ES101 - Electrical Site Plan.pdf

PDF 2 MB Posted

Attached to
Y1PZ--810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton National Cemetery
Solicitation number
36C78626B0007
Issued by

About this file

Electrical Site Plan Summary

This is an electrical site plan drawing for a 250kW diesel generator installation at the Dayton National Cemetery Expansion project. The plan depicts the layout and routing of electrical infrastructure, including generator placement, automatic transfer switch (ATS) installation, conduit runs, and utility connections across the facility grounds.

The project requires installation of a 250kW diesel generator with sound-attenuating enclosure and integral diesel underbelly tank, a 208V, 800A, NEMA 4 pad-mounted automatic transfer switch rated for service entrance use, and associated electrical distribution components. Key requirements include providing a 4'x4' traffic-rated manhole, installing an Emergency Power Off (EPO) device to control fuel dispensing pumps per NEC Article 514.11(a), grounding and bonding of equipment per NEC Article 514.16, and locating the generator annunciator panel in the maintenance bay. The electrical contractor is responsible for verifying all utility locations before excavation, repairing all disturbed surfaces to match existing conditions, sealing wall penetrations to maintain watertight ratings, and disconnecting and removing existing service conductors with coordinated downtime. Temporary generator service is specified during the service outage required for installing new service conductors. All underground utilities must be precisely located and properly compacted during backfill operations.

View the file

Other files

File Type Posted
36C78626B0007 0003.docx DOCX document
CG108 GRADING and DRAINAGE PLAN - PPC SECTION 51.pdf PDF
CD112 DEMOLITION PLAN - PPC SECTION 51.pdf PDF
CG106 GRADING and DRAINAGE PLAN - PPC SECTIONS 48 and 52.pdf PDF
LS400A.pdf PDF
LS204.pdf PDF
Revised Davis Bacon Wage Determination_Heavy_OH20260001 06252026.pdf PDF
LS401.pdf PDF
CG100.pdf PDF
CD111 DEMOLITION PLAN _ PPC SECTION 49 and 50.pdf PDF
LS402.pdf PDF
10 14 00 Exterior Signage.pdf PDF
S001.pdf PDF
LS301.pdf PDF
CS502 SITE DETAILS - 2.pdf PDF
01 43 39 Mockup Requirements.pdf PDF
Revised Davis Bacon Wage Determination_Building_OH20260093 05182026.pdf PDF
LS400B.pdf PDF
36C78626B0007 0002.docx DOCX document
36C78626B0007 0001.docx DOCX document
Prebid Site Visit Attendance Record_20260612.pdf PDF
LS200_Pages from 18125 DNC_BID_20260211.pdf PDF
LS300_Pages from 18125 DNC_BID_20260211.pdf PDF
Davis Bacon Wage Determination _ Building _ OH20260093 01022026.pdf PDF
Bid Drawings Volume 3 of 14_C LOGI DEMO_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 1 of 14_GEN SURV_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
36C78626B0007_1.docx DOCX document
Davis Bacon Wage Determination _ Heavy _ OH20260001 01022026.pdf PDF
Bid Specifications 810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 11 of 14_C GRADE UTIL_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 12 of 14_L PLANTING_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 6 of 14_L SITE PRECAST_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 5 of 14_C GRAVESITE_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 2 of 14_C BORING_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 8 of 14_L CAPS ADDRESSING_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 14 of 14_STRUC ELECT_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 13 of 14_IRRIGATION_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 10 of 14_L SECTIONS DETAILS_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 9 of 14_L ELEVATIONS_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Bid Drawings Volume 7 of 14_L FLATWORK_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
VAAR 852.219-75 VA Notice of Limitations On Subcontracting Certificate.docx DOCX document
IFB Cost Estimate Worksheet.xlsx XLSX spreadsheet
Bid Drawings Volume 4 of 14_C SITE_810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Statement of Work 810CM3033 Gravesite Expansion with FCA Deficiencies at Dayton NC.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

J J

J

J

J

937937

937 938938

933 933

928929

1931931

933934

92993

94194

928929

991191

92392

911912

G

R

A

V

E

L

G R A V E L A R E A

EDGE OF GRAVEL

EDGE OF GRAVEL

G R A V E L

P A T H

G R A V E L P A T H

EDGE OF GR

AVEL

E D G E

O F G R A V E L

SECTION 15

SECTION 13

SECTION 12

SECTION 17

SECTION 19B SECTION 19A

SECTION 19

SECTION 6 SECTION 5

SECTION 2

SECTION A

SECTION G

SECTION I

SECTION R

SECTION 18B

MEMORIAL

SECTION

A

MEMORIAL

SECTION

B

MEMORIAL

SECTION

C

SECTION 9 SECTION8 SECTION 7

SECTION 14

SECTION 16

SECTION 18

SECTION 4

SECTION 3

SECTION 1

SECTION 11

CIVILIAN SECTIO

N

SECTION 18C

SECTION P

SECTION Q

SECTION 10

SECTION N

SECTION M

SECTION L

SECTION K SECTION H

SECTION F

SECTION E

SECTION D

SECTION C

SECTION B

SECTION S

SECTION I

OP

OQ

O

O

O

O

SECTION 20

SECTION 25

SECTION 21

SECTION 24

SECTION 26

SECTION 37

SECTION 36

SECTION 38

SECTION 39

SECTION 40

SECTION 41

SECTION 42

SECTION 28

SECTION 27

SECTION 29

SECTION 30

SECTION 31

SECTION 33

SECTION 34

SECTION 35

SECTION 46

SECTION 32

G A R A G E

D A K O T A

T E X A S

A V E N U E

A V E N U

E

A V E N U E

M C M A H O N

A V E N U E

W E S T 3 R

D S T R E E

T

M I C H I G A N

A V E N U E

N E W M E X I C O

P L A C E

C O L O R A D O

O H I O

A V E N U E

O H I O

A

V E N

U E

O H I O

A V E N U E

SIG

N (

MC

MA

HO

N&

CO

LOR

ADO

CP #200002

N=641130.385 E=1472091.638

ELEV=945.32

CP #200801

N=640509.937 E=1473258.453

ELEV=924.25

SAN. SEWER MANHOLE

RIM = 936.61

INV E 12" - 15" VCP = 925.75

INV SE 8" VCP = 931.08

INV S 12" - 15" VCP = 926.07

STRUCTURE BOTTOM = 925.75

SAN. SEWER MANHOLE

RIM = 935.62

INV NE 12" - 15" VCP = 924.48

INV W 12" - 15" VCP = 924.65

STRUCTURE BOTTOM = 924.48

SAN. SEWER MANHOLE

RIM = 929.18

INV NE 12" VCP = 920.32

INV SW 12" VCP = 920.55

STRUCTURE BOTTOM = 920.32

SAN. SEWER MANHOLE

RIM = 939.42

INV W 12" VCP = 927.36

INV NE 12" VCP = 927.36

STRUCTURE BOTTOM = 927.36

SAN. SEWER MANHOLE

RIM = 938.65

INV E 12" VCP = 929.12

INV SW 12" VCP = 929.20

STRUCTURE BOTTOM = 929.12

SAN. SEWER MANHOLE

RIM = 921.32

TOP NW 18" VCP = 919.22' (NOT OPEN)

INV NORTH 12" VCP = 913.37

INV NE 18" VCP = 912.26

TOP SE 18" VCP = 919.22 (NOT OPEN)

INV SW 18" VCP = 912.26

STRUCTURE BOTTOM = 912.26

SAN. SEWER MANHOLE

RIM = 922.26

INV NE 18" VCP = 916.56

INV SW 18" VCP = 916.56

STRUCTURE BOTTOM = 916.56

SAN. SEWER MANHOLE

RIM = 931.69

INV NW 12" VCP = 926.84

INV NE 18" VCP = 926.29

INV SW 18" VCP = 926.29

STRUCTURE BOTTOM = 926.29

SAN. SEWER MANHOLE

RIM = 931.54

INV WEST 8" VCP = 926.89

INV SE 12" VCP = 926.89

INV SW 12" VCP = 926.89

STRUCTURE BOTTOM = 926.89

SAN. SEWER MANHOLE

RIM = 917.24

INV NE 18" VCP = 908.84

INV SW 18" VCP = 910.67

STRUCTURE BOTTOM = 908.84

SAN. SEWER MANHOLE

RIM = 939.45

INV NORTH 15" VCP = 933.19

INV NE 15" VCP = 933.21

INV EAST 15" VCP = 932.71

INV SOUTH 15" VCP = 932.71

STRUCTURE BOTTOM = 932.71

TOP OF 4" NE & SW = 936.06

SAN. SEWER MANHOLE

RIM = 943.16

INV NE 8" VCP = 937.32

INV SW 8" VCP = 937.32

BOTTOM OF STRUCTURE = 937.32

SAN. SEWER MANHOLE

RIM = 914.39

INV NORTH 6" PVC = 903.89

INV NE 8" PVC = 903.54

INV SW 8" VCP = 903.79

STRUCTURE BOTTOM = 903.54

SAN. SEWER MANHOLE

RIM = 903.62

INV NORTH 8" VCP = 897.35

INV SOUTH 8" VCP = 897.38

INV SW 8" VCP = 897.84

STRUCTURE BOTTOM = 897.35

SAN. SEWER MANHOLE

RIM = 911.32

NV NORTH = 898.45

INV SOUTH 8" VCP = 898.45

STRUCTURE BOTTOM = 898.45

BRICKS MISSING ON WEST SIDE

10.50' BELOW NO PIPE VISIBLE

SAN. SEWER MANHOLE

RIM = 925.55

INV NW 18" VCP = 915.84

INV SOUTH 18" VCP = 915.74

INV SW 12" VCP = 917.76

INV WEST 8" VCP = 920.20

STRUCTURE BOTTOM = 915.74

SAN. SEWER MANHOLE

RIM = 899.66

INV NORTH (SEALED PIPE)

INV NW 12" VCP = 895.11

INV SOUTH 12" VCP = 895.16

STRUCTURE BOTTOM = 895.11

SAN. SEWER MANHOLE

RIM = 899.46

INV NORTH 8" PVC = 894.71

INV SE 8" PVC INSIDE OF 12" PVC = 894.81

STRUCTURE BOTTOM = 894.71

CURB INLET

RIM = 927.45

INV NORTH 8" VCP = 926.00

INV SOUTH 8" VCP = 925.87

STRUCTURE BOTTOM = 925.85

CURB INLET

RIM = 927.40

INV WEST 8" VCP = 925.97

INV SOUTH 8" VCP = 925.95

STRUCTURE BOTTOM = 925.65

CURB INLET

RIM = 917.67

INV NORTH 8" VCP = 916.25

INV SOUTH 8" VCP = 916.16

STRUCTURE BOTTOM = 916.02

CURB INLET

RIM = 917.52

INV SOUTH 8" VCP = 916.11

STRUCTURE BOTTOM = 916.04

CURB INLET

RIM = 914.77

INV SOUTH 8" VCP = 913.34

STRUCTURE BOTTOM = 913.09

CURB INLET

RIM = 914.84

INV NORTH 8" VCP = 913.41

INV SOUTH 8" PVC = 913.27

STRUCTURE BOTTOM = 913.08

STORM INLET

RIM = 914.85

INV NORTH 8" PVC = 912.60

INV NE 18" PVC = 908.00

INV SE 12" VCP = 910.65

INV SW 4" HDPE = 910.40

INV WEST 18" PVC = 908.02

STRUCTURE BOTTOM = 908.00

INLET

RIM = 914.16

INV NORTH 6" HDPE = 912.81

STRUCTURE BOTTOM = 912.58

CURB INLET

RIM = 913.41

INV NW 6" VCP = 911.88

STRUCTURE BOTTOM = 911.36

STORM INLET

RIM = 952.89

INV E 8" HDPE = 949.69

STRUCTURE BOTTOM = 949.47

STORM INLET

RIM = 934.04

INVV SE 12" RCP = 930.05

STRUCTURE BOTTOM = 930.05

STORM INLET

RIM = 933.99

INV NW 12" RCP = 929.88

INV SE 12" RCP = 929.88

STRUCTURE BOTTOM = 929.88

STORM INLET

RIM = 924.67

INV W 6" PVC = 922.60

INV S 12" RCP = 922.53

STRUCTURE BOTTOM = 922.42

STORM SEWER MANHOLE

RIM = 923.42

INV N 12" RCP = 917.20

INV E 24" RCP = 916.24

INV W 24" RCP = 916.27

CURB INLET

RIM = 923.31

INV W 12" RCP = 920.79

STRUCTURE BOTTOM = 920.79

STORM INLET

RIM = 923.84

INV W 12" RCP = 919.25

INV E 12" RCP = 919.76

STRUCTURE BOTTOM = 919.25

STORM INLET

RIM = 941.01

INV S 12" RCP = 936.30

STRUCTURE BOTTOM = 936.30

STORM INLET

RIM = 940.18

INV W 24" RCP = 935.63

INV NE 24" RCP = 932.00

STRUCTURE BOTTOM = 932.00

STORM SEWER MANHOLE

RIM = 940.18

INV N 24" RCP = 930.28

INV E 4" VCP = 935.10

INV S 24" VCP = 930.35

INV SW 24" RCP = 931.38

STRUCTURE BOTTOM = 930.28

STORM INLET

RIM = 932.53

INV NW 12" VCP = 929.12

INV N 12" VCP = 929.11

INV SE 12" VCP = 929.10

STORM INLET

RIM = 930.57

INV NW 12" VCP = 927.32

INV SE 12" VCP = 927.32

STRUCTURE BOTTOM = 927.32

BEEHIVE INLET AT RIM

RIM = 931.19

INV NW 12" VCP = 927.20

INV E 12" VCP = 927.20

INV S 8" VCP = 928.74

STRUCTURE BOTTOM = 927.20

STORM SEWER MANHOLE

RIM = 933.85

INV NE 24" VCP = 927.23

INV SW 24" VCP = 927.50

STRUCTURE BOTTOM = 927.23

STORM SEWER MANHOLE

RIM = 932.85

INV NE 24" VCP = 925.31

INV SW 24" VCP = 925.59

INV W 12" VCP = 926.02

STRUCTURE BOTTOM = 925.31

STORM SEWER MANHOLE

RIM = 926.88

INV N 12" RCP = 922.35

INV NE 24" VCP = 919.73

INV SW 24" VCP = 919.82

STRUCTURE BOTTOM = 919.73

STORM SEWER MANHOLE

RIM = 924.23

INV N 12" RCP = 919.58

INV E 24" RCP = 916.89

INV SE 12" RCP = 918.21

INV W 24" RCP = 916.98

STRUCTURE BOTTOM = 916.89

STORM SEWER MANHOLE

RIM = 910.80

INV SW 18" PVC = 902.60

INV E 30 RCP = 902.60

STORM SEWER MANHOLE

RIM = 910.39

INV SW 30" RCP = 902.09

STORM INLET

RIM = 906.18

INV NW 6" HDPE = 904.98

INV SE 6" HDPE = 904.98

STRUCTURE BOTTOM = 904.98

STORM INLET

RIM = 917.21

INV NW 4" HDPE = 914.03

INV NE 15" VCP = 914.21

INV SE 15" VCP = 914.28

STRUCTURE BOTTOM = 913.35

ST

OR

M

INL

ET

RIM

21.

INV

N

OR

TH

T O 15"

C

UT

O

UT

19.

ST

RU

CT

UR

E

BO

TTO

M

.78

SAN SEWER MH

RIM = 923.04

INV NE 18" VCP = 914.49

INV SE 12" RCP = 919.79

INV SW 18" VCP = 917.04

INV SW 8" VCP = 917.54

STRUCTURE BOTTOM = 914.49

CURB INLET

RIM = 922.84

INV NW 12' RCP = 919.59

STRUCTURE BOTTOM = 919.59

STORM INLET

RIM = 926.31

INV NW 12" RCP = 922.56

STRUCTURE BOTTOM = 922.56

STORM SEWER MANHOLE

RIM = 926.31

INV NW 8" HDPE = 920.26

INV NE 18" VCP = 919.01

INN SE 12" RCP = 921.81

INV SW 18" VCP = 919.18

STRUCTURE BOTTOM = 919.01

STORM INLET

RIM = 925.86

INV NW 6" VCP = 923.56

STRUCTURE BOTTOM = 923.56

STORM INLET

RIM = 931.89

INV WEST 12" RCP = 929.59

STRUCTURE BOTTOM = 929.59

STORM INLET

RIM = 932.17

INV NW 12" RCP = 928.97

INV EAST 12" RCP = 929.17

STORM INLET

RIM = 931.92

INV NW 12" RCP = 927.82

INV SE 12" RCP = 927.92

STRUCTURE BOTTOM = 927.82

STORM SEWER MANHOLE

RIM = 931.97

INV WEST 12" VCP = 923.47

INV NE 24" VCP = 922.47

INV SE 12" VCP = 927.22

INV SW 24" VCP = 922.47

STRUCTURE BOTTOM = 922.47

STORM INLET

RIM = 937.86

INV SOUTH 15" CMP = 934.60

STRUCTURE BOTTOM = 934.37

CURB INLET

RIM = 926.05

INV EAST 8" VCP = 923.45

STRUCTURE BOTTOM = 923.45

STORM INLET

RIM = 898.59

INV NW 24" RCP = 890.04

INV N 12" VCP = 890.01

INV SE 24" RCP = 889.78

STRUCTURE BOTTOM = 889.78

CURB INLET

RIM = 901.11

INV N 12" HDPE = 896.01

STRUCTURE BOTTOM = 896.01

STORM INLET

RIM = 932.93

INV S 12" RCP = 929.57

STRUCTURE BOTTOM = 929.57

STORM INLET

RIM = 936.40

INV W 12" VCP = 930.15

INV E 12" VCP = 930.15

STRUCTURE BOTTOM = 930.15

STORM SEWER MANHOLE

RIM = 935.19

INV W 12" VCP = 925.41

INV E 12" VCP = 925.09

STRUCTURE BOTTOM = 925.09

TERMINUS OF PIPE UNKNOWN

STORM INLET RIM = 934.49

INV N 12" RCP = 932.04

INV W 8" HDPE = 932.42

STRUCTURE BOTTOM = 931.74

STORM INLET

RIM = 918.00

STRUCTURE IS FULL OF DEBRIS

INLET IS NOT ACCESSIBLE

STORM INLET

RIM = 925.39

INV WEST 8" VCP = 922.34

STRUCTURE BOTTOM = 922.34

I.P.

WSV

WSV

WSV

S

TM

S

TM

CB

S A N

G A S

SAN

MH

SAN

MH

S

TM

CB

12"

STM

GV

WV

FH

WSV

WSV

TELE

MH

WSV

GSV

WM

WSV

STM

MH

CB

PULL

BOX

CB

PULL

BOX

GSV

WSV

WM

WSV

GSV

FH

PULL

BOX

CB

GAS

G A S

12" 12"

CB

CB

STM

MH

STM

MH

S

TM

S

TM

12"

STM

PULL

BOX

INV 12" N 874.79

INV 12" W 875.44

TOP CB 878.89

887.8

897.6

893.9 893.6

CB

X-WALK

RISER

X-WALK

RISER

TRAFFIC

PED

L

P

L

P

P

S

S

S

L

P

L

P

P

P

L

L

L

L

P

P

T

P

L

BROWN AVE.

COLORADO AVE

PE

NN

SY

LV

AN

IA

A

VE

TEXAS AVE.

MICHIGAN AVE.

W. THIRD ST.

HA

W

AI

I P

L

OHIO AVE.

925.500 Columbarium Survey Point

PPC

PPC

PPC

PPC

IGC

TRAD

33A

PPC

R O

C K

C O

N

STR

U C

TIO

N

EN

TR

A N

C E

NEW CONTRACTOR

LAYDOWN YARD

N=641549.23 E=1473963.51

N=641535.14 E=1473932.38

N=641528.27 E=1473896.39

N=641529.37 E=1473859.47

N=641215.72 E=1472467.76

N=641248.59 E=1472436.09

N=641277.95 E=1472467.76

N=641282.34 E=1472539.01

N=641248.59 E=1472570.26

N=641230.72 E=1472539.01

N=13.40E=13.42

N=641156.56 E=1471990.42

N=641175.43 E=1471999.33N=641172.38

E=1471976.81

TABLES / SCHEDULES /

LEGENDS

DETAILS

PROFILE

S

PLAN

CO

CO CO CO

CO

CO

CO CO

CO

CO

CO CO

CO CO

CO

CO CO

CO

CO

CO

CO

CO

CO CO

CO

CO

CO CO COCOCOCO

CO CO CO CO

CO CO

CO

COCOCOCO

CO CO CO CO

CO CO

CO

CO CO

CO

CO CO CO CO

CO

CO

CO

CO

CO

CO CO

CO

CO

COCO

CO

CO

CO

CO

CO

CO

COCO

CO

CO

EXISTING MEDIUM VOLTAGE

TRANSFORMER

'T-34'

EX MDP

PO

RT

AB

LE

0k

W

DIE

SE

L G

EN

ER

AT

OR

E9

PANEL RR

J E10

E3

UE

UE

UE

UE

UE

UE

EPO

GEN EPO

PANEL RR-33

E4

E5

FUEL PUMP

PANEL RR-28

FUEL PUMP

PANEL RR-32

FUEL EPO

PANEL RR-36

E7

UE

UE

UE

E1

NEW 250KW

GENERATOR

HEATER

PANEL RR-29

BATTERY CHARGER

PANEL RR-31

E8

EPO

UE

UE

E6

ATS HEATER

PANEL RR-35

E2

WP

WP

ELECTRICAL GENERAL NOTES

A.

B.

C.

D.

E.

F.

G.

UNDERGROUND DUCTS AND CONDUITS SHALL BE ENCASED IN CONCRETE. DIRECT

BURIAL CONDUIT MAY BE USED FOR OUTDOOR LIGHTING AND POWER BRANCH

CIRCUITS 600V AND LESS.

UTILITIES SHOWN ARE INDICATED SCHEMATICALLY. CONTRACTORS SHALL VERIFY

ALL DEPTHS AND ALL LOCATIONS/DIMENSIONS PRIOR TO EXCAVATING. ALL

UTILITIES MAY NOT BE SHOWN.

REFER TO CIVIL DRAWINGS FOR ADDITIONAL INFORMATION ON EXISTING AND NEW

SITE CONDITIONS INCLUDING UTILITES.

ALL UNDERGROUND UTILITIES, PIPING, ETC. SHALL BE LOCATED EXACTLY BEFORE

DIGGING.ANY BACKFILL SHALL BE TAMPED AND COMPACTED TO PREVENT FUTURE

SETTLING. ALL EXCESS DIRT SHALL BE CLEARED FROM THE AREA AND DISPOSED

OF.

ELECTRICAL CONTRACTOR SHALL REPAIR ALL DISTRUBED SURFACES SUCH AS

SIDEWALKS, DRIVEWAYS, STREETS, GRASS, AND CONCRETE. REPLACED SURFACES

SHALL MATCH EXISTING.

CONTRACTOR IS RESPONSIBLE FOR DOING ALL WORK PER LOCAL RESPECTIVE

UTILITY REQUIREMENTS.

VERIFY EXACT LOCATIONS OF UTILITY CONNECTIONS, PRIOR TO START OF WORK.

ELECTRICAL PLAN KEYED NOTES

NOTE: NOT ALL KEYED NOTES MAY BE USED ON EACH PLAN

E1 PROVIDE 250 kW DIESEL GENERATOR WTH SOUND ATTENUATING

ENCLOSURE AND INTEGRAL DIESEL UNDERBELLY TANK. REFER TO SHEET

E501 AND SPECIFICATIONS FOR ADDITIONAL INFORMATION.

E2

PROVIDE 208V, 800A, NEMA 4, PAD MOUNTED, SERVICE ENTRANCE RATED

3-POLE AUTOMATIC TRANSFER SWITCH. PROVIDE 120V POWER TO ATS

STRIP HEATER.

E3

EXISTING SERVICE CONDUCTORS SHALL BE DISCONNECTED AND

REMOVED. COORDINATE PHASING WITH INSTALLATION OF NEW SERVICE

ENTRANCE TRANSFER SWITCH AND TEMPORARY GENERATOR. MINIMIZE

AND COORDINATE ANY REQUIRED DOWNTIME WITH OWNER.

E4 ALL PENETRATIONS THROUGH WALL SHALL BE SEALED TO BE

WATERTIGHT AND MAINTAIN EXISTING RATINGS.

E5 LOCATE GENERATOR ANNUNCIATOR PANEL IN MAINTENACE BAY IN

ACCESSIBLE LOCATION.

E6

PROVIDE AND LABEL EPO DEVICE TO SHUT-OFF FUEL DISPENSING PUMPS

(GAS AND DIESEL) IN ACCORDANCE WITH NEC ARTICLE 514.11(A). EPO

SHALL SHUT OFF CIRCUIT BREAKERS VIA SHUNT TRIP.

E7

POWER TO EXISTING FUEL TANK SHALL BE DISCONNECTED AND REMOVED.

REFER TO SHEET CO100 FOR DETAILS ON TEMPORARY FUEL TANK

LOCATION AND SCOPE. EXISTING CIRCUITS MAY BE REUSED IF

DETERMINED FEASIBLE DURING CONSTRUCTION. INSTALL GROUND RODS

WITH 4/0 COPPER INSULATED WIRE. BOND THE TRANK FRAME TO THE

GROUNDING RODS USEING BARE 4/0 COPPER WIRE. GROUND AND BOND

PER NEC ARTICLE 514.16 AND MANUFACTURERS INSTALLATION

INSTRUCTIONS.

E8 PROVIDE 4'x4' MANHOLE WITH TRAFFIC RATED LID. SEE PHASING NOTES

FOR ADDITIONAL INFORMATION.

E9

PROVIDE 250KW, 208Y/120V, DIESEL PORTABLE GENERATOR WITH 800A

CIRCUIT BREAKER FOR TEMPORARY POWER DURING SERVICE OUTTAGE

REQUIRED FOR INSTALLING NEW SERVICE CONDUCTORS.

E10

TEMPORARY SERVICE CONDUCTORS SHALL BE ROUTED OVERHEAD TO

WALL ADJACENT TO MDP. ROUTE CONDUIT DOWN WALL AND INTO SIDE OF

MDP CONNECTING TO BUS ON LINE SIDE OF MAIN CIRCUIT BREAKER.

PROVIDE JUNCTION BOX AS REQUIRED. SEE PHASING NOTES FOR

ADDITIONAL DETAILS.

ELECTRICAL SERVICE PHASING

NOTES

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

INSTALL NEW GENERATOR AND AUTOMATIC TRANSFER SWITCH. PREPARE FOR

SERVICE CONNECTIONS.

PROVIDE TEMPORARY 250KW GENERATOR WITH 800A CIRCUIT BREAKER.

DISCONNECT POWER TO MDP FROM TRANSFORMER T-34 AFTER ISOLATING

POWER AND REMOVE SERVICE CONDUCTORS.

CONNECT TEMPORARY GENERATOR TO MDP. POWER SHALL BE ROUTED FROM

GENERATOR TO MDP AND CONNECTED TO THE LINE SIDE OF THE MAIN CIRCUIT

BREAKER.

TRENCH AND EXPOSE SERVICE ENTRANCE CONDUITS AND PATH TO TRANSFER

SWITCH.

CUT CONDUITS, PROVIDE SLIP FITTINGS, AND INSTALL NEW MANHOLE.

ROUTE CONDUITS FROM HANDHOLE TO NEW TRANSFER SWITCH.

PULL NEW SERVICE AND GENERATOR CONDUCTORS TO TRANSFER SWITCH.

PREPARE TO PULL CONDUCTORS FROM TRANSFER SWITCH TO MDP.

PULL NEW SERVICE CONDUCTORS FROM TRANSFORMER TO ATS AND FEEDER

FROM ATS TO MDP.

DISCONNECT TEMPORARY GENERATOR AND PULL NEW SERVICE CONDUCTORS

FROM ATS TO MDP.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

PhaseDESIGNER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

DAYTON NATIONAL CEMETERY

GRAVESITE EXPANSION

BID DOCUMENTS

4400 W THIRD ST. DAYTON, OH 45428

810CM3033

BID DOCUMENTS

C :\U se rs

\a w eb er

\D oc um en ts \1

_D ay to n

N C

A_ E_

R

_a w eb er

S4

6.

rv t 7/

6/

1:

:4

AM

ES101

ELECTRICAL SITE PLAN

FEBRUARY 5, 2026 WH ATW

Project Number

1/8" = 1'-0"1 ELECTRICAL SITE PLAN

Revisions: Date:

ADDENDUM 2 7/8/26

2 ADDENDUM 2

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

DESIGNER OF RECORD STAMPCONSULTANT

Project NumberRevisions: Date:

ARCHITECT/ENGINEER OF RECORDCONSULTANTS

Revisions:

1 3 6 0 5 1 s t A v e . N . # 1 0 0 P l y m o u t h , M N 5 5 4 4 1 P 7 6 3 . 4 1 2 . 4 0 0 0 | F 7 6 3 . 4 1 2 . 4 0 9 0 | a e - m n . c o m Anderson Engineering of Minnesota, LLC | Proj # 18125Date:

GEOTECHNICAL

TERRACON

JEFF DUNLAP, PE

IRRIGATION

WATER IN

MOTION, INC.

TIMOTHY MALOOLY

COST ESTIMATING

OCMI

KYLE VEATER

175 James Avenue North Minneapolis, MN 55405 952.229.1911

611 Lunken Park Drive Cincinnati, Ohio 45226 513.612.9020

2100 North Greenville Ave. Richardson, Texas 75082 469.431.0571

U.S. Department of Veterans Affairs

Office of Design and Construction

Services

AMENDMENT 02 7/8/20262

1/8" = 1'-0"1 ELECTRICAL SITE PLAN

File details come from the government source that posted it. Updated .