Supplemental Scope of Work requirements Phase 2 Truman Elevators .pdf

PDF 62 KB Posted

Attached to
HST Elevator Phase 2 Federal contract opportunity
Solicitation number
47PM0220R0027
Issued by
General Services Administration Public Buildings Service National Capital Region

About this file

This solicitation is for a design-build elevator modernization project at the Harry S Truman Federal Office Building in Washington, DC. The scope of work includes renovating twenty-one elevators and associated machine rooms to extend the building's useful life and bring elevators up to code compliance. Work comprises abatement, demolition, HVAC replacement, electrical work, and elevator monitoring/communication systems installation. All noisy construction must occur on weeknights and weekends. Offerors and their subcontractors/consultants must have Secret-level facility security clearance, and all workers must have Final Secret clearance. The General Services Administration is seeking responses from small businesses certified in NAICS Code 238290 (Elevator and Moving Stairway Manufacturing) with a size standard of $15 million. The estimated design-build cost is over $10 million and period of performance is approximately 1,095 calendar days from notice to proceed.

View the file

Other files for this federal contract opportunity

Other files attached to HST Elevator Phase 2, newest first.
File Type Posted
SF30 Amendment 0007 Solicitation 47PM0220R0027 HST Elevator Modernization 2021 4 15.pdf PDF
Solicitation Amendment 47PM0220R0027_0006.pdf PDF
PROJNET - Truman Building Elevator Upgrades documents on PROJNET 3.pdf PDF
Security Specifications 10-12-18 HST Elevator Renovaton Project 01541_181012 .pdf PDF
Sign in Sheet HST Elevator Phase 2 2021 02 17.pdf PDF
Electrical SOW Design Recommendations for the GSA Elevator Upgrade design.pdf PDF
SOW_Phase 2 Elevator Document .pdf PDF
GOVT RFI Responses HST Elevator Phase 2 2021 03 23 .pdf PDF
SF - 30 Solicitation Amendment 47PM0220R0027_(0005). 2021 03 16 pdf.pdf PDF
Solicitation Amendment 47PM0220R0027_0004 (1).pdf PDF
SF1442 47PM0220R0027 Form 2021 01 11.pdf PDF
Past Performance Form (PPQ).docx DOCX document
Solicitation Amendment 47PM0220R0027_0003.pdf PDF
Solicitation Amendment 47PM0220R0027_0002.pdf PDF
Revised SF 30 Solicitation Amendment 47PM0220R0027_0001.pdf PDF
SF 30 Solicitation Amendment 47PM0220R0027_0001.pdf PDF
Security Specifications TASK 399 (Elevator Phase2) Section 01541.pdf PDF
Tradesman Information Form - Revised 2.26.20.xlsx XLSX spreadsheet
03_Appendix A_Phase 2 Elevator Location PlansHST Elevators - Construction 2020 12 08 .pdf PDF
C and D Waste Monthly Report BAS Replacement 2020 11 30.pdf PDF
SOW_100 Percent_ Narrative Elevator_ 01-25-17 HST Elevators - Construction 2020 12 08.pdf PDF
SBU Attachment pdf.pdf PDF
GSA527-15b Form.pdf PDF
EVALUATION FACTORS.pdf PDF
DB Agreement Oct 2020 r2 508 Revised 11.17.2020 (LDW 11.19.2020) (1) (5).pdf PDF
SF25A - Payment Bond .pdf PDF
RFP Letter 47PM0220R0027 HST Elevator Upgrade 2020 01 08 TRB.pdf PDF
GC Reps and Certs Nov 2020 508.pdf PDF
Attachment A - OSHA3990_GuidanceforPreparingWorkplaceforCOVID-19 2020 07 11 (1) (2) (3) (1) (1).pdf PDF
04_Appendix B_Elevator Reference Specifications HST Elevators - Construction 2020 12 08.pdf PDF
Attachment B - OSHA3994_10_Steps_All_Workplaces_Can_Take_to_Reduce_Risk_of_Exposure_to_Coronavirus 2020 07 11 pdf.pdf PDF
beta.SAM Wage rate DC20210002 Jan 1.pdf PDF
Waste Mgmt Plan (3).xlsx XLSX spreadsheet
Asbestos Survey Report HST Elevators - Construction 2020 12 08.pdf PDF
SF25 - Performance Bond .pdf PDF
DB Solicitation 1 Phase July 2020 r2 508.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3-19-21

Truman Building Elevators – Phase 2

Supplemental Scope of Work requirements dated 3-19-21

Supplemental Work Items to the Phase 2 Elevator Scope Document dated January 25, 2017, and the project, are as follows:

1. Weekly project meetings shall be held. If the Government deems that sufficient work is being performed and work is on schedule, the frequency of progress meetings can be revised by the Government.

2. Provide detailed 2 week “Look Ahead” schedules that provide more detail than the project schedule especially as related to coordination with tenants, security, outages and building operations.

3. Patch voids in blockwork around frames inside the hoistway as needed. During two previous elevator upgrade project a very limited number of voids were found in the blockwork at some frames.

4. All work that generates noise that disturbs the tenants must be preformed on weekday nights between 6:00 p.m. and 6:00 a.m. and on weekends.

5. DELETE requirements in Truman Building Phase 2 Elevator Scope Document, January 25, 2017, paragraph V. DESIGN/BUILD CONTRACTOR SERVICES requiring estimates with design submissions.

6. Truman Building Phase 2 Elevator Scope Document, January 25, 2017, Section

14220, DELETE all requirements to “Retain” Roping for all elevators and ADD the requirement to “Replace with New” all Roping for all elevators. Also, in this same

Section 14220, DELETE all requirements to “Retain” Machines for all elevators and

ADD the requirement to “Replace with New” all Machines for all elevators. These requirements supersede other direction in the solicitation documents.

7. All Codes, Standards, Guidelines and Requirements Documents noted in the documents in this solicitation shall the most current edition as of the date of the bid due date.

8. Provide all electronic documents required after NTP for the project via ePM, the electronic project management system used by GSA, and then in KAHUA. The ePM system is planned to be phased out during the project and then a new system called

KAHUA is planned to be used for projects. The new KAHUA system is planned to start in the second half of 2021 or the first half of 2022.

9. New conduit and wiring shall from the emergency generator to the elevator machine rooms shall be installed from the emergency generator (located on the roof of the 2nd floor) then under the metal grate flooring from the generator to the building exterior wall, then up the outside of the exterior wall to the roof of the 8th floor, then into interior mechanical space and to all elevator machine rooms to be upgraded under this project.

Provide a metal cover / shroud over the conduit where it is installed on the exterior wall.

The metal cover over the conduit shall be painted to match the color of the facade.

10. See documents in PRONET site for Phasing / Sequence of Phasing of work in document titled “HST__Elevator_Sequencing (1)”.

11. Provide conduit and wiring for the Liftnet monitoring system from each elevator machine room to the central elevator control room. Connect wiring on both ends to the control system. The central elevator control room is located near the center of the building. Conduit may need to run down a floor level and back up a floor level to the control room depending on the location of the elevator machine room.

end

File details come from the government source that posted it. Updated .