Attachment 01 S05 - Tech Questions Tracker.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Y1DA--586-401 | Construct CLC Residential Neighborhood | Jackson, MS | Scott Tom
Solicitation number
36C77626B0023
Issued by

About this file

This is a Technical Questions Tracker documenting 80 questions and answers submitted by contractors during the solicitation period for a construction project at the VA facility in Jackson, Mississippi (Solicitation 36C77626B0023).

The project involves constructing a Clinical Learning Center residential neighborhood addition and includes structural work, mechanical/electrical systems integration, site utilities, asbestos abatement in connection areas, ICRA containment requirements, and approximately 29 drilled bell piers with minimum 3-foot embedment into competent clay. Key contractual requirements include: the project is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) with bonding requirements that must be met through SDVOSB or approved SBA/VA Mentor-Protégé partnerships; pricing is firm fixed price with no economic price adjustment clause; all state and local sales taxes are the contractor's responsibility; Notice to Proceed is anticipated within 90 calendar days of award; contractor personnel require VA PIV badging; design team members are precluded from serving as prime contractor, mentor-protégé partner, or subcontractor on the construction phase; and work occurs in two phases with potential after-hours utility connection outages. The tracker clarifies that drilled pier depths are not provided at bid but shall be determined per geotechnical report parameters; retaining wall design responsibility rests with the contractor for bidding purposes but final design parameters must be confirmed by the geotechnical engineer prior to construction; temporary HVAC and mobile SPS are not required; and unarmed guards are not required despite specification language.

View the file

Other files

File Type Posted
Attachment 01 C - FAR Clause 52.212-4 - Construction KAE.docx DOCX document
36C77626B0023 0007.docx DOCX document
Attachment 01 S05 - Tech Questions Tracker w clarifications v1.xlsx XLSX spreadsheet
36C77626B0023 0006.docx DOCX document
Attachment 02 23-060_Addendum 02 Door Tags Locations.pdf PDF
Attachment 01 Asbestos AHERA Baseline Survey--February 2017.pdf PDF
36C77626B0023 0005.docx DOCX document
Attachment 09 A-104 Cubicle Curtains.pdf PDF
Attachment 06 M-503.pdf PDF
Attachment 03 107315 Extruded Alum Canopy.pdf PDF
Attachment 08 M-601.pdf PDF
Attachment 07 M-504.pdf PDF
Attachment 05 117300 Ceiling Pt. Lift System.pdf PDF
Attachment 04 331000 Water Utilities.pdf PDF
Attachment 02 051200 StructSteelFraming.pdf PDF
36C77626B0023 0004.docx DOCX document
36C77626B0023 0003.docx DOCX document
36C77626B0023 0002.docx DOCX document
GeoReport.VA CLC Neighborhood - Jackson MS.EB245012_locked_.pdf PDF
S04 Site Visit Sign in Sheet 36C77626B0023.pdf PDF
36C77626B0023 0001.docx DOCX document
S02 36C77626B0023_1 Final.pdf PDF
Attachment 06 - Site Visit Details.docx DOCX document
Attchment 1 23-060 Specs 100 percent SS 20250618 Final.pdf PDF
Attachment 05 Wage Determination Hinds County MS 05_28_2026.pdf PDF
Attachment 04- Limitations on Subcontracting - Construction.pdf PDF
Attachment 3 P11 Vol2 Drawings SS Final.pdf PDF
Attachment 2 P11 Vol1 Drawings SS Final.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

PROJECT TITLE: Construct CLC, Jackson MS
#RECEIVEDANSWEREDCONTRACTOR QUESTIONVA RESPONSEA/E RESPONSE
1Will the government pay for materials stored per VAAR 852.232-70 and FAR 52.232-5? We have experienced PCAC Contracting Officers refusal to pay for materials stored on site during these periods of material shortages and the need to expedite procurement of materials when available to meet schedule obligations and prevent project delays. This is an important factor in preparing Price proposals.In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves.
2Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor-Protégé partner, or subcontractor.Any member of the design team of this project is not permitted to be part of the construction team.
3Please confirm that this project is a competitive SDVOSB set-aside and that any bonding provided by a contractor must be through a SDVOSB or SBA/VA APPROVED Mentor-Protégé partnership under the SBA/VA Mentor- Protégé program in which the partnership has been approved prior to the due date.This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
4Please confirm that a large business not part of an SBA/VA APPROVED Mentor-Protégé team under the VA Mentor- Protégé program cannot provide a bid guarantee or a payment & performance bond for a SDVOSB.This project is set aside for SDVOSBs. The bonding requirements must be met for this project per the applicable clauses, provisions, and instructions to offerors.
506/18/2026When visiting the link, I noticed the project was “set aside for Service-Disabled Veteran Owned Small Business” – does this mean that General Contractors cannot bid the project unless they meet that requirement?Yes, this project is a 100% set-aside for SDVOSBs. The prime contractor submitting the offer must be certified as such in the SBA VetCert database.
606/18/2026Is this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate?No. See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes in the solicitation. It is solely the responsibility of the offeror to include all state and local sales or use taxes for construction materials, and all other applicable taxes, in their bid or proposal price.
706/18/2026Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes.Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card. PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp

Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site.

806/18/2026How soon after award is NTP expected to be issued?The Government anticipates issuance within 90 calendar days after award.
906/18/2026Will the VA allow deviations to Buy American Act if the noted products are not available?See the solicitation for the pertinent RFO Compliant Buy American Act Clauses and Provisions
1006/18/2026Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin.This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added.
1106/18/2026There is a section in the specifications for asbestos abatement. We have been unable to find the location or extent of asbestos material to be abated. Please adviseAsbestos risk is limited to the connection areas in Phase II and demolition for the connection of Phase I to the existing structure. The VA can provide a current asbestos survey report.
1206/18/2026Typically, existing government facilities have proprietary systems currently in use for various Division 27 and Division 28 systems. Please provide all Sole-Source Justification & Approvals. Please provide the company names, and specific point of contact for each with name, email, and phone numberDivision 27:

Nurse Call: Rauland Responder V

Division 28:

PACS: JCI/Software House iSTAR w/ C-Cure 9000 software.

SSTV: Vicon Valerus (VMS) Fire Alarm: Siemens Desigo

Reference Drawings for tie in locations.

1306/18/2026Per CS101, coded note 12 provide new 3" ductile iron underground domestic water service connection, see plumbing drawings: plumbing sheet P-401 detail 1 coded note 1 see detail 3/P502. Plumbing plans and civil plans are inconclusive on scope of work. Please provide plans and details for civil water line work, including specifications, connection details, depth of existing, for example is a water box required, is a shut off required, etc.Please refer to spec 33 10 00 provided
1406/18/2026Will there be a spec provided for the patient lifts shown on sheet QH-101?Will be issued with addendum
1506/18/2026Will the Government consider including and Economic Price Adjustment (EPA) clause to address significant fluctuations in material pricing.RFI answered #10
1606/18/2026How soon after contract award does the government anticipate issuing the official notice to proceed?RFI answered #8
1706/18/2026Will TB Screening and testing be a requirement for this project?Yes this will be required.Required by spec 01 35 26 part 1.16.
1806/18/2026Please verify the minimum number of on-site personnel that will be required to fulfill the roles of GC superintendent, SSHO and QCM System Manager?One if he/she meets the requirements of the position.
1906/18/2026Can the superintendent take the photos, or do we need to hire a commercial photographer to do this work?Superintendent can meet the requirements.
2006/18/2026Will the owner pay for stored materials?Previously answered.
2106/18/2026Please provide the offerors the Geotechnical Report provided by Terracon Consultants dated July 24, 2024 as soon as possible, before answering any other technical questions and at least 3 weeks prior to the bid date in order for the offerors to have time to read it and provide bid pricing based on the recommendation made inside as noted on Sheet CS101 note #10Goetechnical report provided in Amendment 0002 issued 06/24/2026
2206/18/2026Can the Superintendent also be the Prime Contractor’s Commissioning Manager during commissioning?Yes
2306/18/2026Is a full-time on-site quality control manager required for this project?Yes
2406/18/2026Can the Superintendent also be the quality control manager?Yes
2506/18/2026Is a full-time on-site Safety and Health Officer required for this project?Yes
2606/18/2026Can the Superintendent also be the site safety and Health Officer?Yes
2706/18/2026Can the Superintendent be Triple hatted as the SSHO and QC Manager?Yes
2806/18/2026As is typical for most VA projects, can the QC plan be implemented by the onsite superintendent and administrated by the PM without additional staff (other than what is required for commissioning) as call for in 01 45 00.?Yes
2906/18/2026Has this funding request been approved and full funding for this project currently available to the NCO station?Full funding will be requested after final bids received and bid amount is known…
3006/18/2026Will any of this work have to be performed after hours or weekends?None anticipated unless the utility connections require outages of the hospital.
3106/18/2026Will this project be done in phases?The phases are illustrated on G-006. The majority of the project occurs as Phase I, which is the addition. Phase II is utility connections to support the addition, which may need to occur intermittenly with Phase I.
3206/18/2026Please confirm there will not be any ICRA requirements for the new addition?ICRA will be required anywhere that the addition connects to the existing building or utilities are routed and/or connected to the existing building. ICRA requirements are outlined on G-004, G005, and AD101.
3306/18/2026For work in the existing building, which openings can we use to vent our negative air to meet the ICRA requirements?

In ICRA areas that require Category B Level 1 or 2, can we use zip-walls or plastic sheeting as containment?

In any ICRA areas that require above Category B containment, can plastic wall panels be used for the ICRA walls, such as STARC Panels or Temporary Wall System’s panels?Type B Cosntruction/Project Activities can use plastic wall panels. In some cases, the COR may allow plastic sheeting, but this must be coordinated with the COR for the specific instances. for some above ceiling work in the existing space, using ICRA carts while limiting the removed ceiling tiles may be possible.
3406/18/2026Who is the manufacturer of the current Nurse Call system,

Please provide contact name and phone number for who services the current Nurse Call System,

Provide the location of the nearest existing head-end for the Nurse Call System that we can tie-in to?See item #12.
3506/18/2026Who is the manufacturer of the current Fire Alarm system.

Please provide contact name and phone number for who services the current Fire Alarm System.

Provide the location of the nearest existing head-end for the Fire Alarm that we can tie-in to?See item #12.
3606/18/2026Who is the manufacturer of the current Security and Access Control system?
Please provide contact name and phone number for who services the current Security and Access Control System?See item #12.
3706/18/2026Please confirm whether the Access Control work in this project is to be CFCI, OFCI, or OFOI?CFCI
3806/18/2026Provide the location of the nearest existing head-end for the AC/Security System that we can tie-in to?See T-101 and details on T-501.
3906/18/2026Who is the manufacturer of the current CCTV system?

Please provide contact name and phone number for who services the current CCTV System?

Please confirm whether the CCTV work in this project is to be CFCI, OFCI, or OFOI?See item #12. All new CCTV work is CFCI.
4006/18/2026Who is the manufacturer of the current Telecommunications system?

Please provide contact name and phone number for who services the current Telecommunications System?

Provide the location of the nearest existing head-end for the Telecommunications System that we can tie-in to?If the question is about Network connections for VA computers then the answer is that the VA manages their own network. See the contract drawings and specifications. If the question is about other Communications and Electronic Safety and Security equipment like Nurse Call, Fire Alarm, PACS, and SSTV, see item #12. Contact information may be given at the discretion of the VA. Nearest tie in points are shown on the contract documents.
4106/18/2026Does the CLC currently use any Real Time Location system for tracking?

If so please provide the manufacturer and contact name and phone number for who services the current RTLS System?

Provide the location of the nearest existing head-end for the RTLS System that we can tie-in to?Centrac and is in the existing CLC adjacent to project location.
4206/18/2026Who is the manufacturer of the current HVAC Controls?
Please provide contact name and phone number for who services the current HVAC Controls?Johnson Controls - Kevin Deason - 601-896-4968
4306/18/2026Who is the manufacturer of the current Building Automation System?
Please provide contact name and phone number for who services the current Building Automation System?Johnson Controls - Kevin Deason - 601-896-4968
4406/18/2026Is a Specification for Structural Steel Available?Spec 05 12 00 (Structural Steel Framing) is provided
4506/18/2026Is there any chance of uncovering hazardous materials?
If so please provide the latest hazardous materials survey report for the area of construction?Asbestos risk is limited to the connection areas in Phase II and demolition for the connection of Phase I to the existing structure. The VA can provide a current asbestos survey report.
4606/18/2026Who is the existing signage vendor for this VA?Signage Company, Takeform Architectural Graphics for room numbers and Creative Sign Systems for wayfinding
4706/18/2026Will the contractor be responsible for any permits with the City of Jackson?No city permits are anticipiated at this time.
4806/18/2026Can the VA provide installation manuals or cut sheets for the Owner Furnished Contractor Installed items?VA will not be able to provide furniture information once it is ordered. It will go out for bid; VA does not know who will get the contract at this time.
4906/18/2026When painting touch-up in the corridors, can we go doorway to doorway, or do we have to go corner to corner?Corner to corner
5006/18/2026The scheduled leaving and entering water temperatures for the chiller and the chilled water coil of the AHU are not the same. Chiller schedule indicates 44F/54F and AHU Cooling Coil Schedule indicates 42F/57F. What is the correct entering and leaving water temps for the system?LWT of the chiller heater should be used for the entering water temperature to the cooling coil. Schedule will be updated and resubmitted.
5106/18/2026Can you please provide a schematic for the layout of the AHU to ensure the desired sections/modules are provided in the desired order and configuration?Schematic will be provided on M-503.
5206/18/2026The controls schematic indicates four (4) fan array for the AHU. The notes on the AHU schedule & the Fan Schedule indicate a two (2) fan array with one VFD per fan. Which one is correct?Two fan array is correct. Drawing will be updated.
5306/18/2026The finish schedule on 090600 specs calls for metal fire extinguisher cabinets. Are these to be powder coated steel, aluminum, or stainless steel?Refer to specification section 104413, which notes it as white enamel on steel.
5406/18/2026There's a spec section for cubicle curtain tracks, however these tracks are not shown on the drawings. Where are these located if required?See Updated drawing A104 in Amendment 0004
5506/18/2026What thickness can we assume on exterior concrete demo?Unless otherwise specified, assume 4" minimum per VA sidewalk detail 2/CS501.
5606/18/2026Does the VA know of any concrete footers to expect to encounter during exterior concrete demo?None anticipated.
5706/18/2026Please provide specifications or a basis of design product for the canopy.We are providing a specification in Amendment 0004.
5806/18/2026Will the contractor be required to relocate the existing 1” steel gas line that is running under the new foundation location?Refer to note 8 on sheet CD 101.
5906/18/2026Will the contractor be required to relocate the existing L.V. Electrical that is running under the new foundation?
If so, is this electrical line owned and maintained by City of Jackson Public Works?Existing UG electrical lines serving the courtyard are to be demolished back to source. If any electrical lines feeding other equipment are found COR is to be notified. reference CD101. Refer to note 7 on sheet CD 101.
6006/18/2026Please confirm that this project is a Design-Bid-Build procurement and all design is the responsibility of the Engineer of Record and no designs will be the responsibility of the contractor?This project is a design bid build project. Design has been accomplished By Apogee and they will be awarded a CPS option for post award construction period services through closeout.
6106/18/2026Placing the retaining wall design responsibility on the Contractor creates a significant and potentially unquantifiable risk that is inconsistent with the principles of fair and equitable competition in a Design-Bid-Build procurement. Under the current solicitation, offerors are required to provide a lump-sum price for a retaining wall that is a major project element without the benefit of an approved design, geotechnical-based engineering analysis, or sufficient design criteria to accurately determine the scope, type, dimensions, materials, and construction requirements of the wall. As a result, offerors are forced to speculate regarding the final design and associated construction costs. This approach creates several concerns:

The Contractor assumes substantial liability for the adequacy and performance of the retaining wall design despite the absence of sufficient design information at the time bids are due. Please clarify if the contractor is required to obtain Errors and Omissions insurance for the design?

Offerors cannot reasonably or accurately estimate the cost of the retaining wall prior to completion and approval of the design, resulting in widely varying assumptions and pricing methodologies. Therefore the lack of a defined design basis undermines the Government's ability to obtain comparable bids and the principles underlying sealed bidding procedures. The solicitation effectively transfers significant design risk to bidders without providing the information necessary to quantify that risk, forcing offerors either to include substantial contingencies or to underprice an unknown scope. Please provide the Government's justification for assigning retaining wall design responsibility to the Contractor while simultaneously requiring firm pricing prior to completion and approval of the design?

Additionally, please explain how this approach complies with FAR requirements for fair competition, adequate specifications, and the preparation of responsive and comparable bids in a Design-Bid-Build procurement?For bidding purposes only, the Contractor shall assume conservative retaining wall design parameters where wall-specific geotechnical parameters are not provided. Final retaining wall design parameters, including lateral earth pressures, soil shear strength, bearing capacity, settlement, drainage, reinforced fill requirements, and global stability, shall be determined by the delegated retaining wall engineer and confirmed by the project Geotechnical Engineer prior to construction.The segmented retaining walls are routinely "engineered" by the manufacturers, as they are the ones who understand the limitations of their system. The extents of the retaining walls are illustrated on the drawings, which gives these manufacturers adequate ability to provide a price to the Contractors.
6206/18/2026Please provide the VA Sustainable Practice Guidelines that must be followed in designing and installing the new Automatic Irrigation System?https://vatilms.va.gov/vatilms/reports/Sustainable%20Design
6306/18/2026The contract drawings and specifications identify at least 29 drilled bell piers; however, neither the drawings nor specifications provide the required pier depths, design loads, allowable bearing criteria, or pier schedule necessary for offerors to accurately estimate the cost of this work. The cost of drilled bell piers is highly dependent upon depth, subsurface conditions, groundwater conditions, casing requirements, concrete quantities, and reinforcing steel quantities. Without knowing the assumed depth of the pier offerors are forced to make assumptions regarding a significant scope of work that prominently impacts project pricing. Please provide the following:

Assumed depth of all piers? Design loads for each pier?

Allowable bearing values and geotechnical design criteria? Soil borings showing ground water conditions?

Any information from the Geotechnical Engineer as to whether or not casings will be required?

If this information is not available, please explain how offerors are expected to develop accurate and comparable bid pricing for the drilled bell piers when the primary cost- driving factors have not been defined in the project documents. Assumed depth of all piers? As per the Geotec Report, the minimum embedment of the drilled shaft shall be 3-ft into competent unweathered Yazoo "blue" clay. The approximate elevation to top of competent unweathered Yazoo "blue" clay varies, ranges from about Elev. 312 ft to Elev. 307 ft. Design loads for each pier? the factored vertical (kip), shear (kip) and moment (kip-ft) loads for CP3, CP4, and CP5 are 120, 8,9 and 200,11,35 and 290,13, 50, respectively.

Allowable bearing values and geotechnical design criteria? See Geotec Report. Soil borings showing ground water conditions? See Geotec Report.

Any information from the Geotechnical Engineer as to whether or not casings will be required? See Geotec Report.

6406/18/2026Please confirm that the contractor is not responsible for any mobile SPS requirements?None Required
6506/18/2026Please confirm that no temporary HVAC will have to be provided during construction?No temporary HVAC will be required.
6606/18/2026Please confirm there are not blast or bullet resistant doors or windows required?Design all exterior glazed openings to meet the blast requirements of the PSRDM for Essential Facilities. Refer to specified blast design calculation requirements in sections 08 41 13 for storefronts and 08 56 53 for windows. Ballistic resistance is not required in this design. Per the PSRDM, hollow metal doors constructed with 14-ga metals meets the VA's blast requirements. Blast analysis, certification, and / or testing is not required.
6706/18/2026Can the bid date for the project be extended to provide more time for contractors?The VA does not anticipate extending the solicitation close date; however, please continue to monitor SAM.gov.
6806/18/2026Can a second round of RFIs be submitted once the initial RFI answers are provided as usually these answers call for more clarifications in most cases?The VA does not anticipate a second round of RFIs.
6906/18/2026Please advise the meaning of designation on partitions marked as shown on drawing

(G-006). This is not shown on the Legend on the attached sheet.

Are we required to do any additional work to these walls to achieve their designated fire rating other than to fire stop any penetrations which we add to the walls? Can we assume the walls as they now exist meet the required fire rating?The legend for the fire ratings is shown on G-002. The markings in themselves do not direct the Contractor to do any upgrades to these partitions. Refer to other drawings for locations where partitions must be created or modified. The ratings are identified both for general understanding of the code compliance for the facility and to assist the Contractor in accounting for the firestopping scope that will be required as utilities are routed through the existing facility.
7006/18/2026The specifications (Para 1.4 of Section 01 00 00 required unarmed guards at all times when work is not underway. This would seem to be redundant since the site is surrounded by a 7 foot security fence and since such a small area is involved.Not Required
7106/18/2026Can we get a copy of soil report referred to in Para 1.10 of Section 010000?A/E to provide in addendum
7206/18/2026Is a Resident Engineers Office (Para 1.15 Section 010000 required? VA personnel have an equipped office where they normally work.Not Required for the COR, just for construction functions.
7306/18/2026Can the contractor's superintendent wear three hats, i.e., can he also serve as QC manager and as SSHO?Yes based on qualifications.
7406/18/2026Para 1.1 Section 01 45 35 Are any design conditions as noted in this section which require a special inspector? If so, which inspections are applicable?Refer to tables in pages 6 and 11 of Spec 01 45 35
7506/18/2026What is meant by "activation budget" Alternate 12 and 13?VA cost to open the facility.
7606/18/2026What is depth of bottom of drilled piers?As per the Geotec Report, the minimum embedment of the drilled shaft shall be 3-ft into competent unweathered Yazoo "blue" clay. The approximate elevation to top of competent unweathered Yazoo "blue" clay varies, ranges from about Elev. 312 ft to Elev. 307 ft.
7706/18/2026Who is responsible for the design of the Retaining Wall?For bidding purposes only, the Contractor shall assume conservative retaining wall design parameters where wall-specific geotechnical parameters are not provided. Final retaining wall design parameters, including lateral earth pressures, soil shear strength, bearing capacity, settlement, drainage, reinforced fill requirements, and global stability, shall be determined by the delegated retaining wall engineer and confirmed by the project Geotechnical Engineer prior to construction.The segmented retaining walls are routinely "engineered" by the manufacturers, as they are the ones who understand the limitations of their system. The extents of the retaining walls are illustrated on the drawings, which gives these manufacturers adequate ability to provide a price to the Contractors. Refer to note 8 on sheet CD101.
7806/23/2026In the event it is necessary to us slip casing to install the drilled piling, will the contractor be compensated by change
order for the increased cost? If it proves impossible to install drilled piling even using slip casing, what will be the next course of action?Refer to the Geotechnical report for anticipated soil conditions.
7906/25/2026The Deducts requested in the solicitation, and shown in the general plan pages, architectural pages, structural pages, landscape pages, and civil pages do not align. Please provide direction on which list takes precedent for pricing on bid day. Please see attached excel file with deducts highlighted in yellow.Refer to the deducts per price schedule and G-002
8006/25/2026
Can a manufacturer and color be selected for the face brick? The specifications do not include this information and describe a wide variety and types of brick.The brick veneer will use modular size face brick. The intent is to match the existing brick, which is a redish brown with some modulation in color. Contractor should obtain pricing from brick supplier for a range of options that may match and present those options for consideration during the submittal stage.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.osp.va.gov%2FHow_To_Get_A_VA_ID_Badge.asp&data=05%7C02%7C%7Ca161741650ed4b22218208de6008203d%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C639053785169652282%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=bOyRo4yD6UcMOZ261M7rEERPQ4zyMuZo1ibLTo%2BidoM%3D&reserved=0https://vatilms.va.gov/vatilms/reports/Sustainable%20Design