47PF0023R0049 Supplemental 1442 Pricing Sheet 6 4 2024.pdf
PDF 198 KB Posted
- Attached to
- Construction Manager as Constructor (CMc) for the International Falls Land Port of Entry Project
- Solicitation number
- 47PF0023R0049
About this file
This document appears to be a Supplemental 1442 Pricing Sheet related to RFP 47PF0023R0049 for a Construction Manager as Constructor (CMc) contract for the International Falls Land Port of Entry project.
The pricing sheet details various contract line items (CLINs) and pricing for the Design/Pre-Construction Phase Services (Firm Fixed Price), Target Estimated Cost of Work (including non-IRA and IRA expenditures for low embodied carbon materials), CMc Contingency Allowance, CMc Fee, Guaranteed Maximum Price for Construction Services, and an optional Firearms Range. The pricing sheet also includes environmental remediation unit pricing.
The related federal contract opportunity is for CMc services for the International Falls Land Port of Entry project, with the objective of selecting a proposal that represents the best value to the Government. The solicitation will be competed using FAR Part 15 source selection procedures, with technical factors significantly more important than price. The project has an estimated total construction cost range of $175-195 million and a performance period of approximately 1085 calendar days. The Government is also seeking suppliers and manufacturers of low embodied carbon materials to support the project.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 47PF0023R0049 - Supplemental 1442 Pricing Sheet Updated 6/4/2024
CLIN ITEM PRICE
1 Design/PreConstruction Phase Services (Firm Fixed
Price)
2 Target Estimated Cost of Work (ECW) (Sum of 2.A and 2.B below)
2.A Non IRA Expenditures $ 2.B IRA Acquisition and installation of low embodied carbon materials (CLIN 2.B.a + 2.B.b + 2.B.c + 2.B.d)
2.B.a Acquisition and installation of low embodied carbon steel and associated expenses
2.B.b Acquisition and installation of low embodied carbon asphalt and associated expenses
2.B.c Acquisition and installation of low embodied carbon glass and associated expenses
2.B.d Acquisition and installation of low embodied carbon concrete and associated expenses
2.C IRA emerging and sustainable Technologies $ 3 CMc Contingency Allowance (CCA) Percentage 3% 4 CCA (CLIN 2 x CLIN 3) $ 5 Fee Percentage % 6 Fee (CLIN 2 x CLIN 5) $ 7 Option 1: Guaranteed Maximum Price (GMP) for
Construction Services (CLIN 2+4+6)
8 Option 2: Firearms Range 8.A Non IRA Expenditures 8.B IRA Acquisition and installation of low embodied carbon materials (CLIN 2.B.a + 2.B.b + 2.B.c + 2.B.d) 8.B.a Acquisition and installation of low embodied carbon steel and associated expenses 8.B.b Acquisition and installation of low embodied carbon asphalt and associated expenses 8.B.c Acquisition and installation of low embodied carbon glass and associated expenses 8.B.d Acquisition and installation of low embodied carbon concrete and associated expenses 9 Total Evaluated Price (CLIN 1+7+8) $
Environmental Remediation Unit Pricing:
International Falls LPOE Project - Environmental Remediation Unit Cost Items
ITEM Unit Unit Cost (Add)
Unit Cost (Deduct)
Remove & Dispose of Rubble or Debris CY $ $ Excavate Dioxin Contaminated Soil Material (Off Site Landfill Disposal) CY $ $ Excavate Metal Contaminated Soil Material (Off Site Landfill Disposal) CY $ $ Excavate Petroleum Contaminated Soil Material (Off Site Landfill Disposal) CY $ $ Dispose of Dioxin Contaminated Soil Material (Off Site Landfill Disposal) TON $ $
Dispose of Metal Contaminated Soil Material (Off Site Landfill Disposal) TON $ $ Dispose of Petroleum Contaminated Soil Material (Off Site Landfill Disposal) TON $ $ Clean General Fill Borrow Soil (Compacted Volume) CY $ $ Clean Select Suitable Borrow Soil (Compacted Volume) CY $ $ Clean Granular Borrow Soil (Compacted Volume) CY $ $ Clean Topsoil Borrow Soil (Compacted Volume) CY $ $