36E77618R0005-044.pdf
PDF 74 KB Posted
- Attached to
- VISN 8 Orlando Energy Savings Performance Contract (ESPC) (Previously posted under 36E77618Q0013)
- Solicitation number
- 36E77618R0005
About this file
This document outlines the requirements for an Energy Savings Performance Contract to implement energy conservation measures at four Department of Veterans Affairs medical campuses in Orlando, Florida. The solicitation will be issued as a Request for Proposal open only to Service Disabled Veteran Owned Small Businesses. Offerors must be on the Department of Energy's Qualified List of Energy Service Companies and proposals are due within 60 calendar days of issuance on March 22, 2018. The opportunity is set aside for SDVOSBs with a NAICS code of 541330 and size standard of $38.5 million. The identified energy conservation measures include improvements to boiler plants, chiller plants, HVAC systems, lighting, electric motors and drives, renewable energy installations, water conservation, and commissioning at the Lake Baldwin, Lake Nona, Lakemont, and Viera campuses.
36E77618R0005 S02 RFP ATTACHMENT J-16 - IGA Checklist.pdf
View the file
Other files
Show all 47
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The Department of Veterans Affairs requires that all IGA submissions meet the minimum content requirements as detailed below. Failure to meet these requirement will result in return of the IGA submission.
30% or 35% IGA Submission Received Sufficient Notes
1. Baseline Conditions
Included Facility(s) description, hours of operation, quantity of occupants, and standards of comfort should be agreed upon by this point
2. Project Development Costs
Current Project Development Cost (PDC) with full pricing breakout shall be provided in addition to a Not To Exceed (NTE) amount for PDC through Task Order Award.
3. ECMs Descriptions and Calculations (anticipated)
4. List of ECMs that were considered for installation but were disqualified because of cost or other constraints.
This list should be prioritized based on Facility needs. This list should include an estimated cost (if applicable) for the ECM and a detailed explanation as to why the ECDM was disqualified.
5. Metering Plan Data logging should be done by this point to confirm baseline conditions
6. Measurement & Verification (Preliminary) VA M&V Guidelines should be taken into consideration when recommending Options.
7. Risk, Responsponsibilitity and Performance Matrix
8. TO Schedules 1-5 current to 30 or 35%
9. Initiate project within eProjectBuilder Contract Specialist will assist in initiating project in ePB.
ESPC/UESC IGA CONTENT CHECKLIST
60% or 65% IGA Submission Received Sufficient Notes
1. Baseline Conditions
Included Facility(s) description, hours of operation, quantity of occupants, and standards of comfort should be agreed upon by this point
2. ECM Development including Descriptions and Calculations
Preliminary pricing and estimated paybacks should be included.
Provide feasibility study data needed to assess capital contributions for renewable energy or CHP, as appropriate.
3. List of ECMs that were considered for installation but were disqualified because of cost or other constraints.
This list should be prioritized based on Facility needs. This list should include an estimated cost for the ECM and a detailed explanation as to why the ECDM was disqualified.
4. Metering Results
5. Measurement & Verification Outline
6. Risk, Responsponsibilitity and Performance Matrix
7. TO Schedules 1-5 current to 60 or 65%
8. Manufacturing Information for Equipment - Cut Sheets
90% or 95% Draft Final IGA Submission Received Sufficient Notes
1. Baseline Conditions/Assumptions
2. ECM Development (SOW) including Descriptions and Calculations
ECM pricing should include sub contractor bids.
3. List of ECMs that were considered for installation but were disqualified because of cost or other constraints.
This list should be prioritized based on Facility needs. This list should include an estimated cost for the ECM and a detailed explanation as to why the ECDM was disqualified.
5. Detailed Measurement & Verification (baseline & calcs) plan including reporting.
6. Risk, Responsponsibilitity and Performance Matrix
7. TO Schedules 1-5 with firm, detailed cost and savings
8. Subcontractor Abstracts with full transparency including quotes. Provide price analysis where no competition was received.
Subcontract offers shall be on the Sub's letterhead. The offer shall be signed and dated by the Subcontractor.
9. Commissioning
10. Training (Detailed)
11. Operations & Maintenance (Detailed including responsponsibilities per ECM).
12. Full transparency of all overhead costs, travel, etc..
With justification.
13. Schedule for project completion on a per facility basis.
Show the times that each facility is or is not available for construction activity.
14. Manufacturing Information for Equipment - Cut Sheets
15. IDS and SFO (Investor Deal Summary & Standard Finance Offer)
16. Healthcare Impact Plan
17. Post Acceptance Performance Period Services
18. TO Schedules submitted into eProjectBuilder
Once negotiation is complete, final schedules will be uploaded and accepted within ePB.
19. Time Sheets for each individual that worked in the Project Development Stage. (Time Sheets for all projects individuals have worked on during this time may also be requested.)
Required if the Project Development Stage costs have not previously been agreed to.