5.7_-_Mechanical.pdf
PDF 5 MB Posted
- Attached to
- CFD Station #344 HVAC Renovation
- Solicitation number
- IFB-2026-019
- Issued by
- Hamilton County, Indiana
About this file
Document Summary
This file is a comprehensive mechanical design document set for the City of Carmel Fire Station #44 HVAC Replacement project located at 5032 E Main Street, Carmel, Indiana 46033. The project involves complete replacement of the heating, ventilating, and air conditioning systems, including demolition of existing Variable Refrigerant Flow (VRF) equipment, installation of new rooftop units (RTU-1 and RTU-2), boiler systems, split-system units, VAV boxes with hot water reheat, exhaust fans, and associated ductwork and piping throughout the basement, first floor, second floor, and roof. The mechanical design includes detailed specifications for equipment scheduling, installation details, and coordination requirements across multiple building levels. The document package consists of mechanical symbols and abbreviations (M-001), demolition plans for basement (MD100), first floor (MD101), second floor (MD102), and roof (MDR101), HVAC plans for each level (MH100-MH102 and MR101), piping plans (MP100-MP102), mechanical details (M-501 and M-502), and equipment schedules (M-601). All work must conform to SMACNA standards for ductwork fabrication, incorporate proper vibration isolation for equipment containing fans or compressors, and maintain fire-rated wall penetrations with appropriate sealing and dampers.
The mechanical systems are designed with two primary rooftop units: RTU-2 (Trane YSK240) serving the basement, first floor, and second floor with 3,000 CFM capacity, and RTU-1 (Trane YSK102) serving the dorms with 1,300 CFM capacity. Additional equipment includes a wall-mounted boiler for heating hot water distribution, split-system units for specific zones, an air separator, expansion tank, water sediment filter, circulation pump with variable frequency drive technology, and multiple exhaust fans. The design emphasizes coordination with structural elements, electrical systems, telecommunications rooms, and elevator equipment rooms, with explicit requirements to avoid routing systems through these critical spaces. Installation must include proper ductwork insulation (externally applied unless noted otherwise), volume dampers for balancing, temperature control sensors, and Building Automation System integration. All work is scheduled with the understanding that existing mechanical systems will be carefully demolished with refrigerant recovery per EPA standards, and salvageable equipment remains the owner's property upon inspection and approval.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABBREVIATIONS
SA
GFUH GAS FIRED UNIT HEATER
HHWR
HHWP
HEATING HOT WATER RETURN
HEATING HOT WATER PUMP
HVLS
HSPF
HS
HR
HX
HD
HP
HUV
HYDRONIC WATER SUPPLY
HIGH VOLUME LEW SPEED FANS
HYDRONIC WATER RETURN
HEATING SEASONAL PERFORMANCE FACTOR
HORIZONTAL UNIT VENTILATOR
HEAT EXCHANGER
HORSEPOWER OR HEAT PUMP
HEAD (FT, U.N.O.)
H
GC
GPM
HUMIDITY / HUMIDIFIER / HUMIDISTAT
GENERAL CONTRACTOR
GALLONS PER MINUTE
STD
ST
SS
SPEC
SD
SG
SHR
SF
F&T FLOAT & THERMOSTATIC STEAM TRAP
FIRE DAMPER
FTR
GAL
GA
FT
FPM
FINNED TUBE RADIATION
GALLON
GAUGE
FEET PER MINUTE
FOOT/FEET
F/SD
FD
FCU
COMBINATION FIRE AND SMOKE DAMPER
FAN COIL UNIT
RS/RL
RPM
RM
RG
RHC
RH
RAT
RECIRC
RF
R
RA
R-#
ENTERING WATER TEMPERATURE (°F)
EXTERNAL STATIC PRESSURE (IN WG)
EX
EXP
FBP
ET
EWT
FACE AND BYPASS DAMPER
EXPANSION
EXISTING
EXPANSION TANK
EMER
ENCL
EOM
ESP
ERV
EF
EFF
ELEV
ELEC
EG
EMERGENCY
END OF MAIN DRIP
ENERGY RECOVERY VENTILATOR
ENCLOSURE
EXHAUST GRILLE
ELEVATION
ELECTRIC
EFFICIENCY
EXHAUST FAN
PSIG
PRESS
PSI
PREFAB
PPM
PHC
PH
PUH
PD
PE
PTAC
SUPPLY AIR
SOUND TRAP / DUCT ATTENUATOR
SPLIT SYSTEM (INDOOR UNIT)
STANDARD
SPECIFICATIONS
SUPPLY DIFFUSER
SENSIBLE HEAT RATIO
SUPPLY GRILLE
SQUARE FOOT
REVOLUTIONS PER MINUTE
PROPOSED REFRIGERANT PIPING ROUTING
RELIEF HOOD / PENTHOUSE
REHEAT COIL
RETURN GRILLE
ROOM
RECIRCULAT(E), (OR), (ING)
RETURN AIR TEMPERATURE (°F)
RETURN FAN
THERMAL RESISTANCE
REFRIGERANT NUMBER
RETURN AIR
POUNDS PER SQUARE INCH
POUNDS PER SQUARE INCH GAUGE
PRESSURE
PARTS PER MILLION
PREFABRICATED
HYDRONIC PROPELLER UNIT HEATER
PRESSURE DROP (IN WG, U.N.O.)
PACKAGE TERMINAL AIR CONDITIONING UNIT
PREHEAT COIL
PHASE
PNEUMATIC-ELECTRIC
BFW BOILER FEED WATER
CONV CONVECTOR
ENTERING AIR TEMPERATURE (°F)
CONDENSER WATER CHEMICAL FEED
EA
EAT
EC
DN
ELECTRICAL CONTRACTOR
EXHAUST AIR DUCT
DOWN
CWP
CWCF
DC
DCR
CP
CU
CV
CUH
CONDENSER WATER PUMP
DRY COOLER
DUCT COIL
CONTROL VALVE
CONDENSING UNIT
HYDRONIC CABINET UNIT HEATER
CIRCULATION PUMP
P
PBD
OFOI
OFCI
OBD
OA
OAT
N/A
NO
NTS
NIC
NC
CHILLED WATER RETURN
CHILLED WATER CHEMICAL FEED
BRITISH THERMAL UNIT PER HOUR
CO
CONN
CHWR
CFM
CH
CHCF
CHP
CONNECTION
CLEANOUT
CHILLED WATER PUMP
CUBIC FEET PER MINUTE
CHILLER
CD
BTUH
CAV
BHP
BFWP
BOD
BOP
BLDG
CONSTANT AIR VOLUME
CONDENSATE DRAIN
BOTTOM OF PIPING
BOTTOM OF DUCT
BRAKE HORSEPOWER
BOILER FEED WATER PUMP
BUILDING
MECH
MD
MCC
MC
MBH
MAT
LWT
LPS
LP
LEC
LD
AIR CURTAIN
BBD
BFC
BDD
ARU
AS
APD
BOILER BLOW DOWN
BACKDRAFT DAMPER
BELOW FINISHED CEILING
AIR PRESSURE DROP (IN WG)
AIR ROTATION UNIT
AIR SEPARATOR
ADJ
AFF
AHU
ALT
AFM
AC
AAV
ADJUSTABLE
AIR FLOW MEASURING
ABOVE FINISHED FLOOR
AIR HANDLING UNIT
ALTERNATE
AUTOMATIC AIR VENT
LBS
LAT
KW
KEC
IN
INSUL
INT
IB
ID
HHWS
HZ
VARIABLE FREQUENCY DRIVE
OWNER FURNISHED / CONTRACTOR INSTALLED
OWNER FURNISHED / OWNER INSTALLED
OUTSIDE AIR TEMPERATURE (°F)
PARALLEL BLADE DAMPER
PUMP
OPPOSED BLADE DAMPER
OUTSIDE AIR
NOT APPLICABLE
NORMALLY CLOSED
NORMALLY OPEN
NOT TO SCALE
NOT IN CONTRACT
ZN
WTR
WSHP
ZONE
WATER SOURCE HEAT PUMP
WATER
MIXED AIR TEMPERATURE (°F)
THOUSANDS OF BTU PER HOUR
MOTOR CONTROL CENTER
MOTORIZED DAMPER
MECHANICAL
MECHANICAL CONTRACTOR
MAKEUP AIR UNIT
LOW PRESSURE STEAM
LEAVING WATER TEMPERATURE (°F)
LABORATORY EQUIPMENT CONTRACTOR
LIQUID PETROLEUM
LINEAR SLOT DIFFUSER
WG WATER GAUGE
VERT
VFD
VIF
VD
VAC
VAV
VA
VOLUME DAMPER
VERIFY IN FIELD
VERTICAL
VOLT AMPERE
VARIABLE AIR VOLUME (TERMINAL BOX)
VOLTS AC
TEMPERATURE CONTROL CONTRACTOR
TEMPERATURE CONTROL PANEL
TOTAL STATIC PRESSURE (IN WG, U.N.O.)
HEAT TRANSFER COEFFICIENT
LEAVING AIR TEMPERATURE (°F)
KITCHEN EQUIPMENT CONTRACTOR
POUNDS
KILOWATT
HEATING HOT WATER SUPPLY
INVERTED BUCKET STEAM TRAP
INCH / INCHES
INSULAT(E), (ED), (ION)
INTERIOR
FREQUENCY (MEGAHERTZ)
INSIDE DIAMETER
U
TYP.
TSTAT
TSP
THERMOSTAT
TYPICAL
TC
TOA
TCC
TCP
TB
TEMPERATURE CONTROL
TEMPERED OUTDOOR AIR
TERMINAL BOX
CWR CONDENSER WATER RETURN
CWS CONDENSER WATER SUPPLY
COP COEFFICIENT OF PERFORMANCE
CHILLED WATER SUPPLYCHWS
EER ENERGY EFFICIENCY RATIO
SEER SEASONAL ENERGY EFFICIENCY RATIO
HTR HEATER
MAU
VRF VARIABLE REFRIGERANT FLOW
BRANCH SELECTOR BOXBSB
ABBREVIATIONS
C COMMON
LPC LOW PRESSURE CONDENSATE
MPC MEDIUM PRESSURE CONDENSATE
MPS MEDIUM PRESSURE STEAM
HPS HIGH PRESSURE STEAM
HPC HIGH PRESSURE CONDENSATE
GMU GLYCOL MAKEUP UNIT
ACCESS DOORAD
ARCH ARCHITECT(URAL)
B BOILER
BUFFER TANKBT
CRAC COMPUTER ROOM AIR CONDITIONER
CSF CHEMICAL SHOT FEEDER
CSP CONDENSATE PUMP
CT COOLING TOWER
EC EGG CRATE
ECUH ELECTRIC CABINET UNIT HEATER
FPB FAN POWERED TERMINAL BOX
EPUH ELECTRIC PROPELLER UNIT HEATER
EQUIP EQUIPMENT
IH INTAKE HOOD / PENTHOUSE
IRH INFRARED TUBE RADIANT HEATERS
RCP RADIANT CEILING PANEL
RH RELATIVE HUMIDITY
RTU PACKAGED ROOFTOP (OR ON GRADE) UNIT
RWP RADIANT WALL PANEL
SAF SUPPLY AIR FAN
SAT SUPPLY AIR TEMPERATURE (°F)
TA TRANSFER AIR
VDC VOLTS DC
WPD WATER PRESSURE DROP
M-301
M-501
SECTION REFERENCE
DETAIL REFERENCE
DRAWING NOTATIONS
NOTE:
ALL SYMBOLS AND ABBREVIATIONS
MAY NOT BE USED FOR THIS PROJECT
NEW TO EXISTING
DEMO TO THIS POINT
EQUIPMENT TAG - (SEE SCHEDULE SHEETS)
DIFFUSER, REGISTER, GRILLE TAG - (SEE
SCHEDULE SHEETS)
SD24-12
XXX-1
CFM
MARK
DUCTWORK SYMBOLS
MANUAL VOLUME DAMPER
SHOETAP (OR 45° ENTRY) FITTING
BELLMOUTH FITTING
45° LATERAL FITTING
90° TEE FITTING
SHOETAP WITH SQUARE TO ROUND TRANSITION
DUCT TRANSITION
CONICAL FITTING
90° ELBOW WITH TURNING VANES
STANDARD RADIUS ELBOW, CENTER RADIUS
INSULATED FLEXIBLE DUCTWORK
OFFSET IN DUCTWORK (R = RISE D = DROP)
RECTANGULAR DUCTWORK
ROUND SPIRAL DUCTWORK
OVAL DUCTWORK
DROP IN DUCTWORK (RETURN, ETC.)
RISE IN DUCTWORK (RETURN, ETC.)
RISE IN DUCTWORK (SUPPLY ONLY)
DROP IN DUCTWORK (SUPPLY ONLY)
1-1/2 TIMES WIDTH OF DUCT
12"x8"ϴ
12"Ø
12"x8"
R D
BLADE DAMPER PBD = PARALLEL BLADE DAMPER
DUCT-MOUNTED REHEAT COIL (HYDRONIC)
INTERNALLY INSULATED DUCTWORK
ACCESS DOOR
MOTORIZED DAMPER
BDD = BACKDRAFT DAMPER OBD = OPPOSED
20° 30°
M
AD
FSD
FD-(A/B) = FIRE DAMPER (TYPE A OR TYPE B)
FSD = FIRE/SMOKE DAMPER
SD = SMOKE DAMPER
BDD
SD
FD
AIR FLOW
DROP IN DUCTWORK (EXHAUST)
RISE IN DUCTWORK (EXHAUST)
DUCTWORK SYSTEMS
EXHAUST AIR
TEMPERED OUTDOOR AIR
KITCHEN EXHAUST AIR
OUTSIDE AIR
RELIEF AIR
RETURN AIR
SUPPLY AIR
TRANSFER AIR
EA
TOA
KEA
OA
RLA
RA
SA
TA
C
EQUIPMENT SYMBOLS
SUPPLY DIFFUSER W/TYPE AND CFM
(ONE-WAY SIDE TYPE)
LINEAR DIFFUSER W/TYPE AND CFM
(TWO-WAY SIDE TYPE)
SUPPLY DIFFUSER W/TYPE AND CFM
(THREE-WAY TYPE)
RETURN GRILLE W/ TYPE AND CFM
SUPPLY DIFFUSER W/TYPE AND CFM
(FOUR-WAY TYPE)
SUPPLY DIFFUSER W/TYPE AND CFM
(TWO-WAY SIDE TYPE)
ROOF-MOUNTED EXHAUST FAN
CARBON DIOXIDE SENSOR
ON ROOF
EXHAUST GRILLE W/ TYPE AND CFM
H HUMIDITY SENSOR
T THERMOSTAT
CONDENSATE DRAIN
HYDRONIC RETURN
HYDRONIC SUPPLY
HEATING HOT WATER RETURN
HEATING HOT WATER SUPPLY
PROPOSED REFRIGERANT ROUTING
CD
HR
HS
HHWR
HHWS
PIPING SYSTEMS
R
F&T
GENERAL DUTY VALVES & FITTINGS
EXPANSION LOOP (SIZE INDICATED
ON DRAWINGS)
CONCENTRIC REDUCER
ECCENTRIC REDUCER
PRESSURE REDUCING VALVE
STEAM TRAP W/DESIGNATION
GAS COCK
PETE'S PLUG
PIPE EXPANSION JOINT
FLEXIBLE PIPING CONNECTOR
Y-STRAINER W/BLOWDOWN
VALVE & CAP
PIPE ANCHORS
PIPE GUIDES
THERMOMETER WELL
AUTOMATIC AIR VENT
GAUGE CONNECTION(S) & WELL
THERMOMETER & WELL
MANUAL AIR VENT
AUTOMATIC BALANCING VALVE
TWO-WAY CONTROL VALVE
THREE-WAY CONTROL VALVE
UNION
MANUAL BALANCING VALVE
VALVE IN RISER
ANGLE VALVE
PLUG VALVE
TRIPLE DUTY VALVE
PRESSURE REGULATING VALVE
BUTTERFLY VALVE
RELIEF VALVE
VALVE - SEE SPECIFICATIONS
FOR VALVE TYPE
PIPE CONTINUED ON ANOTHER
DRAWING
CHECK VALVE
CAPPED PIPE
RISE IN PIPING
DROP IN PIPING
GATE VALVE
BALL VALVE
1. THESE GENERAL NOTES APPLY TO M-SERIES DRAWINGS. ADDITIONAL GENERAL NOTES
SPECIFIC TO A PARTICULAR DRAWING ARE NOTED ON THOSE SHEETS.
2. IT IS THE INTENT OF THESE DOCUMENTS TO PROVIDE MECHANICAL SYSTEMS THAT ARE FULLY
FUNCTIONAL. PROVIDE ALL ITEMS SPECIFIED AND REQUIRED FOR COMPLETE OPERATIONAL
SYSTEMS.
3. ON MECHANICAL "M" SERIES DRAWINGS, DARK LINE ITEMS INDICATE NEW WORK. LIGHT LINE
ITEMS ARE ITEMS THAT SHALL REMAIN.
4. THESE DRAWINGS INDICATE REQUIRED SIZE AND POINTS OF TERMINATION FOR PIPING,
DUCTWORK, CONDUIT, ETC. THE EQUIPMENT SHOWN ILLUSTRATES SUGGESTED ROUTING,
BUT ALL NECESSARY OFFSETS MAY NOT BE SHOWN. DIVISION 23 SHALL INSTALL HIS WORK IN
A MANNER THAT WILL CONFORM WITH THE STRUCTURE. DIVISION 23 SHALL AVOID
OBSTRUCTIONS, PRESERVE HEADROOM AND MAINTAIN MAXIMUM CLEARANCE WITHOUT
FURTHER INSTRUCTION FROM THE ARCHITECT/ENGINEER OR ADDITIONAL COST TO THE
OWNER.
5. ALL DUCTWORK, PIPING, AND VALVES SHALL BE CONCEALED ABOVE CEILING AND WITHIN
WALLS IN FINISHED AREAS UNLESS OTHERWISE INDICATED.
6. ALL VALVES, ETC. SHALL BE INSTALLED ALLOWING EASY ACCESS BETWEEN LIGHT FIXTURES AND NO HIGHER THAN 12" TO 24" ABOVE THE CEILING. PROVIDE FITTINGS IN DUCTWORK AND
PIPING AS REQUIRED SO THAT NO PIPING REMAINS TIGHT TO ROOF STRUCTURE. PROVIDE
ACCESS PANELS AS REQUIRED. AREA ADJACENT TO THE ACCESS PANELS SHALL BE CLEAR
OF ANY OBSTRUCTIONS. PROVIDE EXTENDED VALVE HANDLES FOR INSULATED PIPING.
7. DIVISION 23 SHALL BE GUIDED BY THE ARCHITECT/ENGINEER'S REFLECTED CEILING PLAN FOR
LOCATION OF DIFFUSERS, REGISTERS, GRILLES SHOWN OR COVERED BY THESE PLANS.
RETURN GRILLES SHALL NOT ALIGN WITH SUPPLY AIR THROW.
8. CONTRACTOR SHALL COORDINATE EXACT LOCATION OF ALL GRILLES, REGISTERS AND
DIFFUSERS IN CEILINGS WITH THE CEILING SYSTEM AND LIGHT FIXTURES. PROVIDE FLEXIBLE
DUCT UPSTREAM OF EACH DIFFUSER WHERE SHOWN.
9. ARROWS ON THE HEATING HOT WATER MAINS INDICATE THE DIRECTION OF FLOW. PITCH
MAINS UPWARD A MINIMUM OF 1" PER 60' IN THE DIRECTION OF FLOW. ARROWS ON STEAM
AND CONDENSATE PIPING AND DRAIN LINE INDICATE THE DOWNWARD PITCH OF THE PIPING.
10. INSTALL AIR VENTS AT ALL HIGH POINTS AND DRAINS AT ALL LOW POINTS OF WATER PIPING
SYSTEMS. DRAINS TO HAVE HOSE END THREADS WITH CLEARANCE TO ATTACH HOSE.
11. PIPING BRANCHES TO EQUIPMENT SHALL HAVE SAME SIZE VALVES AND FITTINGS AS THAT OF
THE LINE SIZE WITH THE EXCEPTION OF THE TEMPERATURE CONTROL VALVES.
12. PIPE "SWING" CONNECTIONS WITH UNIONS OR FLANGES SHALL BE MADE EXTERNAL TO COILS
OR A TUBE BUNDLE TO FACILITATE REMOVAL OF THAT ITEM WITHOUT DISTURBING THE
BRANCH VALVES AND/OR PIPING.
13. DUCT AND PIPING PENETRATING FLOOR SLABS AND/OR WALLS SHALL BE SEALED WITH
ACOUSTIC SEALANT. IF THE FLOOR OR WALL IS FIRE RATED PROVIDE THE FIRE STOPPING OR
FIRE DAMPER TO MAINTAIN THE FIRE RATING.
14. ALL RECTANGULAR SHEET METAL DUCT SIZES ARE INSIDE DIMENSIONS. ALL ROUND DUCT
SIZES SHOWN ARE INSIDE DIAMETERS. ALLOWANCE FOR ACOUSTICAL LINER WHERE
INDICATED ON DRAWINGS MUST BE ADDED TO OBTAIN OUTSIDE SHEET METAL DIMENSION.
15. ALL WALL THERMOSTATS, TEMPERATURE SENSORS, AND/OR HUMIDISTATS SHALL BE
APPROXIMATELY 46" ABOVE FINISHED FLOOR TO CENTER AND LINED UP HORIZONTALLY WITH
LIGHT SWITCHES UNLESS OTHERWISE NOTED OR DIRECTED BY THE ARCHITECT/ENGINEER.
16. DIVISION 23 CONTRACTOR SHALL BE RESPONSIBLE FOR HIS RESPECTIVE WORK FOR
REPAIRING AND PATCHING TO MATCH EXISTING SURFACES, SIDEWALKS, STREETS, FLOORS,
WALLS, ROOFS, CEILING AND PAVEMENT. CONTRACTOR SHALL INCLUDE IN BID PROPOSAL ALL
COSTS FOR CUTTING AND PATCHING REQUIRED TO INSTALL NEW OR REMOVE EXISTING
WORK, EQUIPMENT, OR SYSTEMS.
17. DIVISION 23 CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING ALL OF HIS WORK TO
BE INSTALLED WITH ANY AND ALL OTHER CONTRACTORS TO BE AFFECTED BY SUCH WORK,
PRIOR TO ORDERING ANY OF THE EQUIPMENT. THIS SHALL INCLUDE BUT NOT LIMITED TO
ELECTRICAL CHARACTERISTICS, CONNECTIONS REQUIRED, PHYSICAL SIZE, COLOR AND FIT.
ALSO REFER TO SPECIFICATIONS.
18. ALL EQUIPMENT SHALL BE OF, AND CONSIST OF, AT LEAST MINIMUM SIZES SELECTED, AND
SHALL PERFORM TO OR SURPASS THE MINIMUM REQUIREMENTS, SCHEDULES, NOTED AND
SPECIFIED.
19. COORDINATE INSTALLATION OF NEW WORK WITH ALL OTHER TRADES AND EXISTING
CONDITIONS AS REQUIRED FOR A COMPLETE AND OPERABLE HVAC SYSTEM. CLEARANCES
ABOVE CEILINGS ARE EXTREMELY TIGHT IN CERTAIN AREAS. RELOCATE PIPING, ELECTRIC
CONDUIT, STRUCTURAL BRACING, ETC., AS REQUIRED FOR A COMPLETE INSTALLATION OF
HVAC WORK. COORDINATE ROUTING OF NEW DUCTWORK ABOVE CEILINGS WITH EXISTING
ELECTRIC CABLE TRAY. M.C. TO COORDINATE ALL DUCTWORK ROUTING AND DUCTWORK
ELEVATIONS WITH STRUCTURAL STEEL SUPPORTS FOR FOLDING WALLS. REFERENCE
STRUCTURAL DRAWINGS FOR SIZE AND LOCATIONS OF STEEL. FIELD VERIFY ALL EXISTING
CONDITIONS.
20. CONTRACTOR SHALL COORDINATE EXACT LOCATION OF ALL VAV REHEAT BOXES AND
DUCTWORK WITH THE CEILING SYSTEM AND LIGHT FIXTURES. FIELD VERIFY EXISTING CEILING
SYSTEMS AND LOCATION OF EXISTING LIGHT FIXTURES. ALLOW REQUIRED CLEARANCES FOR
SERVICE TO BOX AND CONTROLS.
21. CONTRACTOR SHALL RELOCATE EXISTING LIGHT FIXTURE AND CEILING GRID SUPPORT
HANGERS AS REQUIRED FOR INSTALLATION OF NEW VAV REHEAT BOXES, DUCTWORK AND
PIPING.
22. PROVIDE VOLUME DAMPERS IN ALL SUPPLY AIR BRANCH DUCTWORK AS REQUIRED TO
BALANCE EACH SYSTEM. ALL VOLUME DAMPERS LOCATED ABOVE DRYWALL CEILINGS SHALL
BE CABLE OPERATED WITH REMOTE REGULATOR LIKE YOUNG REGULATOR. FIELD VERIFY
EXISTING CEILINGS FOR DRYWALL CEILINGS. COORDINATE LOCATION OF ALL DAMPERS WITH
AIR BALANCE CONTRACTOR. IN HARD CEILINGS PROVIDE VOLUME DAMPER BEHIND THE
GRILLE, REGISTER, OR DIFFUSER.
23. PROVIDE 45°/90° FITTING WITH VOLUME DAMPER LIKE FLEXMASTER MODEL STO AT ALL
SUPPLY AIR AND PRIMARY AIR BRANCH DUCTWORK TAKEOFFS.
24. CONTRACTOR SHALL REVIEW RETURN AIR PATH BACK TO ALL HVAC EQUIPMENT. PROVIDE
RETURN AIR OPENINGS AND/OR JUMPER DUCTS IN WALLS ABOVE THE CEILING WHERE
REQUIRED. COORDINATE WITH GENERAL TRADES. VELOCITY THRU R.A. OPENINGS SHALL NOT
EXCEED 500 FPM. FIELD VERIFY LOCATION OF EXISTING WALLS EXTENDING TO DECK.
25. ALL TRANSFER AIR DUCTS TO BE INTERNALLY INSULATED TO DETER NOISE TRANSFER. SIZE
SHOWN ON PLANS INDICATES ACTUAL FREE AREA.
GENERAL NOTES
26. ALL NEW PIPING AND DUCTWORK CROSSING THRU EXISTING CORRIDOR AND/OR CLASSROOM
WALLS TO DECK; CUT WALLS AS REQUIRED. COORDINATE ALL OPENINGS THROUGH EXISTING
WALL CONSTRUCTION WITH GENERAL TRADES. SEAL AROUND DUCTWORK AND PIPING TO
HELP REDUCE THE TRANSFER OF NOISE BETWEEN CLASSROOMS. FIELD VERIFY ALL EXISTING
CONDITIONS PRIOR TO SUBMITTING OF BID.
27. ROUND DUCT SIZE TO BE THE SAME SIZE AS THE DIFFUSER NECK; UNLESS OTHERWISE
NOTED. MAXIMUM LENGTH OF FLEXIBLE DUCTWORK CONNECTED TO A DIFFUSER SHALL BE
5'-0".
28. ALL DUCTWORK CONSTRUCTION SHALL BE FABRICATED SHEET METAL & BUILT IN
ACCORDANCE WITH "SMACNA" STANDARDS.
29. ALL INSULATED DUCT SHALL BE EXTERNALLY INSULATED UNLESS NOTED OTHERWISE. SIZE
SHOWN INDICATES ACTUAL DUCT FREE AREA. SEE SPECIFICATION FOR ADDITIONAL
INSULATION REQUIREMENTS.
30. ALL NEW ROOF WORK TO BE IN ACCORDANCE WITH OWNER'S EXISTING ROOF WARRANTY.
31. ALL ROOF PENETRATIONS TO BE SEALED WATER TIGHT. PACK VOID BETWEEN DUCT
PENETRATING ROOF AND STRUCTURE WITH FIBERGLASS INSULATION AND CAULK WATER
TIGHT. FOR HIGH TEMPERATURE OR GREASE DUCTS UTILIZE MINERAL WOOL.
32. TEMPERATURE CONTROL CONTRACTOR SHALL PROVIDE ALL CONTROL WIRING COMPLETE
FOR THIS PROJECT. ALL WIRING (AND INTERLOCK WIRING) TO THERMOSTATS, SPACE
SENSORS, HUMIDISTATS, CARBON DIOXIDE MONITORS, ETC. ARE TO BE CONCEALED WITHIN
THE WALL.
33. ALL HARD 90° ELBOWS IN SUPPLY DUCTWORK ARE TO HAVE TURNING VANES PER
SPECIFICATION AIR DUCT ACCESSORIES.
34. REMOVE ALL WORK MADE OBSOLETE BY NEW CONSTRUCTION.
35. DEMOLITION OF EXISTING MECHANICAL EQUIPMENT TO INCLUDE ASSOCIATED PIPING AND
DUCTWORK NECESSARY FOR NEW EQUIPMENT INSTALLATION.
36. ALL EXISTING TO REMAIN AND NEW PVC PLUMBING VENT LINES LOCATED ABOVE CEILING IN
RETURN PLENUM ARE TO BE EXTERNALLY WRAPPED WITH FLAME AND SMOKE SPREAD RATED
INSULATION MATERIAL AS REQUIRED.
37. REFERENCE SECTION DIVISION 01 "SUMMARY" [MULTIPLE CONTRACT SUMMARY] FOR
CONSTRUCTION PHASING.
38. CONTRACTOR SHALL THOROUGHLY EXAMINE THE CONTRACT DOCUMENTS, INCLUDING THE
WORK OF OTHER CONTRACTORS PRIOR TO SUBMITTING A BID PROPOSAL.
39. ALL EXHAUST FANS, RELIEF VENTS, FLUES, AND PLUMBING VENTS TO BE INSTALLED A
MINIMUM OF 10 FT. FROM OUTDOOR AIR INTAKES.
40. CONTRACTOR SHALL CLEAN ALL OF HIS WORK INSIDE AND OUT. AIR DISTRIBUTION SYSTEMS
SHALL HAVE ALL DIRT AND FOREIGN MATERIAL REMOVED FROM INSIDE AND OUTSIDE OF
DUCTS, PLENUMS, HOUSINGS, DEVICES, TERMINALS, ETC. AS INSTALLATION PROGRESSES,
PROTECT OPEN ENDS OF DUCTWORK AND INLETS AND OUTLETS OF EQUIPMENT AND DEVICES
DURING CONSTRUCTION. CLEAN ALL ACCESSIBLE PARTS OF DUCTWORK AND AIR PASSAGES
IN EQUIPMENT BEFORE FILTERS ARE INSTALLED OR REPLACED FOR SYSTEM BALANCING.
41. FURNISH AND INSTALL ACCEPTABLE CONCRETE INSERTS, ANCHORS, CLAMPS, BRACKETS,
HANGERS, STRUCTURAL MEMBERS (ANGLES, CHANNELS, ETC.) AND FRAMES, ETC., REQUIRED
FOR SUPPORTING ALL RESPECTIVE WORK. SUPPORTING DEVICES, ASSEMBLIES AND
ATTACHMENTS SHALL BE DESIGNED AND ARRANGED TO CARRY THE WEIGHT OF THE
SUPPORTED ITEMS INCLUDING HANGER AND CONTENTS WITHOUT TRANSMITTING VIBRATION
OR NOISE TO THE BUILDING CONSTRUCTION; DESIGNED, APPROPRIATE AND APPROVED FOR
THE PURPOSE USED; HAVE A NEAT AND FINISHED APPEARANCE AND COMPLEMENT THE
INSTALLATION; HAVE CORROSION PROTECTION SUITABLE FOR THE ATMOSPHERE WHERE
INSTALLED; ADEQUATELY AND SAFELY ATTACHED TO THE BUILDING STRUCTURE OR
STRUCTURAL MEMBERS. EXPOSED SUPPORTS SHALL BE PAINTED UNLESS OF NON-FERROUS
MATERIAL OR PROVIDED WITH PLATED (RUSTPROOF) FINISH.
42. PROVIDE NEC CLEARANCES AND SERVICE CLEARANCES FOR EQUIPMENT. COORDINATE
EQUIPMENT SERVICE ACCESS. CLEARANCES INDICATED ARE BASED UPON BEST AVAILABLE
INFORMATION. CONTRACTOR SHALL VERIFY PIPING, DUCTWORK, ETC., ROUTING PRIOR TO
SUBMITTING A BID PROPOSAL AND INCLUDE ANY SUCH COSTS AS REQUIRED TO INSTALL
WORK AS SHOWN AND INTENDED.
43. ELEVATOR EQUIPMENT ROOMS: DO NOT ROUTE ANY SYSTEMS THROUGH ELEVATOR
EQUIPMENT ROOMS. FOR SYSTEMS THAT SERVE ELEVATOR EQUIPMENT ROOMS, DO NOT
ROUTE OVER ELEVATOR EQUIPMENT OR ELECTRICAL COMPONENTS AND DO NOT HINDER
SERVICE ACCESS.
44. TELECOMMUNICATIONS ROOMS (MDF AND IDF): DO NOT ROUTE ANY SYSTEMS THROUGH
TELECOMMUNICATIONS ROOMS. FOR SYSTEMS THAT SERVE T-COMM ROOMS, DO NOT ROUTE
OVER EQUIPMENT OR ELECTRICAL COMPONENTS AND DO NOT HINDER SERVICE ACCESS.
45. ELECTRICAL EQUIPMENT ROOMS: DO NOT ROUTE ANY SYSTEMS THROUGH ELECTRIC ROOMS.
FOR SYSTEMS THAT SERVE ELECTRIC ROOMS, DO NOT ROUTE OVER EQUIPMENT, PANELS,
TRANSFORMERS, VFD’S, OR ELECTRICAL COMPONENTS AND DO NOT HINDER SERVICE
ACCESS.
46. EXISTING VALVES MADE INACCESSIBLE BY NEW DUCT AND/OR PIPING SHALL BE RELOCATED
AS REQUIRED FOR ACCESS.
47. DURING REMOVAL OF ITEMS, CAUTION SHALL BE USED TO PREVENT DAMAGE TO ANY
EQUIPMENT HAVING SALVAGE VALUE. ALL REUSABLE SALVAGED MATERIAL SHALL REMAIN
THE PROPERTY OF THE OWNER AND BE RETAINED FOR HIS INSPECTION. ONLY ITEMS SO
INSPECTED AND REJECTED BY THE OWNER SHALL BE DISPOSED OF BY THE CONTRACTOR.
ALL OTHER ITEMS SHALL BE TURNED OVER AND DEPOSITED AS DIRECTED BY THE OWNER.
48. CONTRACT DOCUMENTS CONSIST OF BOTH PROJECT MANUAL AND DRAWINGS AND BOTH ARE
MEANT TO BE COMPLEMENTARY - ANYTHING APPEARING ON EITHER MUST BE EXECUTED THE
SAME AS IF SHOWN ON BOTH.
49. VERIFY EXACT SIZE AND LOCATION OF ALL EXISTING PIPING AND DUCTWORK PRIOR TO
CONSTRUCTION OR BIDDING.
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:1
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
MECHANICAL SYMBOLS
AND ABBREVIATIONS
M-001
AJE
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M -0
M
E C
H A
N
IC
A L
S Y
M B
O L S
A N
D A
B B
R E
V
IA
T
IO
N S
J M
J
# Revision Date
T
T
T
T
A. DARK DASHED LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING,
AND/OR MECHANICAL ACCESSORIES DEMOLISHED COMPLETE. CONTRACTOR TO FIELD
VERIFY ACTUAL EXISTING CONDITIONS PRIOR TO BIDDING AND DEMOLITION. CONTRACTOR TO
INCLUDE ALL COST TO REMOVE ITEMS MADE OBSOLETE DUE TO NEW HVAC WORK.
B. CONTRACTOR GIVES OWNER FIRST RIGHTS OF REFUSAL ON ANY EXISTING EQUIPMENT THE
OWNER MAY WANT TO KEEP. IF OWNER DECIDES SAID ITEM IS TO BE REMOVED, THEN
CONTRACTOR IS TO REMOVE FROM PROJECT SITE AS REQUIRED.
C. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO DEMOLITION AND BIDDING.
D. VARIABLE REFRIGERANT FLOW (VRF) SYSTEM DEMOLITION: CAREFULLY VACUUM ALL
EXISTING REFRIGERANT AND RECOVER/RECLAIM PER EPA STANDARDS.
GENERAL DEMOLITION NOTES
EX. FCU-2
T-FCU-2
EX. FCU-1
T-FCU-1
EX. FCU-1
T-FCU-1
EX. VRF FCU
T-FCU
EX. FCU
EX. HRB-1
STORAGE
006A
PLANNING
RR
OFFICE
EMERGENCY OPERATIONS
RR
STAIR 1
ST-1-0
OFFICE
MDF
003A
DATA ROOM
SPLIT SYSTEM
SHALL REMAIN
OFFICE
CUSTODIAL
004A
1/2 HEIGHT WALL1/2 HEIGHT WALL
EX. CD TO MOP SINK
EX. 1" CD
E X
C D
EXISTING DOAS VENTILATION
AIR DUCTWORK
EXISTING EXHAUST
AIR DUCTWORK
EX. T-FCU
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:1
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
BASEMENT DEMOLITION
PLAN
MD100
AJE / VT
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M D
B
A S
E M
E N
T D
E M
O L
IT
IO
N
P L A
N
DEMOLITION COMBINED PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 REMOVE EXISTING VRF CEILING MOUNTED CASSETTE FAN COIL UNIT COMPLETELY.
2 REMOVE EXISTING VRF HEAT RECOVERY BOX AND ALL ASSOCIATED POWER AND/OR CONTROLS
WIRING, ALL REFRIGERANT PIPING, AND ALL HANGERS/SUPPORTS COMPLETELY. TYPICAL OF ALL
HRB.
3 REMOVE EXISTING VRF REFRIGERANT PIPING COMPLETETLY INCLUDING ALL HANGERS/SUPPORTS.
SINGLE LINE REPRESENTS ALL REFRIGERANT SUPPLY AND RETURN LINES.
4 REMOVE EXISTING VRF SYSTEM THERMOSTAT IN PREPARATION FOR NEW DDC THERMOSTAT. REFER
TO M-700 SERIES TEMPERATURE CONTROL DRAWINGS.
5 REMOVE EXISTING VRF OUTDOOR UNIT COMPLETELY.
6 REMOVE EXISTING VRF HIGH WALL MOUNTED FAN COIL UNIT COMPLETELY,
7 EXISTING HOUSEKEEPING PAD TO REMAIN.
8 REMOVE EXISTING PACKAGED DOAS-1 ROOFTOP AIR HANDLING UNIT AND ASSOCIATED ROOF CURB
IN PREPARATION FOR NEW WORK.
9 REMOVE EXISTING DUCTWORK TO POINT INDICATED AND CAP.
10 REMOVE EXISTING CONDENSATE DRAIN TO POINT INDICATED AND CAP. REMAINING DRAIN LINE
SHALL REMAIN IN SERVICE.
11 REMOVE EXISTING CONDENSATE DRAIN WHERE VISIBLE ABOVE ACCESSIBLE CEILING. CAP OPEN
ENDS.
12 REMOVE EXISTING VRF DUCTED FAN COIL UNIT COMPLETELY.
13 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
14 EQUIPMENT ON GRADE. REFER TO MD101.
15 EXISTING DUCT/PIPE DOWN TO FIRST FLOOR. REFER TO MD101.
16 EXISTING DUCT/PIPE UP TO SECOND FLOOR. REFER TO MD102.
17 EXISTING DUCT/PIPE DOWN TO BASEMENT. REFER TO MD100.
18 EXISTING DUCT UP TO ROOF TO EQUIPMENT AS INDICATED. REFER TO MDR101.
19 EXISTING DUCT/PIPE UP TO FIRST FLOOR. REFER TO MD101.
20 EXPAND EXTERIOR WALL OPENING AS REQUIRED FOR NEW DUCTWORK.
1/4" = 1'-0" 2A
BASEMENT DEMOLITION ENLARGED PLAN
J M
J
T T
T
T
T
T
M
M
T
A. DARK DASHED LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING,
AND/OR MECHANICAL ACCESSORIES DEMOLISHED COMPLETE. CONTRACTOR TO FIELD
VERIFY ACTUAL EXISTING CONDITIONS PRIOR TO BIDDING AND DEMOLITION. CONTRACTOR TO
INCLUDE ALL COST TO REMOVE ITEMS MADE OBSOLETE DUE TO NEW HVAC WORK.
B. CONTRACTOR GIVES OWNER FIRST RIGHTS OF REFUSAL ON ANY EXISTING EQUIPMENT THE
OWNER MAY WANT TO KEEP. IF OWNER DECIDES SAID ITEM IS TO BE REMOVED, THEN
CONTRACTOR IS TO REMOVE FROM PROJECT SITE AS REQUIRED.
C. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO DEMOLITION AND BIDDING.
D. VARIABLE REFRIGERANT FLOW (VRF) SYSTEM DEMOLITION: CAREFULLY VACUUM ALL
EXISTING REFRIGERANT AND RECOVER/RECLAIM PER EPA STANDARDS.
GENERAL DEMOLITION NOTES
EX. FCU-4
EX. FCU-4
EX. HRB-1
EX. FCU-4T-FCU-1
T-FCU-4
EX. FCU-4
EX. HRB-1
T-FCU-4
T-FCU-5
EX. FCU-5
EX. HRB-1
EX. FCU-3
EX. EH-2
EX. EH-3
EX. EH-3
EX. EH-3
EX. EH-1
EX. EH-1
EX. EF-4
EX. EF-2
EX. RH
T-FCU-4
EX. EH-1
EX. EH-1
EX. FCU-4
ELEC
115 TOOL ROOM
APPARATUS BAY
CUSTODIAL
RR
RISER
EMS STORAGE
AIR COMPRESSOR
STAIR 2.1
ST 2-1
VESTIBULE
OFFICE / WATCHROOM
OFFICE STORAGE
CAPTAIN'S OFFICE
STAIR 1
ST 1-1
STOR.
FITNESS ROOM
GEAR ROOM
ADA RR
RR
CORRIDOR
EX. SSCU-TECH
EX. HP-1B
EX. HP-1C
EX. HP-1A
EX. RH-1
EX. RH-2
EX. RH-3
EX. RH-4
CD DOWN TO
LAV DRAIN
EF-3
EF-1
EX. GFUH
T- EH-2
T-GFUH
PATCH
14"x8" SA 8"x14" EA
1" CD
CD
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:1
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
FIRST FLOOR
DEMOLITION PLAN
MD101
AJE / VT
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M D
F
IR
S
T F
L O
O R
D E
M O
L
IT
IO
N
P L A
N
DEMOLITION COMBINED PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 REMOVE EXISTING VRF CEILING MOUNTED CASSETTE FAN COIL UNIT COMPLETELY.
2 REMOVE EXISTING VRF HEAT RECOVERY BOX AND ALL ASSOCIATED POWER AND/OR CONTROLS
WIRING, ALL REFRIGERANT PIPING, AND ALL HANGERS/SUPPORTS COMPLETELY. TYPICAL OF ALL
HRB.
3 REMOVE EXISTING VRF REFRIGERANT PIPING COMPLETETLY INCLUDING ALL HANGERS/SUPPORTS.
SINGLE LINE REPRESENTS ALL REFRIGERANT SUPPLY AND RETURN LINES.
4 REMOVE EXISTING VRF SYSTEM THERMOSTAT IN PREPARATION FOR NEW DDC THERMOSTAT. REFER
TO M-700 SERIES TEMPERATURE CONTROL DRAWINGS.
5 REMOVE EXISTING VRF OUTDOOR UNIT COMPLETELY.
6 REMOVE EXISTING VRF HIGH WALL MOUNTED FAN COIL UNIT COMPLETELY,
7 EXISTING HOUSEKEEPING PAD TO REMAIN.
8 REMOVE EXISTING PACKAGED DOAS-1 ROOFTOP AIR HANDLING UNIT AND ASSOCIATED ROOF CURB
IN PREPARATION FOR NEW WORK.
9 REMOVE EXISTING DUCTWORK TO POINT INDICATED AND CAP.
10 REMOVE EXISTING CONDENSATE DRAIN TO POINT INDICATED AND CAP. REMAINING DRAIN LINE
SHALL REMAIN IN SERVICE.
11 REMOVE EXISTING CONDENSATE DRAIN WHERE VISIBLE ABOVE ACCESSIBLE CEILING. CAP OPEN
ENDS.
12 REMOVE EXISTING VRF DUCTED FAN COIL UNIT COMPLETELY.
13 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
14 EQUIPMENT ON GRADE. REFER TO MD101.
15 EXISTING DUCT/PIPE DOWN TO FIRST FLOOR. REFER TO MD101.
16 EXISTING DUCT/PIPE UP TO SECOND FLOOR. REFER TO MD102.
17 EXISTING DUCT/PIPE DOWN TO BASEMENT. REFER TO MD100.
18 EXISTING DUCT UP TO ROOF TO EQUIPMENT AS INDICATED. REFER TO MDR101.
19 EXISTING DUCT/PIPE UP TO FIRST FLOOR. REFER TO MD101.
20 EXPAND EXTERIOR WALL OPENING AS REQUIRED FOR NEW DUCTWORK.
1/4" = 1'-0" 2A
FIRST FLOOR DEMOLITION ENLARGED PLAN
T
T
T
T
TTTT
T
T T
A. DARK DASHED LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING,
AND/OR MECHANICAL ACCESSORIES DEMOLISHED COMPLETE. CONTRACTOR TO FIELD
VERIFY ACTUAL EXISTING CONDITIONS PRIOR TO BIDDING AND DEMOLITION. CONTRACTOR TO
INCLUDE ALL COST TO REMOVE ITEMS MADE OBSOLETE DUE TO NEW HVAC WORK.
B. CONTRACTOR GIVES OWNER FIRST RIGHTS OF REFUSAL ON ANY EXISTING EQUIPMENT THE
OWNER MAY WANT TO KEEP. IF OWNER DECIDES SAID ITEM IS TO BE REMOVED, THEN
CONTRACTOR IS TO REMOVE FROM PROJECT SITE AS REQUIRED.
C. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO DEMOLITION AND BIDDING.
D. VARIABLE REFRIGERANT FLOW (VRF) SYSTEM DEMOLITION: CAREFULLY VACUUM ALL
EXISTING REFRIGERANT AND RECOVER/RECLAIM PER EPA STANDARDS.
GENERAL DEMOLITION NOTES
EX. DOAS-1
EX. FCU-5
T-FCU-5
EX. HBR-1
T-FCU-6
EX. FCU-6
EX. FCU-1
T-FCU-1
EX. FCU-1
T-FCU-1
T-FCU-1
EX. FCU-1
EX. HRB-1
EX. FCU-1
T-FCU-1 T-FCU-1
EX. FCU-1
T-FCU-1
EX. FCU-1
EX. FCU-1
T-FCU-1
EX. FCU-1
T-FCU-1
EX. HRB-1
EX. HRB-1
EX. FCU-4
T-FCU-4
T-FCU-4
T-FCU-4
EX. FCU-4 EX. FCU-4
EX. FCU-4
EX. MAU-1
EX. EF-3
EX. EF-1
BATH
213B
LAUNDRY
CORRIDOR
LOCKER
DORM
214A
BATH
214B
BATH
215BDORM
215A
LOCKER
STORAGE
MECH.
SUPPLY CLOSET
KITCHEN
DAY ROOM
DINING
DORM
220A
PANTRY
PANTRY
PANTRY
JANITOR
LOCKER
BATH
220B
LOCKER
BATH
219B
DORM
219A
DORM
218A
LOCKER
DORM
217A
BATH
217B
LOCKER
BATH
216B
LOCKER
DORM
216A
STAIR 2
ST 2-2
BATH
218B
4 4
1 1
KITCHEN
HOOD
GEAR ROOM EXHAUST
APPARATUS BAY EXHAUST
KITCHEN HOOD MAKEUP AIR UNIT
EX.14"x10" OA
EX.24"x10" SA EX.22"x10" EA
EX.22"x10" EA EX.24"x10" SA
EX.14"x8" SA EX.14"x8" EA
EXISTING DOAS VENTILATION
AIR DUCTWORK
EXISTING EXHAUST
AIR DUCTWORK
KEF-1
EX.22"x10" EA
EX.24"x10" SA
EX.6"Ø SA
TYPICAL
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:1
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
SECOND FLOOR
DEMOLITION PLAN
MD102
AJE / VT
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M D
S
E C
O N
D F
L O
O R
D E
M O
L
IT
IO
N
P L A
N
1/4" = 1'-0" 2A
SECOND FLOOR DEMOLITION ENLARGED PLAN
DEMOLITION COMBINED PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 REMOVE EXISTING VRF CEILING MOUNTED CASSETTE FAN COIL UNIT COMPLETELY.
2 REMOVE EXISTING VRF HEAT RECOVERY BOX AND ALL ASSOCIATED POWER AND/OR CONTROLS
WIRING, ALL REFRIGERANT PIPING, AND ALL HANGERS/SUPPORTS COMPLETELY. TYPICAL OF ALL
HRB.
3 REMOVE EXISTING VRF REFRIGERANT PIPING COMPLETETLY INCLUDING ALL HANGERS/SUPPORTS.
SINGLE LINE REPRESENTS ALL REFRIGERANT SUPPLY AND RETURN LINES.
4 REMOVE EXISTING VRF SYSTEM THERMOSTAT IN PREPARATION FOR NEW DDC THERMOSTAT. REFER
TO M-700 SERIES TEMPERATURE CONTROL DRAWINGS.
5 REMOVE EXISTING VRF OUTDOOR UNIT COMPLETELY.
6 REMOVE EXISTING VRF HIGH WALL MOUNTED FAN COIL UNIT COMPLETELY,
7 EXISTING HOUSEKEEPING PAD TO REMAIN.
8 REMOVE EXISTING PACKAGED DOAS-1 ROOFTOP AIR HANDLING UNIT AND ASSOCIATED ROOF CURB
IN PREPARATION FOR NEW WORK.
9 REMOVE EXISTING DUCTWORK TO POINT INDICATED AND CAP.
10 REMOVE EXISTING CONDENSATE DRAIN TO POINT INDICATED AND CAP. REMAINING DRAIN LINE
SHALL REMAIN IN SERVICE.
11 REMOVE EXISTING CONDENSATE DRAIN WHERE VISIBLE ABOVE ACCESSIBLE CEILING. CAP OPEN
ENDS.
12 REMOVE EXISTING VRF DUCTED FAN COIL UNIT COMPLETELY.
13 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
14 EQUIPMENT ON GRADE. REFER TO MD101.
15 EXISTING DUCT/PIPE DOWN TO FIRST FLOOR. REFER TO MD101.
16 EXISTING DUCT/PIPE UP TO SECOND FLOOR. REFER TO MD102.
17 EXISTING DUCT/PIPE DOWN TO BASEMENT. REFER TO MD100.
18 EXISTING DUCT UP TO ROOF TO EQUIPMENT AS INDICATED. REFER TO MDR101.
19 EXISTING DUCT/PIPE UP TO FIRST FLOOR. REFER TO MD101.
20 EXPAND EXTERIOR WALL OPENING AS REQUIRED FOR NEW DUCTWORK.
J M
J
EX. DOAS-1
EX. MAU-1
EX. EF-3
EX. EF-1
EX. KEF-1
EX. HP-1A
EX. SSCU-TECH
GEAR ROOM EXHAUST
APPARATUS BAY EXHAUST
EX. HP-1B
EX. HP-1C
EX.24"x10" SA EX.22"x10" EA
KITCHEN HOOD EXHAUST
KITCHEN HOOD MAKEUP AIR UNIT
A. DARK DASHED LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING,
AND/OR MECHANICAL ACCESSORIES DEMOLISHED COMPLETE. CONTRACTOR TO FIELD
VERIFY ACTUAL EXISTING CONDITIONS PRIOR TO BIDDING AND DEMOLITION. CONTRACTOR TO
INCLUDE ALL COST TO REMOVE ITEMS MADE OBSOLETE DUE TO NEW HVAC WORK.
B. CONTRACTOR GIVES OWNER FIRST RIGHTS OF REFUSAL ON ANY EXISTING EQUIPMENT THE
OWNER MAY WANT TO KEEP. IF OWNER DECIDES SAID ITEM IS TO BE REMOVED, THEN
CONTRACTOR IS TO REMOVE FROM PROJECT SITE AS REQUIRED.
C. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO DEMOLITION AND BIDDING.
D. VARIABLE REFRIGERANT FLOW (VRF) SYSTEM DEMOLITION: CAREFULLY VACUUM ALL
EXISTING REFRIGERANT AND RECOVER/RECLAIM PER EPA STANDARDS.
GENERAL DEMOLITION NOTES
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
ROOF DEMOLITION PLAN
MDR101
AJE / VT
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M D
R
R
O O
F D
E M
O L
IT
IO
N
P L A
N
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
ROOF DEMOLITION PLAN
MDR101
AJE / VT
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M D
R
R
O O
F D
E M
O L
IT
IO
N
P L A
N
1/4" = 1'-0" 2A
ROOF DEMOLITION ENLARGED PLAN
DEMOLITION COMBINED PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 REMOVE EXISTING VRF CEILING MOUNTED CASSETTE FAN COIL UNIT COMPLETELY.
2 REMOVE EXISTING VRF HEAT RECOVERY BOX AND ALL ASSOCIATED POWER AND/OR CONTROLS
WIRING, ALL REFRIGERANT PIPING, AND ALL HANGERS/SUPPORTS COMPLETELY. TYPICAL OF ALL
HRB.
3 REMOVE EXISTING VRF REFRIGERANT PIPING COMPLETETLY INCLUDING ALL HANGERS/SUPPORTS.
SINGLE LINE REPRESENTS ALL REFRIGERANT SUPPLY AND RETURN LINES.
4 REMOVE EXISTING VRF SYSTEM THERMOSTAT IN PREPARATION FOR NEW DDC THERMOSTAT. REFER
TO M-700 SERIES TEMPERATURE CONTROL DRAWINGS.
5 REMOVE EXISTING VRF OUTDOOR UNIT COMPLETELY.
6 REMOVE EXISTING VRF HIGH WALL MOUNTED FAN COIL UNIT COMPLETELY,
7 EXISTING HOUSEKEEPING PAD TO REMAIN.
8 REMOVE EXISTING PACKAGED DOAS-1 ROOFTOP AIR HANDLING UNIT AND ASSOCIATED ROOF CURB
IN PREPARATION FOR NEW WORK.
9 REMOVE EXISTING DUCTWORK TO POINT INDICATED AND CAP.
10 REMOVE EXISTING CONDENSATE DRAIN TO POINT INDICATED AND CAP. REMAINING DRAIN LINE
SHALL REMAIN IN SERVICE.
11 REMOVE EXISTING CONDENSATE DRAIN WHERE VISIBLE ABOVE ACCESSIBLE CEILING. CAP OPEN
ENDS.
12 REMOVE EXISTING VRF DUCTED FAN COIL UNIT COMPLETELY.
13 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
14 EQUIPMENT ON GRADE. REFER TO MD101.
15 EXISTING DUCT/PIPE DOWN TO FIRST FLOOR. REFER TO MD101.
16 EXISTING DUCT/PIPE UP TO SECOND FLOOR. REFER TO MD102.
17 EXISTING DUCT/PIPE DOWN TO BASEMENT. REFER TO MD100.
18 EXISTING DUCT UP TO ROOF TO EQUIPMENT AS INDICATED. REFER TO MDR101.
19 EXISTING DUCT/PIPE UP TO FIRST FLOOR. REFER TO MD101.
20 EXPAND EXTERIOR WALL OPENING AS REQUIRED FOR NEW DUCTWORK.
J M
J
# Revision Date# Revision Date
A. DARK LINES INDICATE NEW WORK.
B. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO BIDDING.
C. DUCTWORK SHALL BE EXTERNALLY INSULATED UNLESS SPECIFICALLY STATED TO BE
INTERNALLY LINED. REFER TO DUCTWORK INSULATION SPECIFICATIONS.
GENERAL HVAC NOTES
EX. FCU
STORAGE
006A
PLANNING
RR
OFFICE
EMERGENCY OPERATIONS
RR
STAIR 1
ST-1-0
OFFICE
MDF
003A
VAV-2-6
VAV-2-7
VAV-2-9
VAV-2-10
50 CFM
75 CFM
75 CFM
SD24-10
TYP. OF 3
SD24-8
SD24-8
SD24-8
SD24-8
SD24-6
SD24-6
8"Ø SA
1/2 HEIGHT WALL
LSR-4
LSR-4
LSR-4
LSR-4
20"x20" RA
"x
S A
"x
S A
12"Ø SA
16"x16" SA
16"x16"
EC24/12
EC24/12 EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
8"Ø SA
10"Ø SA
10"x6" SA
VAV-2-8
12"Ø SA
16"x16"
10"Ø SA
TYP. OF 3
10"Ø SA
TYP. OF 3
SS-1
8"Ø SA
8"Ø SA
10"Ø SA
"Ø
S A
"Ø
S A
6"Ø SA
12"x8"
"Ø
S A6 "Ø
S A
OFFICE
OFFICE
SD24-10
TYP. OF 3
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
BASEMENT HVAC PLAN
MH100
AJE / PWF
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M H
B A
S E
M E
N T
H V
A C
P L A
N
MECHANICAL HVAC PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-1. REFER TO M-701.
2 DUCT DROPS SHALL BE INTERNALLY LINED WITH 1" FIBROUS LINER.
3 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
4 COORDINATE WITH EXISTING STRUCTURAL BEAMS.
5 ROOM-TO-PLENUM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3C/M-502.
6 ROOM-TO-ROOM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3D/M-502.
7 RETURN DUCT STUBBED INTO PLENUM AND CAPPED WITH 1/2"X1/2" GALVANIZED MESH BIRD SCREEN.
8 EXPOSED DUCTWORK WITHIN APPARATUS BAY SHALL BE PAINTED BY DIVISION 9 TO MATCH
ADJACENT SYSTEMS.
9 PROVIDE REMOTE BALANCING DAMPER ACTUATOR LIKE YOUNGS REGULATOR AS REQUIRED TO
PROVIDE BALANCING CAPABILITIES ABOVE INACCESSIBLE CEILING. LOCATE REGULATOR CONTROL
WITHIN CEILING PLENUM IN AN ACCESSIBLE LOCATION.
10 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-2. REFER TO M-701.
11 DUCTWORK UP TO THE FIRST FLOOR. REFER TO MH101.
12 DUCTWORK UP TO THE ROOF AND SERVING ROOFTOP EQUIPMENT AS INDICATED. REFER TO MR101.
13 DUCTWORK DOWN TO THE BASEMENT. REFER TO MH100.
14 DUCTWORK UP TO THE SECOND FLOOR. REFER TO MH102.
15 DUCTWORK UP TO THE ROOF. REFER TO MR101.
16 DUCTWORK DOWN TO THE FIRST FLOOR. REFER TO MH101. REFER TO DETAIL 4A/M-502.
17 BOILER FLUE AND COMBUSTION AIR DUCTWORK SHALL BE SIZED PER MANUFACTURER'S
REQUIREMENTS.
18 EXPAND WALL OPENING VERTICALLY AS REQUIRED.
1/4" = 1'-0" 2A
BASEMENT HVAC ENLARGED PLAN
J M
J
J M
J
M
M
ELEC
TOOL ROOM
APPARATUS BAY
CUSTODIAL
RR
RISER
EMS STORAGE
AIR COMPRESSOR
STAIR 2.1
ST 2-1
VESTIBULE
OFFICE / WATCHROOM
OFFICE STORAGE
CAPTAIN'S OFFICE
STAIR 1
ST 1-1
STOR.
FITNESS ROOM
GEAR ROOM
ADA RR
RR
CORRIDOR
VAV-2-1
VAV-2-3
VAV-2-5
VAV-2-4
SD24-8
SD24-6
SD24-6
SD24-6
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
SD24-8
LS48-10-3S
VAV-2-2
6"Ø SA
6"Ø SA
"Ø
S A
UP TO EF-5
4E
MH101
80 CFM 80 CFM
EG24/24
1B
MP101
1C
MP101
BOILER FLUE
BOILER COMBUSTION
INTAKE THROUGH WALL
B-1
EX. GFUH
6"Ø EA
EX. EF-2
EX. EH-3
EX. EH-1
EX. EF-4
6"Ø EA
EX. EH-3
EX. EH-3
EX. EH-1
EX. EH-2
EX. RH-1 EX. RH-2
EX. RH-3
EX. RH-4
12"Ø SA
8"Ø SA
EG8/8
20"x20" RA
EC24/12
20"x20" RA
10"Ø SA 12"x12" SA
10"Ø SA
18"x12" RA
30"x30" RA
12"x10" EA
EC24/12
14"x14" RA
16"x16" EA
10"Ø SA
10"Ø SA
EC24/24
8"Ø SA
8"Ø SA
8"Ø SA
12"Ø SA
"x
S
A 10"Ø SA
10"Ø SA
10"Ø SA10"Ø SA
"x
S A
"x
S A
6"Ø
8"Ø SA
6"Ø SA
48"x14" RA
16"x12" SA
16"x12" SA
EX. SSCU-TECH
14"Ø SA
FIRE POLE
FIRE POLE
EX. GFUH FLUE
EF-3
EF-1
COORDINATE EXACT ROUTING
WITH EXISTING CONDITIONS.
RTU-2
EC24/24
EC24/24
VD
VD
38"x38" RLA
RH-112
2,900
CFM
2,800
CFM
2,300
CFM
"Ø
S A
20"x20" SA
"x
S A
"Ø
S A
16"x16" SA
VD
"x
R A
"x
E A
"Ø
S A
8"Ø EA
24"x14" RA
A. DARK LINES INDICATE NEW WORK.
B. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO BIDDING.
C. DUCTWORK SHALL BE EXTERNALLY INSULATED UNLESS SPECIFICALLY STATED TO BE
INTERNALLY LINED. REFER TO DUCTWORK INSULATION SPECIFICATIONS.
GENERAL HVAC NOTES
RTU-2RH-1
EF-5
SSCU-1
PIPE CURB
20"x20" RA
VAV-2-1
16"x16" SA
20"x20" SA16"x16" SA
16"x12" SA
20"x20" RA
30"x30" RA 48"x14" RA
36"x24" SA
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
FIRST FLOOR HVAC PLAN
MH101
AJE / PWF
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M H
F
IR
S
T F
L O
O R
H V
A C
P L A
N
1/4" = 1'-0" 2A
FIRST FLOOR HVAC ENLARGED PLAN
MECHANICAL HVAC PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-1. REFER TO M-701.
2 DUCT DROPS SHALL BE INTERNALLY LINED WITH 1" FIBROUS LINER.
3 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
4 COORDINATE WITH EXISTING STRUCTURAL BEAMS.
5 ROOM-TO-PLENUM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3C/M-502.
6 ROOM-TO-ROOM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3D/M-502.
7 RETURN DUCT STUBBED INTO PLENUM AND CAPPED WITH 1/2"X1/2" GALVANIZED MESH BIRD SCREEN.
8 EXPOSED DUCTWORK WITHIN APPARATUS BAY SHALL BE PAINTED BY DIVISION 9 TO MATCH
ADJACENT SYSTEMS.
9 PROVIDE REMOTE BALANCING DAMPER ACTUATOR LIKE YOUNGS REGULATOR AS REQUIRED TO
PROVIDE BALANCING CAPABILITIES ABOVE INACCESSIBLE CEILING. LOCATE REGULATOR CONTROL
WITHIN CEILING PLENUM IN AN ACCESSIBLE LOCATION.
10 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-2. REFER TO M-701.
11 DUCTWORK UP TO THE FIRST FLOOR. REFER TO MH101.
12 DUCTWORK UP TO THE ROOF AND SERVING ROOFTOP EQUIPMENT AS INDICATED. REFER TO MR101.
13 DUCTWORK DOWN TO THE BASEMENT. REFER TO MH100.
14 DUCTWORK UP TO THE SECOND FLOOR. REFER TO MH102.
15 DUCTWORK UP TO THE ROOF. REFER TO MR101.
16 DUCTWORK DOWN TO THE FIRST FLOOR. REFER TO MH101. REFER TO DETAIL 4A/M-502.
17 BOILER FLUE AND COMBUSTION AIR DUCTWORK SHALL BE SIZED PER MANUFACTURER'S
REQUIREMENTS.
18 EXPAND WALL OPENING VERTICALLY AS REQUIRED.
3/16" = 1'-0" 4E
NORTH/SOUTH SECTION - LEVEL 1
J M
J
1A
RTU-2 DUCTWORK ISOMETRIC
A. DARK LINES INDICATE NEW WORK.
B. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO BIDDING.
C. DUCTWORK SHALL BE EXTERNALLY INSULATED UNLESS SPECIFICALLY STATED TO BE
INTERNALLY LINED. REFER TO DUCTWORK INSULATION SPECIFICATIONS.
GENERAL HVAC NOTES
DORM
213A
BATH
213B
LOCKER
LAUNDRY
CORRIDOR
LOCKER
DORM
214A
BATH
214B
BATH
215B
DORM
215A
LOCKER
STORAGE
MECH.
SUPPLY CLOSET
KITCHEN
DAY ROOM
DINING
PANTRY
PANTRY
PANTRY
JANITOR
LOCKER
BATH
220B
LOCKER
219BATH
219B
DORM
219A
DORM
218A
LOCKER
DORM
217A
BATH
217B
LOCKER
BATH
216B
LOCKER
DORM
216A
STAIR 2
ST 2-2
BATH
218B
EX. MAU-1
EX. EF-3
VAV-1-8VAV-1-7VAV-1-6
VAV-1-5
VAV-1-4
VAV-1-3
VAV-1-2
VAV-1-1
VAV-2-11
VAV-2-12
VAV-1-9
SD24-10
75 CFM
75 CFM
75 CFM
75 CFM 75 CFM
25 CFM 25 CFM
75 CFM75 CFM
75 CFM
SD24-10
EC24/12
EC24/12
EC24/12
SD24-8
SD24-10
SD24-10
SD24-10
SD24-10
SD24-10
SD24-10
EC24/12
25 CFM
50 CFM
SD24-8
SD24-8
EC24/24
SD24-10
SD24-10
LS48-10-3S
LS48-10-3S
LS48-10-3S
LS48-10-3S
SD24-8
8"Ø SA8"Ø SA
8"Ø SA
8"Ø SA
10"Ø SA10"Ø SA
8"Ø SA
8"Ø SA
8"Ø SA
10"Ø SA
10"Ø SA 10"Ø SA
10"x10" SA
8"Ø SA
8"Ø SA
8"Ø SA
10"Ø SA
10"Ø SA
SD24-6
16"x10" SA
4E
MH101
EC24/12EC24/12EC24/12EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
EC24/12
10"Ø SA
EC24/12EC24/12
EC24/12EC24/12
EC24/12
EC24/12
EC24/12
EF-5
EX. EF-1
LOCATION OF STRUCTURAL BEAM
CAP1
RTU-2
24"x10" SA 22"x16" RA
16"x16" SA
RTU-1
8"Ø SA
8"Ø SA
6"Ø SA
4E
MR101
SSCU-1
"x
S A
"x
S A
"x
S A
14"x10" SA 10"x10" SA 10"Ø SA 8"Ø SA
16"x16" EA
EF-6
"x
R A
16"x14" SA
"Ø
S A
8"Ø
8"Ø SA
"Ø
S A
DORM
220A
14"x14" SA
12"Ø SA
EC24/24
38"x38" RLA
12 RH-2
RH-1
VD, TYP.
E X
.2 "x
E A
E X
.2 "x
E A
EX.22"x10" EA
EG8/8
EG8/8
6"Ø EA
6"Ø EA
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
SECOND FLOOR HVAC
PLAN
MH102
AJE / PWF
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M H
S
E C
O N
D F
L O
O R
H V
A C
P L A
N
MECHANICAL HVAC PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-1. REFER TO M-701.
2 DUCT DROPS SHALL BE INTERNALLY LINED WITH 1" FIBROUS LINER.
3 HVAC SYSTEM ON MEZZANINE. SHOWN ON FIRST FLOOR PLAN FOR REFERENCE.
4 COORDINATE WITH EXISTING STRUCTURAL BEAMS.
5 ROOM-TO-PLENUM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3C/M-502.
6 ROOM-TO-ROOM TRANSFER AIR ASSEMBLY WITH 12"X12", INTERNALLY LINED DUCTWORK WITH 1"
FIBROUS LINER, WITHOUT TURNING VANES. REFER TO DETAIL 3D/M-502.
7 RETURN DUCT STUBBED INTO PLENUM AND CAPPED WITH 1/2"X1/2" GALVANIZED MESH BIRD SCREEN.
8 EXPOSED DUCTWORK WITHIN APPARATUS BAY SHALL BE PAINTED BY DIVISION 9 TO MATCH
ADJACENT SYSTEMS.
9 PROVIDE REMOTE BALANCING DAMPER ACTUATOR LIKE YOUNGS REGULATOR AS REQUIRED TO
PROVIDE BALANCING CAPABILITIES ABOVE INACCESSIBLE CEILING. LOCATE REGULATOR CONTROL
WITHIN CEILING PLENUM IN AN ACCESSIBLE LOCATION.
10 APPROXIMATE LOCATION OF 2/3 DUCT PRESSURE SENSOR RTU-2. REFER TO M-701.
11 DUCTWORK UP TO THE FIRST FLOOR. REFER TO MH101.
12 DUCTWORK UP TO THE ROOF AND SERVING ROOFTOP EQUIPMENT AS INDICATED. REFER TO MR101.
13 DUCTWORK DOWN TO THE BASEMENT. REFER TO MH100.
14 DUCTWORK UP TO THE SECOND FLOOR. REFER TO MH102.
15 DUCTWORK UP TO THE ROOF. REFER TO MR101.
16 DUCTWORK DOWN TO THE FIRST FLOOR. REFER TO MH101. REFER TO DETAIL 4A/M-502.
17 BOILER FLUE AND COMBUSTION AIR DUCTWORK SHALL BE SIZED PER MANUFACTURER'S
REQUIREMENTS.
18 EXPAND WALL OPENING VERTICALLY AS REQUIRED.
1/4" = 1'-0" 2A
SECOND FLOOR HVAC ENLARGED PLAN
J M
J
T
T
T
T
C
T
T
A. DARK LINES INDICATE NEW WORK.
B. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO BIDDING.
GENERAL PIPING NOTES
EX. FCU
STORAGE
006A PLANNING
RR
OFFICE
EMERGENCY OPERATIONS
RR
STAIR 1
ST-1-0
OFFICE
MDF
003A
OFFICE
TECHNOLOGY/SERVER ROOM
BAS
EXISTING REFRIGERANT LINESET TO
TECHNOLOGY SERVER ROOM SPLIT
SYSTEM CONDENSING UNIT.
VAV-2-6
VAV-2-7
VAV-2-9
VAV-2-10
VAV-2-10
VAV-2-9
VAV-2-8
VAV-2-7
VAV-2-6
1/2 HEIGHT WALL
EX. CD TO MOP SINK
OFFICE
VAV-2-8
SS-1
SS-1
CUSTODIAL
004A
1 1/4" HHWS
1 1/4" HHWR
3/4"
3/4"
3/4"
1"
1"
3/4"
3/4"
3/4"
ISOLATION VALVES
EX. T-FCU
CO2 SENSOR
RTU-2
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:2
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
BASEMENT PIPING PLAN
MP100
AJE / PWF
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
R M
E L
F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
M P
B
A S
E M
E N
T P
IP
IN
G P
L A
N
MECHANICAL PIPING PLAN NOTES
REFER TO M-001 FOR GENERAL NOTES. NOT ALL NOTES APPLY TO EVERY SHEET.
# NOTE
1 NEW BUILDING AUTOMATION SYSTEM TEMPERATURE SENSOR. REFER TO M-700 SERIES DRAWINGS.
2 3/4" DRAIN DOWN LINES VALVED AND CAPPED WITH THREADED HOSE CONNECTION AT LOW POINT
OF HHW SYSTEM, USED FOR DRAIN DOWN OF THE SYSTEM.
3 FIRE SEAL ALL RATED WALL PENETRATIONS.
4 NEW SPLIT SYSTEM HIGH WALL UNIT INSTALLED ABOVE DOORWAY +8'-0" AFF.
5 PROPOSED REFRIGERANT LINESET ROUTING. LINESET SHALL BE SIZED PER MANUFACTURER'S
RECOMMENDATIONS. COORDINATE EXACT ROUTING WITH ALL EXISTING CONDITIONS AND NEW
SYSTEMS.
6 NEW THERMOSTAT IN NEW LOCATION. WIRING SHALL BE CONCEALED WITHIN WALL. REFER TO M-701.
7 MANUAL AND AUTOMATIC AIR VENTS INSTALLED IN SUPPLY AND RETURN PIPING AT HIGH POINT.
HARD PIPE COMMON DRAIN LINE TO MOP SINK. REFER TO DETAIL 5A/M-501.
8 BOILER CARBON MONOXIDE SENSOR. REFER TO M-701.
9 DIFFERENTIAL PRESSURE TRANSDUCER STATION. REFER TO M-701. INSTALL WITHIN PLENUM IN AN
ACCESSIBLE LOCATION.
10 NEW THERMOSTAT INSTALLED IN SIMILAR LOCATION AS EXISTING. WIRING SHALL BE CONCEALED
WITHIN WALL. REFER TO M-701.
11 EXPOSED PIPING WITHIN APPARATUS BAY SHALL BE PAINTED BY DIVISION 9 TO MATCH ADJACENT
SYSTEMS.
12 PIPING UP TO FIRST FLOOR. REFER TO MP101.
13 REFRIGERANT PIPING UP THROUGH ROOF CURB TO SSCU-1. REFER TO MR101.
14 SPLIT SYSTEM MANUFACTURER'S WALL MOUNTED CONTROLLER.
1/4" = 1'-0" 2A
BASEMENT PIPING ENLARGED PLAN
J M
J
T
T T
T
T
T
T
T
CO
A. DARK LINES INDICATE NEW WORK.
B. LIGHT SOLID LINES INDICATE EXISTING MECHANICAL EQUIPMENT, DUCTWORK, PIPING, AND/OR
MECHANICAL ACCESSORIES TO REMAIN AS-IS. CONTRACTOR TO FIELD VERIFY ACTUAL
EXISTING CONDITIONS PRIOR TO BIDDING.
GENERAL PIPING NOTES
EX. EH-2
EX. EH-3
EX. EH-1
T- EH-2
EX. EH-3
EX. EH-3
EX. EH-1
EX. RH-3
EX. EH-1
EX. EH-1
ELEC
TOOL ROOM
APPARATUS BAY
CUSTODIAL
RR
RISER
EMS STORAGE
AIR COMPRESSOR
STAIR 2.1
ST 2-1
VESTIBULE
OFFICE / WATCHROOM
OFFICE STORAGE
CAPTAIN'S OFFICE
STAIR 1
ST 1-1
STOR.
FITNESS ROOM
GEAR ROOM
ADA RR
RR
CORRIDOR
VAV-2-4
VAV-2-5
VAV-2-4
VAV-2-5
VAV-2-3
VAV-2-2
VAV-2-1
VAV-2-1
VAV-2-2
VAV-2-3
EX. SSCU-TECH
EX. RH
1B
MP101
1C
MP101
3/4" HHWR
3/4" HHWS
1" HHWR
1" HHWS
1" HHWS
1" HHWR
BAS
B-1
AS-1
EX. GFUH
ET-1
TCP-HHW
HOUSEKEEPING PAD
T-GFUH
WF-1
HHWS&R UP TO SECOND FLOOR.
CONTINUED ON MP102.
HHWS&R DOWN TO BASEMENT.
CONTINUED ON MP100.
1 1/2" HHWS
1 1/2" HHWR
2" HHWS
2" HHWR
3/4" HHWS
3/4" HHWR
3/4" HHWS
3/4" HHWR
1 1/4" HHWS
1 1/4" HHWR
3/4" HHWS
3/4" HHWR
1" HHWS
1" HHWR
1 1/4" HHWS
1 1/4" HHWR
ISOLATION VALVES
ISOLATION VALVES
REFRIGERANT LINESET
DOWN TO BASEMENT.
CONTINUED ON MP100.
1 1/2" HHWS
1 1/2" HHWR
COORDINATE EXACT ROUTING
WITH EXISTING CONDITIONS
P-1
Level 1 0' - 0"
FIRST FLOOR
0' - 0"
ET-1
EX. GFUH
AS-1
B-1
WF-1
TCP-HHW
P-1
SECOND FLOOR
18' - 0"
FIRST FLOOR
0' - 0"
1C
MP101
ET-1 AS-1
B-1
WF-1
EX. GFUH
BOILER FLUE
ET-1
AS-1
TCP-HHW
WF-1
P-1
B-1
FLUE
COMBUSTION AIR
3/4" COPPER
DRAIN LINES
2" HHWS
2" HHWR
3/4"
3/4"
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:5
:3
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
M
\2
-0
.4
H
B ld g
M a e c k ri c h
.r v t
2026-028.44H
10.28.2026
FIRST FLOOR PIPING
PLAN
MP101
AJE / PWF
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4 H
C
IT
Y
O F
C A
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .