47PF0024R0076 I Falls GC Supplemental 1442 Pricing Sheet 7 29 2025.pdf

PDF 111 KB Posted

Attached to
General Construction Services - International Falls Land Port of Entry Project
Solicitation number
47PF0024R0076
Issued by

About this file

This Supplemental 1442 Pricing Sheet for the International Falls Land Port of Entry General Construction project provides a detailed pricing breakdown for multiple construction contract line item numbers (CLINs) and unit pricing rates. The document outlines base contract construction services and five optional scope modifications, including adding an exterior 2nd floor terrace, choosing between asphalt and concrete paving, designing a roundabout intersection, selecting window mullion cap materials, and modifying site fencing.

The unit pricing rates cover specialized construction activities such as geothermal well installation, contaminated material removal, clean fill material procurement, temporary contaminated material storage, and ground improvements below building structures. Each unit price includes a detailed description, base bid quantity, and unit of measurement. The pricing sheet is part of a $193-$203 million project funded under the Infrastructure Investment and Jobs Act, involving the General Services Administration and multiple federal agencies including Customs and Border Protection, USDA, and FDA. The project aims to construct a new land port of entry in International Falls, Minnesota, with an anticipated contract award in February 2026 and a performance period of approximately 1,103 calendar days.

View the file

Other files

File Type Posted
IFalls LPOE Substitution Request Log 250821.pdf PDF
RFP 47PF0024R0076 Amend 0007 RFIs.pdf PDF
RFP 47PF0024R0076 Amend 0007 SF30.pdf PDF
Transmittal - 00086.pdf PDF
Existing building CAD files-20241226T212033Z-001.zip ZIP file
RFP 47PF0024R0076 Amend 0006 RFIs.pdf PDF
IFALLS LPOE_75 percent CD DRAWINGS V1_L6-14_RFI markup.pdf PDF
RFP 47PF0024R0076 Amend 0006 SF30.pdf PDF
MN0300ZZ LPOE IFalls Asbestos Inspection CCA 2020.pdf PDF
01 91 13_General Commissioning Requirements_2.pdf PDF
IFALLS LPOE_75 percent CD DRAWINGS V1_L7-03_RFI markup.pdf PDF
RFP 47PF0024R0076 Amend 0005 RFIs.pdf PDF
RFP 47PF0024R0076 Amend 0005 SF30.pdf PDF
RFP 47PF0024R0076 Amend 0004 RFIs.pdf PDF
75percent CD Civil AutoCAD Files.zip ZIP file
RFP 47PF0024R0076 Amend 0004 SF30.pdf PDF
IFalls LPOE Substitution Request Log 250731.pdf PDF
GSA I Falls LPOE_Soil Management Plan_Dec 9 2024.pdf PDF
RFP 47PF0024R0076 Amend 0003 SF30.pdf PDF
RFP 47PF0024R0076 Amend 0003 RFIs.pdf PDF
IFalls LPOE GC PreProposal Presentation 7 22 2025.pdf PDF
IFalls LPOE GC PreProposal Agenda 7 22 2025.pdf PDF
IFalls In Person and Virtual Attendence Sheets 7 22 2025.pdf PDF
RFP 47PF0024R0076 Amend 0002 SF30.pdf PDF
RFP 47PF0024R0076 Amend 0001 SF30.pdf PDF
RFP 47PF0024R0076 Amend 0001 SF30.pdf PDF
RFP 47PF0024R0076 Amend 0001 RFIs.pdf PDF
RFP 47PF0024R0076 SF1442 7 17 2025.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 8 Fire Protection.pdf PDF
47PF0024R0076 Reps and Certs GC MAY 2025.pdf PDF
47PF0024R0076 I Falls GC Supplemental 1442 Pricing Sheet.pdf PDF
47PF0024R0076 IFalls LPOE GC SoW.pdf PDF
Past Performance Questionnaire.docx DOCX document
I FALLS GC PRE-PROPOSAL CONFERENCE ATTENDANCE REQUEST FORM.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 4 Architecture.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 1 Cover and LifeSafety.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 2 Survey and Civil.pdf PDF
IFALLS LPOE_75_CD PROJECT MANUAL V1 0523 2025.pdf PDF
IFALLS LPOE_75_CD PROJECT MANUAL V3 0523 2025.pdf PDF
IFALLS LPOE_75_CD PROJECT MANUAL V2 0523 2025.pdf PDF
MN20250062 2 7 2025.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 9 Electrical.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 10 Technology.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 7 Plumbing.pdf PDF
47PF0024R0076 Sol_GC MAY 2025.pdf PDF
47PF0024R0076 Agr_GC_MAY 2025.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 5 V2 Cover and Structure.pdf PDF
IFALLS LPOE_75_ CD DRAWINGS 6 Mechanical.pdf PDF
47PF0024R0076 SF1442.pdf PDF
Individual Model_Subk_Plan - May 2025 - 508 Compliant.docx DOCX document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

47PF0024R0076 - International Falls Land Port of Entry

General Construction

Supplemental 1442 Pricing Sheet

7/29/2025

CLIN ITEM PRICE

0001 Base Contract Construction Services $

Option 1: Add Exterior 2nd Floor Terrace to Main Building Base Scope: Provide ballasted roof area with paver path (no terrace) Option 1: Provide terrace and associated improvements as shown on the drawings.

Note: most drawings show the option scope.

Option 2: Asphalt vs concrete paving areas - Base Scope:

Provide paving with greater quantity of asphalt as shown on the drawings.

Option 2: Provide paving with greater quantity of concrete as shown on the drawings.

Note: most drawings show the option scope.

Option 3: Main Intersection Layout - Base Scope: Provide stop-controlled intersection as shown on the drawings.

Option 3: Provide a roundabout as shown on the drawings.

Note: most drawings show the option scope.

Option 4: Window Mullion Cap Details - Base scope: Provide Aluminum Mullion Caps at all second floor openings as noted in detail 3/A5.61 Option 4: Provide Wood Mullion Caps at all second floor openings as shown in detail 7 and 10/A5.61

Option 5: Site Fencing - Base Scope: Provide Site fencing as shown on detail 2/A5.96 Option 5: Provide Site fencing as shown on detail 1/A5.96

Total Contract Price (CLIN 0001 + 0002 + 0003 + 0004 + 0005 + 0006)

Unit Pricing Rates

Unit Price No. 1: Geothermal Well

1. Description: All costs associated with installation of geothermal well from building to bore location including but not limited to drilling, excavation, backfill, installation of vertical and horizontal piping, antifreeze and testing in accordance with Section

232113.33 – Ground-Loop Heat-Pump Piping and Drawings.

2. Base Bid Quantity: as shown on the drawings

3. Unit of Measurement: Cost in place per bore of single geothermal well.

Unit Price No. 2: Contaminated Material Removal.

1. Description: Removal of additional contaminated material designated as non-hazardous, certified non-special waste and legally disposing off-site at a permitted facility. Costs to include permits from regulatory agencies, earth moving, transportation, disposal fees and environmental services consultant fees for characterizing and signing manifests. Reference RAP the Soil Management Plan (SMP) for all information regarding contaminated soils and hazardous materials (e.g., identification, assessment, procedures, testing, handling, stockpiling, disposal, etc.)

2. Base Bid Quantity: 25,000 cubic yards of contaminated material removal.

3. Unit of Measurement: Cost per ton (compacted/in-place volume).

Unit Price No. 3: Clean Fill Material

1. Description: Additional clean fill material certified as virgin material mined directly from a quarry that meets applicable Soil Reference Values (SRVs) and placing in accordance with the requirements for Primary Support Material to replace Contaminated Material removed with application of Unit Price 10 2.

2. Base Bid Quantity: 10,000 cubic yards of clean fill material.

3. Unit of Measurement: Cost per cubic yard (compacted/in-place volume).

Unit Price No. 4: Temporary Storage of Contaminated Material

1. Description: Additional segregating and temporary storage of excavated materials with apparent contamination or environmental concerns in accordance with the MPCA approved RAP and applicable federal, state, and local laws and requirements in environmental dumpsters or stockpiles

2. Base Bid Quantity: temporary storage of 10,000 cubic yards of apparently contaminated material for four weeks.

3. Unit of Measurement: Cost per cubic yard per week.

Unit Price No. 5: Ground Improvements Below Building Structures

1. Description: Provide and install rigid inclusion ground improvement for building structures in accordance with Section 31 66 23.

2. Base Bid: Quantity assumed based on performance specifications and information available at bid time (contractor to indicate assumed quantity basis of bid)

3. Unit of Measurement: Cost per linear foot installed for each unique rigid inclusion design (diameter) above or below quantity assumed in item 2.

File details come from the government source that posted it. Updated .