B C

B

V A

V -1

-1

T

B C

H

V A

V -1

-1

B C

D

B C

K

T

V A

V -1

-9 B

C

G

B C

E

T

B C

A

V A

V -1

-8

B C

C

B C

-6

T

V A

V -1

-1

B C

-4

B C

T

CD

MPS

C D

M P

S

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Mechanical, Electrical and Plumbing:

B

IM

/5

-1 -2

E x p a n d E

D B e d s

/5

-1

-2

.O P

C .M

E .r v t

/1

/2

:4

:4

A

M

M-601

MECHANICAL AIR FLOW DIAGRAM -

SUPPLY AIR

TRIPLE C - THE A-E GROUP

4401 Atlantic Avenue, Suite 200

Long Beach, CA 90807

562.452.7175

MAT PERKINS

REMODEL ED BEDS FOR

OBSERVATION BEDS

2615 E. CLINTON AVENUE, FRESNO, CA 93703

570-17-210

OPC

06/18/2021 M. PERKINS G. WEAVER

ISSUED FOR

CONSTRUCTION

1/4" = 1'-0" F1

MECHANICAL AIR FLOW DIAGRAM - SUPPLY AIR

GENERAL SHEET NOTES

KEYNOTES

1 (E) PENTHOUSE MECHANICAL ROOM S0-401, PROTECT IN PLACE AND

MAINTAIN OPERATIONS THROUGHOUT CONSTRUCTION.

2 (E) RETURN AND EXHAUST AIR SHAFT

3 (N) EXHAUST FAN, EF-1

4 (N) EXHAUST FAN, EF-ED

5 (N) GRAVITY HOOD, GH-1

6 (N) AIR HANLING UNIT, 1-AHU-3

7 RETURN FAN

8 ECONOMIZER BOX

9 MIXING BOX

10 FILTER PF-1

11 FILTER PF-2

12 HEATING COIL

13 COOLING COIL

14 SUPPLY FAN

15 FINAL FILTER FF-1

16 SUPPLY PLENUM

17 ACCESS DOOR

18 STEAM HUMIDIFIER

19 FROM BUILDING ONE SUB-BASEMENT

20 CONTINUES TO AIR HANDLING UNIT 4

21 SEE SHEET M-602 FOR CONTINUATION

22 PROVIDE NEW HOT WATER SUPPLY AND RETURN PIPING TO NEW

TERMINAL UNITS, INSULATE PIPING PER SPECIFICATION SECTION 23 00

11. COORDINATE ALL ROUTING WITH EXISTING TRADES PRIOR TO

INSTALLATION.

23 (N) 36" DIAMETER EXHAUST DUCT AND STACK FROM NEW AHU-3 WITH

OUTLET MINIMUM 10' ABOVE ROOF LEVEL.

A. THIS SHEET IDENTIFIES THE NEW EXTERIOR DUCT SHAFT

REQUIRED FOR EXHAUST AIR COMPLIANCE, RESPECTIVELY.

B. TEST AND BALANCE CONTRACTOR SHALL PROVIDE A PRE-

CONSTRUCTION TAB REPORT FOR THE EQUIPMENT AND

ASSOCIATED SYSTEMS SHOWN ON THE CONSTRUCTION

DOCUMENTS AND UTILIZE ALL AVAILABLE AS-BUILT

DRAWINGS FROM THE OWNER. TEST AND BALANCE

CONTRACTOR SHALL VISIT SITE PRIOR TO CONSTRUCTION

AND VERIFY ALL EXISTING EQUIPMENT AND DEVICES, AND

DEVELOP THEIR TEST AND BALANCE FORMS INCLUDING

DRAWINGS SHOWING EQUIPMENT LOCATIONS, AIR

DISTRIBUTION DEVICE LOCATIONS AND TAG NUMBERS. IF

THERE ARE LOCATIONS WHERE THE DRAWINGS DO NOT

REFLECT FIELD CONDITIONS, THE TEST AND BALANCE

CONTRACTOR SHALL INCLUDE THE AIRFLOW AND

WATERFLOW READINGS ON THE FORMS AND LOCATE THE

EQUIPMENT AND/OR AIR DEVICE ON THE DRAWINGS. REFER

TO SPECIFICATION SECTION 23 05 93 FOR MORE

INFORMATION.

C. ALL DATA OBTAINED VIA TESTING AND MEASURING SHALL BE

UTILIZED TO ESTABLISH NEW HVAC SYSTEM PERFORMANCE

AND BALANCE DATA FOR THE RENOVATION. DATA SHALL BE

FORWARDED TO THE PROJECT ENGINEER FOR REVIEW AND

COMMENT PRIOR TO COMMENCING THE DEMOLITION AND/OR

NEW WORK ASSOCIATED WITH THE FACILITY RENOVATION.

D. PROVIDE AIR BALANCE REPORT PRIOR TO FINAL INSPECTION

E. CONTRACTOR TO COORDINATE WITH ROOF INSTALLATION

WARRANTY REQUIREMENTS FOR ANY MODIFICATIONS TO

ROOFING TO ENSURE NO VIOLATIONS OCCUR OF THE

WARRANTY. CONTRACTOR TO EMPLOY A CERTIFIED

ROOFING INSPECTOR MEETING THE REQUIREMENTS OF THE

INSTALLED ROOF. ALL WARRANTY VIOLATIONS WILL BE

REQUIRED TO BE CORRECTED PRIOR TO CLOSE OUT. ROOFS

AND/OR ROOFING IMPACTED BY WORK INCLUDE B126.

F. CONTRACTOR TO VALIDATE AND VERIFY ALL FIRE RATED

AND/OR SMOKE RATED WALLS AND ASSEMBLIES INDICATED

ON PLANS IN WORK AREA. PROVIDE ALL PIPING

PENETRATIONS OF FIRE, SMOKE AND FULL HEIGHT WALLS

SHALL BE CAULKED AIRTIGHT TO THE ADJACENT STRUCTURE

BY MEANS OF U.L. APPROVED FIRE PROOF CAULKING

MATERIAL.

G. CONTRACTOR SHALL COORDINATE ALL PIPING, PLUMBING,

AND CONDUIT PIPING WITH STRUCTURAL, MECHANICAL, AND

ELECTRICAL SYSTEMS AND SHALL PROVIDE NECESSARY

OFFSETS TO AVOID CONFLICTS AND TO MAINTAIN REQUIRED

EQUIPMENT ACCESS AND SERVICEABILITY.

H. EXISTING CONDITIONS ARE BASED ON EXISTING PLANS AND

FIELD VERIFICATION WHERE FEASIBLE. ACTUAL CONDITIONS

MAY DIFFER FROM THOSE INDICATED. CONTRACTOR TO

FIELD VERIFY IN ADVANCE THE LOCATION AND CONDITION OF

THOSE EXISTING SYSTEMS SHOWN TO BE MODIFIED OR

REMOVED. CONTRACTOR TO NOTIFY ARCHITECT SHOULD

CONDITIONS BE FOUND TO DIFFER SIGNIFICANTLY FROM

CONSTRUCTION DOCUMENTS.

I. CONTRACTOR TO COORDINATE ALL NEW EQUIPMENT

LOCATIONS WITH ALL TRADES PRIOR TO INSTALLATION.

J. CONTRACTOR TO PROVIDE GALVANIC PROTECTION AS

REQUIRED AT CONNECTIONS BETWEEN ALL DISSIMILAR

METALS.

K. ANY FLOOR, WALL, OR CEILING CUTTING OR FILLING THAT IS

REQUIRED TO COMPLETE THIS PROJECT, THE CONTRACTOR

SHALL PATCH AND PAINT AND RETURN TO MATCH EXISTING

CONDITIONS AND FINISHES.

L. CONTRACTOR TO PROVIDE ESCUTCHEONS ON ALL NEW

EXPOSED EXTERIOR PIPE PENETRATIONS AND SEAL

COMPLETELY.

M. CONTRACTOR TO PROVIDE TEMPORARY FLOORING WHILE

MODIFYING SUBFLOORING.

N. REPLACE ALL EXISTING DUCT WRAP IN AREA OF WORK.

O. SEE M-700 SERIES FOR MECHANICAL EQUIPMENT SCHEDULES

AND M-802 AND M-803 FOR CONTROL SEQUENCE.

P. PROVIDE PRECONSTRUCTION…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .