36E77618R0005-032.pdf

PDF 66 KB Posted

Attached to
VISN 8 Orlando Energy Savings Performance Contract (ESPC) (Previously posted under 36E77618Q0013)
Solicitation number
36E77618R0005
Issued by

About this file

This document package includes an attachment outlining deliverables and a notice of federal contract opportunity. The attachment lists 29 post-award deliverables required on varying frequencies, including project schedules, design packages, commissioning and safety plans, maintenance procedures, warranties and as-built drawings.

The federal contract opportunity is a request for proposal from the Department of Veterans Affairs for an energy savings performance contract to implement energy conservation measures at four locations within the VA Medical Center in Orlando. The solicitation seeks to upgrade lighting, HVAC systems, motors, renewable energy and improve water conservation. Proposals are due within 60 days and must be submitted electronically. The opportunity is set aside for Service-Disabled Veteran Owned Small Businesses and offerors must be on the Department of Energy qualified list of energy service companies.

36E77618R0005 S02 RFP ATTACHMENT J-4 - Deliverables.pdf

View the file

Other files

File Type Posted
36E77618R0005-00001005.pdf PDF
36E77618R0005-00001019.pdf PDF
36E77618R0005-00001015.xlsx XLSX spreadsheet
36E77618R0005-00001013.xlsx XLSX spreadsheet
36E77618R0005-00001011.pdf PDF
36E77618R0005-00001006.pdf PDF
36E77618R0005-00001001.docx DOCX document
36E77618R0005-00001000.docx DOCX document
36E77618R0005-00001017.docx DOCX document
36E77618R0005-00001004.pdf PDF
36E77618R0005-00001009.pdf PDF
36E77618R0005-00001008.pdf PDF
36E77618R0005-00001014.xlsx XLSX spreadsheet
36E77618R0005-00001020.pdf PDF
36E77618R0005-00001002.pdf PDF
36E77618R0005-00001012.pdf PDF
36E77618R0005-00001018.xlsx XLSX spreadsheet
36E77618R0005-00001016.pdf PDF
36E77618R0005-00001021.xlsx XLSX spreadsheet
36E77618R0005-00001007.pdf PDF
36E77618R0005-00001003.pdf PDF
36E77618R0005-00001010.pdf PDF
36E77618R0005-030.pdf PDF
36E77618R0005-031.pdf PDF
36E77618R0005-034.pdf PDF
36E77618R0005-045.pdf PDF
36E77618R0005-037.pdf PDF
36E77618R0005-025.docx DOCX document
36E77618R0005-026.docx DOCX document
36E77618R0005-042.pdf PDF
36E77618R0005-048.pdf PDF
36E77618R0005-035.pdf PDF
36E77618R0005-029.pdf PDF
36E77618R0005-046.pdf PDF
36E77618R0005-047.pdf PDF
36E77618R0005-033.pdf PDF
36E77618R0005-038.pdf PDF
36E77618R0005-039.pdf PDF
36E77618R0005-028.pdf PDF
36E77618R0005-049.pdf PDF
36E77618R0005-040.pdf PDF
36E77618R0005-027.docx DOCX document
36E77618R0005-044.pdf PDF
36E77618R0005-043.pdf PDF
36E77618R0005-041.pdf PDF
36E77618R0005-036.pdf PDF
36E77618R0005-024.docx DOCX document
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT J-4

DELIVERABLES

Pre-award Deliverables Sample:

Item Deliverable Frequency Due

1 Preliminary Assessment One time Per contractor schedule

2 30% IGA One time Per contractor schedule

3 60% IGA One time Per contractor schedule

4 95% IGA One time Per contractor schedule

Final

IGA/

Proposal

One time Per contractor schedule

Post-award Deliverables:

Item Deliverable Frequency Due

Signed Contract One time Upon Receipt from agency

2 OPM Data One Time Upon contract award

Certificate of Insurance One time 15 days after award

4 Performance Bond One time 30 days after award

5 Payment Bond One time 30 days after award

6 Project Schedule (CPM) Bi-Weekly Award Kick-off meeting and subsequent project calls.

Completed SF1413 and Subcontract Signed Agreements

One Time Per 52.222-11 – completed SF1413 within 14 days of awarded subcontract

8 Submittal Log Quarterly Update Initial Due at Award Kick-off.

9 Work Schedule Monthly 10 days before work start

10 Work Outside Normal Hours Per occurrence 5 days before work start

Design and Construction Package

Per ECM/Facility Due date based on proposal and negotiations days after award

ECM

Installation Quality control Inspection Program

One time Due date based on proposal and negotiations days after award

Commissioning Plan One time After Approval of item 11 above

Safety and Health Plan One time

Due date based on proposal and negotiations days after award

Notification of Utility Interruption

Per occurrence 15 working days prior to outage

16 Payrolls Weekly Due date based on proposal and negotiations days after award

17 Daily Logs Daily Due date based on proposal and negotiations days after award

18 Incident Reports As-Required.

Due date based on proposal and negotiations days after award

19 RFI Log As-Required, Monthly Updates

Due date based on proposal and negotiations days after award

Operation Work Procedure

As-Required With training class

Maintenance Work Procedure and Maintenance Work Requirements and Checklist

One time With training class

O&M Manuals and Spare Parts Lists

One time Prior to agency acceptance of project

Warranty Log and a copy of each Warranty

One time Prior to agency acceptance of project

Commissioning Report One time Upon ECM installation and commissioning

Post- Installation Report

One time Prior to Government’s acceptance

As-built Drawings Per ECM Prior to Government’s acceptance

27 First Year - M&V Reports Quarterly Due date based on proposal and negotiations days after award

Annual M&V Report on ECM Performance

Annual As agreed upon in the IGA

29 Modifications Per modification Upon receipt of signed modification