47PF0023R0049 Amend 02 RFIs.pdf
PDF 78 KB Posted
- Attached to
- Construction Manager as Constructor (CMc) for the International Falls Land Port of Entry Project
- Solicitation number
- 47PF0023R0049
About this file
This document is Amendment 02 to Request for Proposal (RFP) 47PF0023R0049 for Construction Manager as Constructor (CMc) services for the International Falls Land Port of Entry project in International Falls, MN. The amendment incorporates additional RFI responses, demolition drawings, and a revised pricing sheet. The RFP calls for Design Phase services and an option for Construction Phase services, with proposals due on June 20, 2024. The project is federally funded via the Bipartisan Infrastructure Law and Inflation Reduction Act, with an estimated total construction cost of $175-195 million. The evaluation criteria include experience, project management approach, personnel qualifications, past performance, sustainability, and small business utilization. The Government intends to make an award in October 2024, with the Design Phase starting then and the Construction Phase potentially awarded in February 2026 for approximately 1,085 calendar days. The amendment also provides details on the soil remediation scope and unit pricing to be included in proposals.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 02 - RFP 47PF0023R0039 - CMc Services for the International Falls
Land Port of Entry Project, International Falls, MN
This Amendment hereby incorporates the RFIs below, as well as the following documents:
“C2.01A SITE DEMOLITION PLAN - AREA A.pdf”, “C2.01B SITE DEMOLITION PLAN - AREA
B.pdf”, and “C2.01C SITE DEMOLITION PLAN - AREA C.pdf”. This amendment also incorporates a revised Supplemental 1442 pricing sheet, titled “47PF0023R0049 Supplemental 1442 Pricing
Sheet 6 4 2024. The due date for proposals remains June 20, 2024, no later than 1:00pm Central
Time.
Please see the submitted RFIs as of 06/03/2024, with corresponding responses:
Q: We need to identify all scopes of work that are outside the scope of the PLA to include with subcontractor solicitations. Can GSA provide input on scopes items known to be outside the scope of the PLA for International Falls?
A: GSA is unable to provide input on scope items as it relates to whether they are in or outside the scope of the Project Labor Agreement. GSA would defer to the National Labor Relations
Board regarding questions concerning covered scope and non covered scope for Project Labor
Agreements.
Q: Is this project federally funded?
A: Yes, this project utilizes federal funding via the Bipartisan Infrastructure Project as well as the
Inflation Reduction Act.
Q: What is the decision criteria?
A: The evaluation criteria can be found in the document titled “47PF0023R0049 Sol_CMc_April
2024”, but overall technical factors are as follows: Experience in Providing Design Phase and
Construction Phase Services on Similar Projects, Project Management Plan/Approach, Qualifications and Experience of Key Personnel, Past Performance in Providing Design Phase and Construction Phase Services on Similar Projects, Sustainability, Small Business Utilization.
Firms will be evaluated via best value/tradeoff, where the Technical evaluation is significantly more important than Price.
Q: Is there a possibility of another extension on the response due date?
A: At this time, GSA does not intend to do a second time extension. The due date shall remain
June 20, 2024.
Additional clarifications as a follow up to items from Amendment 0001:
Question: Can you clarify the Site and Civil Demolition scope?
Answer: Three additional drawings are being issued as part of this amendment to clarify the scope associated with site and civil demolition, “C2.01A SITE DEMOLITION PLAN - AREA A.pdf”, “C2.01B SITE DEMOLITION PLAN - AREA B.pdf”, and “C2.01C SITE DEMOLITION PLAN -
AREA C.pdf”
Question: The condition of the soil and extent of remediation is unknown at this point.
How should this scope be priced for proposal purposes?
Answer: There are contaminants, but it is unknown as to the extent. Guidance/information for how to submit a proposal for this scope is included below.
Question: Is there a ground water issue?
Answer: There may be contaminants, but the extent is unknown. Since the exact clean-up requirements are unknown at the time of this solicitation, offerors are to assume that there is no cost for groundwater cleanup as part of this proposal. If additional scope is required to address groundwater contamination, a change order will be issued at a later time.
Question: How do we define what to price?
Answer: Guidance/information for how to submit a proposal for this scope is included below.
Question: Currently we are pricing that we will not be taking any soil offsite?
Answer: No, that assumption is incorrect. Guidance/information for how to submit a proposal for this scope is included below..
Question: Concerning the soil remediation, there might be many unit costs provided.
Answer: Guidance/information for how to submit a proposal for this scope is included below.
Clarification regarding soil remediation scope:
The scope of soil remediation will be per the following preliminary assumptions:
● Remove & Dispose of Rubble or Debris is assumed as 35% of Building Area with a 2’ depth
● Excavate Dioxin Contaminated Material is assumed as the Leachate Line plus
Incinerator soil volumes
● Excavated Metal Contaminated Material is assumed as the Paving Area with a 2’ depth
● Excavate Petroleum Contaminated Material is assumed as the Landscape Area with a 4’ depth (This item may not be needed, but I thought we may want a unit price to excavate
& dispose of petroleum impacted soil)
● The disposal units are converted to TONS because this is an easier way to track trucked amounts to landfills with weight tickets.
● Clean General Fill assumes 3.67’ of depth under the Landscape Area
● Clean Select Suitable Borrow assumes 2’ depth under the Building Area (with a structured floor slab)
● Clean Granular Borrow assumes 2’ depth under the Paving Area
● Clean Topsoil Borrow assumes 4” depth under the Landscape Area
The assumed quantity of soil remediation scope includes the following:
International Falls LPOE Project
Environmental Remediation Unit Cost Items
ITEM Estimated Unit
Quantity
Remove & Dispose of Rubble or Debris 2,000 CY
Excavate Dioxin Contaminated Soil Material (Off Site Landfill
Disposal) 22,370 CY
Excavate Metal Contaminated Soil Material (Off Site Landfill
Disposal) 35,926 CY
Excavate Petroleum Contaminated Soil Material (Off Site Landfill
Disposal) 62,864 CY
Dispose of Dioxin Contaminated Soil Material (Off Site Landfill
Disposal) 36,240 TON
Dispose of Metal Contaminated Soil Material (Off Site Landfill
Disposal) 58,200 TON
Dispose of Petroleum Contaminated Soil Material (Off Site Landfill
Disposal) 101,840 TON
Clean General Fill Borrow Soil (Compacted Volume) 57,678 CY
Clean Select Suitable Borrow Soil (Compacted Volume) 5,704 CY
Clean Granular Borrow Soil (Compacted Volume) 35,926 CY
Clean Topsoil Borrow Soil (Compacted Volume) 5,186 CY
Offerors shall provide unit cost prices on the updated Supplemental 1442 Pricing Sheet included with this Amendment, dated 6/4/2024. The unit prices proposed may be subject to negotiations prior to award, however, for the purpose of the price evaluation, the Total Evaluated Price (CLIN
9) will be the basis of any final price considerations for award. The intent is for these provided unit prices to be utilized after award as part of potential negotiated modifications to add or remove applicable environmental remediation items.