This file is a General Notes and Sheet Index document for the City of Carmel Fire Station #44 HVAC Replacement project located at 5032 E Main Street, Carmel, Indiana 46033. The project scope includes replacement of the heating, ventilating, and air conditioning systems, along with related electrical, controls, and ancillary work. The building is a Type VB construction occupied as a fire station with a total area of 16,171 square feet, comprising a basement (2,548 sf), first floor (8,244 sf), second floor (5,039 sf), and mezzanine (340 sf). The project documents include comprehensive drawings and specifications across structural, architectural, mechanical, plumbing, and electrical disciplines. Sealed bids for this project will be received by the Board of Public Works and Safety for the City of Carmel via the City's e-Procurement Portal at https://procurement.opengov.com/portal/carmelin, with bids due by 10:00 a.m. on Wednesday, December 16, 2026.
The project must comply with the 2014 Indiana Building Code, 2010 Indiana Energy Code, 2014 Indiana Mechanical Code, 2012 Indiana Plumbing Code, 2014 Indiana Fire Code, and the 2008 National Electrical Code. All contractors are responsible for field verification of existing conditions, coordination with other trades, protection of building surfaces, identification and resolution of deviations from contract documents, and all costs associated with these requirements. The existing building is equipped with both a fire alarm system and automatic sprinkler system. The document does not specify pricing terms, set-asides, incumbent information, or funding sources in the available content.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Notes
• Nothing set forth in these Drawings shall release any Contractor from responsibility to provide appropriate quantities, field measurements, dimensional stability, installation, anchorage and coordination with other trades, or waive the Contractor's responsibility to identify and resolve deviations from the requirements of the Contract Documents, or waive the Contractor's responsibility to alert the Architect to errors or omissions contained therein.
• Each Contractor shall verify in the field all existing applicable conditions and dimensions shown on the Drawings and as pertinent to the intent of these Drawings. Any discrepancy discovered shall be brought to the attention of the Architect prior to the commencement of any Work affected by, or related to, such discrepancy.
• Each Contractor shall be responsible for all costs associated with, or caused by failure to comply with requirement.
• Each Contractor shall review in advance all portions of the Work to verify that the Work will not prohibit completion of the Project as intended in these Contract Documents. Any questions shall be promptly referred to the Architect for resolution.
• Each Contractor shall refer to the Project Manual for cleaning and disposal requirements.
• Each Contractor shall be responsible for the protection of all surfaces and finishes at interior and exterior of building. Damaged surfaces and finishes resulting from the performance of the Work shall be repaired at no cost to the Owner by the responsible Contractor to match existing to the satisfaction of the Owner.
• Each Contractor shall coordinate respective cutting and patching Work with the other Prime Contracts.
• Each Contractor shall become completely familiar with all aspects of the Work, even those areas designated to be provided by others. This familiarization includes full and complete understanding of the Work described on all Sheets of the Drawings and in all Sections of the Project Manual. Failure by the Contractor to become completely familiar and cognizant of all aspects of the Work shall not relieve the Contractor of the responsibility to provide materials, assemblies, or services indicated in the Contract Documents.
Vicinity Map Thoroughfare Map
-0
.4
H
.2
.2
F
IR
E S
T A
T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
C
IT
Y O
F C
A R
M E
L
CITY OF CARMEL
FIRE STATION #44 HVAC REPLACEMENT
5032 E MAIN ST
CARMEL, IN 46033
2026-028.44H
G-001
SHEET INDEX
Number Sheet Name
1 - General
G-001 COVER SHEET
G-002 FIRE AND LIFE SAFETY PLAN
3 - STRUCTURAL
SF101 FIRST FLOOR SLAB AND FRAMING PLAN
SF102 SECOND FLOOR AND LOW ROOF FRAMING PLAN
S-501 SECTIONS AND DETAILS
S-600 STRUCTURAL NOTES
4 - Architectural
A-001 ARCHITECTURAL GENERAL NOTES AND ABBREVIATIONS
AD101 OVERALL DEMOLITION FIRST PLAN
AF101 OVERALL FLOOR PLANS
AC101 FIRST FLOOR REFLECTED CEILING PLAN
AR100 ROOF PLAN
7 - Mechanical
M-001 MECHANICAL SYMBOLS AND ABBREVIATIONS
MD100 BASEMENT DEMOLITION PLAN
MD101 FIRST FLOOR DEMOLITION PLAN
MD102 SECOND FLOOR DEMOLITION PLAN
MDR101 ROOF DEMOLITION PLAN
MH100 BASEMENT HVAC PLAN
MH101 FIRST FLOOR HVAC PLAN
MH102 SECOND FLOOR HVAC PLAN
MP100 BASEMENT PIPING PLAN
MP101 FIRST FLOOR PIPING PLAN
MP102 SECOND FLOOR PIPING PLAN
MR101 MECHANICAL ROOF PLAN
M-501 MECHANICAL DETAILS
M-502 MECHANICAL DETAILS
M-601 MECHANICAL SCHEDULES
M-701 TEMPERATURE CONTROLS SCHEMATICS
M-801 MECHANICAL ZONING PLAN
8 - Plumbing
P-001 PLUMBING SYMBOLS AND ABBREVIATIONS
PPD01 FIRST FLOOR DEMOLITION PLUMBING PLAN
PRD01 PLUMBING DEMOLITION ROOF PLAN
FP100 BASEMENT FIRE PROTECTION PLAN
FP101 FIRST FLOOR FIRE PROTECTION PLAN
FP102 SECOND FLOOR FIRE PROTECTION PLAN
PF101 FOUNDATION PLUMBING PLAN
PP101 FIRST FLOOR PLUMBING PLAN
PR101 PLUMBING ROOF PLAN
P-501 PLUMBING DETAILS
P-901 NATURAL GAS ISOMETRIC
P-902 COMBINE DOMESTIC WATER AND WASTE ISOMETRIC
9 - Electrical
E-001 SYMBOLS
E-002 GENERAL INFORMATION
ED101 DEMOLITION PLAN
EP101 POWER PLAN
EF101 FIRE ALARM PLAN
ER101 ROOF PLAN
E-501 GENERAL DETAILS
E-601 SCHEMATICS & SCHEDULES
584 SF
FITNESS
ROOM
209 SF
CAPTAIN'S
OFFICE
65 SF
OFFICE
STORAGE
351 SF
OFFICE /
WATCHROOM
57 SF
VESTIBULE
280 SF
GEAR
ROOM
57 SF
ADA RR
47 SF
RR
64 SF
AIR
COMPRESSOR
70 SF
EMS
STORAGE
64 SF
RISER
52 SF
RR
56 SF
CUSTODIAL
361 SF
TOOL
ROOM
4158 SF
APPARATUS
BAY
133 SF
ELEC
523 SF
CORRIDOR
12 SF
STOR.
130 SF
STAIR 1
150 SF
STAIR 2.1
23 SF
ELEV.
79 SF
RR
78 SF
RR
295 SF
PLANNING
83 SF
OFFICE
75 SF
STORAGE
1019 SF
EMERGENCY
OPERATIONS
134 SF
OFFICE
122 SF
MDF
173 SF
STAIR 1
77 SF
OFFICE
24 SF
CUSTODIAL
23 SF
ELEV.
104 SF
OFFICE
147 SF
DORM
99 SF
DORM
95 SF
DORM
122 SF
DORM
95 SF
DORM
53 SF
BATH
54 SF
BATH
63 SF
LOCKER
64 SF
LOCKER
53 SF
BATH
54 SF
BATH
63 SF
LOCKER
62 SF
LOCKER
54 SF
BATH
63 SF
LOCKER
40 SF
PANTRY
45 SF
PANTRY
42 SF
PANTRY
39 SF
JANITOR
23 SF
SUPPLY
CLOSET
63 SF
LOCKER
93 SF
DORM
54 SF
BATH 68 SF
MECH.
95 SF
STORAGE
54 SF
BATH
96 SF
DORM
99 SF
DORM
57 SF
LOCKER
52 SF
BATH 73 SF
LAUNDRY
345 SF
KITCHEN
374 SF
DINING
553 SF
DAY ROOM
63 SF
LOCKER
615 SF
CORRIDOR
112 SF
STAIR 1
169 SF
STAIR 2
N
123456
A
B
C
D
E
123456
A
B
C
D
E
Project No.
Project Date
Produced
These Drawings and Specifications, and all copies thereof are and shall remain the property and copyright of the Architect. They shall be used only with respect to this
Project and are not to be used on any other Project or Work without prior written permission from the Architect.
KEY PLAN
/2
/2
:4
:5
A M
C
R e v it L o c a l\
-0
.4
H
B ld g
A
\2
-0
.4
H B ld g
A tp h a n .r v t
2026-028.44H
10.28.2026
FIRE AND LIFE SAFETY
PLAN
G-002
TP
CITY OF CARMEL
FIRE STATION #44
HVAC
REPLACEMENT
-0
.4
H
C
IT
Y
O F
C A
R M
E L F
IR
E
S T
A T
IO
N
H
V A
C R
E P
L A
C E
M E
N T
5032 E MAIN ST
CARMEL, IN 46033
G -0
F
IR
E
A N
D L
IF
E
S A
F E
T Y
P L A
N
1/16" = 1'-0" 1A
FIRE AND LIFE SAFETY PLAN
1/16" = 1'-0" 3A
BASEMENT FIRE AND LIFE SAFETY PLAN
1/16" = 1'-0" 1B
SECOND FLOOR FIRE AND LIFE SAFETY PLAN
Smoke Detectors: Are required for HVAC shutdown for systems delivering in excess of 2000 CFM, and for elevator recall. (3003.2, 606.1 IMC)
Fire Alarm System: Existing building is equipt with a fire alarm system
Automatic Sprinklers: Existing building is equipt with automatic sprinkler system
Emergency lighting is required in all corridors, rooms, spaces that require more than one means of egress or exit. [1006.3]
Emergency and Egress
Lighting:
Exit signs required to indicate the direction of egress travel for rooms and areas that require more than one exit access. [1011.1]
[Table 1016.2]
Exit Travel Distance: The maximum travel distance to an exterior exit is 200 feet.
Fire Dampers: Fire dampers are required at duct penetrations of fire-rated shafts and at duct penetrations of fire barriers required to have more than 1-hour fire rating. [717.5]
Incidental Use
Separation:
Incidental use areas are required to be provided with smoke tight construction. Partitions shall extend from the floor to the underside of the floor, roof deck above, or tight ceiling. Doors shall be self-closing or automatic-closing upon detection of smoke. Air-transfer openings shall be provided with smoke dampers. Duct work does not need to be dampered.
[509.4.2]
Total: 16,171 sf
Second Floor: 5,039 sf
Mezzanine: 340 sf
FIrst Floor: 8,244 sf
Existing Area: Basement: 2,548 sf
Construction Type: Type VB Construction existing
Occupancy Classifications: B Occupancy [304]
Scope of Work: Existing building currently used as a FIre Sation. New scope of work includes new rooftop air handling unit, boilers, chillers, and ceiling replacement.
2010 Indiana Energy Code
2014 Indiana Mechanical Code
2008 National Electrical Code
2012 Indiana Plumbing Code
2014 Indiana Fire Code
Applicable Code: 2014 Indiana Building Code
CODE SUMMARY
# Revision Date
| G-001 - COVER |
| G-002 - FIRE AND LIFE SAFETY PLAN |
File details come from the government source that posted it. Updated .