This is a Technical Questions and Solicitation Responses Tracking Sheet for Solicitation #36C77626R0093, Dallas VAMC - EHRM Infrastructure Upgrades Construction Project. The document contains 52 contractor questions submitted on 3/16/2026 with corresponding VA responses provided on 3/27/2026.
Key contractual and project terms include: the contract will be awarded as Firm Fixed Price (FFP) with no economic price adjustment provisions; Notice to Proceed (NTP) is anticipated within 90 calendar days after award; the project has a 730 calendar day period of performance with substantial completion required within 6 months of the September 2029 EHR deployment; contractors and their personnel must obtain VA PIV Cards before working on site; and design team members are precluded from serving as prime contractors, mentor-protégé partners, or subcontractors. The solicitation emphasizes Buy American Act compliance for construction materials, with exceptions requiring specific documentation. SDVOSB/VOSB participation is an evaluation factor, requiring offerors to be certified in the SBA database at time of submission and award. Critical infrastructure requirements include integration of new HVAC controls into the existing Siemens Building Management System (not Johnson Controls), CCTV camera integration with Avigilon ACC 7 system, and access control reader compliance with FICAM standards for integration with Hirsch Identiv systems. Telecommunications work requires Cat 6A cables with minimum 1-1/4" conduit (1" conduit prohibited), fiber optic runs with innerduct, and standardized 2-data wall outlet density unless otherwise noted. The project encompasses multiple buildings (1, 2, B2J, B3, B60, B72, B74) with ICRA Level IV infection control classifications and requires extensive coordination with the Contracting Officer's Representative for field verification of existing conditions, cable tray assessment, fire extinguisher placement, and potential variances from specification requirements.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND
| SOLICITATION #: |
| 36C77626R0093 |
| RESPONSES TRACKING SHEET |
| PROJECT TITLE: |
| Dallas VAMC - EHRM Infrastructure Upgrades Construction Project |
| # |
| RECEIVED |
| ANSWERED |
| CONTRACTOR QUESTION |
| VA RESPONSE |
| 1 |
| 3/16/2026 |
| 3/27/2026 |
| Will the government pay for materials stored per VAAR 852.232-70 and FAR 52.232-5? We have experienced PCAC Contracting Officers refusal to pay for materials stored on site during these periods of material shortages and the need to expedite procurement of materials when available to meet schedule obligations and prevent project delays. This is an important factor in preparing Price proposals. |
| In accordance with contract terms and conditions, Contractors should not submit an offer assuming the Government will approve monthly progress payments for material and/or equipment procured by the Contractor and stored on the construction site, as space is available, or at a local approved location off the site. Payment of stored materials and/or equipment is at the Contracting Officer’s discretion and will be handled on a case-by-case basis during the contract and under such terms and conditions as the Contracting Officer approves. |
| 2 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm that any designers or consultants who provided professional services for the construction documents, including reports, are precluded from pursuing this project as a Prime contractor, Mentor-Protégé partner, or subcontractor. |
| Any member of the design team of this project is not permitted to be part of the construction team. |
| 3 |
| 3/16/2026 |
| 3/27/2026 |
| Is this project tax exempt? If the project is sales tax exempt will the government/VA provide a sales tax exemption certificate? |
| See Special Note regarding FAR 52.229-3 Federal, State, and Local Taxes in the solicitation. It is solely the responsibility of the offeror to include all state and local sales or use taxes for construction materials, and all other applicable taxes, in their bid or proposal price. |
| 4 |
| 3/16/2026 |
| 3/27/2026 |
| Will the Government provide detailed written requirements for contractor badging? Please clarify the process for obtaining PIV badges, including required documentation, background checks, and estimated processing timeframes. |
| Regardless of affiliation, everyone working within VA facilities or requiring access to VA information systems requires a VA PIV Card. PIV badging requirements can be found at https://www.osp.va.gov/How_To_Get_A_VA_ID_Badge.asp |
Immediately after the bonds are provided to the Government, the contractor shall immediately start working with the identified COR at the site to commence the VA PIV process for all known contractor personnel that will be working the project. All contractors must have a PIV Card in order to work on site.
| 5 |
| 3/16/2026 |
| 3/27/2026 |
| How soon after award is NTP expected to be issued? |
| The Government anticipates issuance within 90 calendar days after award. |
| 6 |
| 3/16/2026 |
| 3/27/2026 |
| Will the VA allow deviations to Buy American Act if the noted products are not available? |
| The process of requesting exceptions to the Buy American Act is detailed in the provision at FAR 52.225-12, Notice of Buy American Requirement—Construction Materials Under Trade Agreements, and the clause at FAR 52.225-11 Buy American—Construction Materials under Trade Agreements, in the solicitation. Any items not compliant must be specifically listed in the offer. |
| 7 |
| 3/16/2026 |
| 3/27/2026 |
| Due to current potentially significant tariffs being placed on the importation of building materials such as wood or steel by the current Presidential Executive Branch, if a tariff is placed after bid time and before award will the government consider a price escalation on a contract value for products such as steel or wood should the executive branch levee tariffs effecting such materials? Most of these materials would still have been Buy American compliant as the tariffs would increase pricing on all steel or wood materials, regardless of origin. |
| This will be awarded as a Firm Fixed Price (FFP) contract and all escalation should be factored in your FFP. Additionally, FAR 52.216-4 “Economic Price Adjustment – Labor and Material” is not included in the solicitation and will not be added. |
| 8 |
| 3/16/2026 |
| 3/27/2026 |
| Could you please clarify the evaluation methodology / scoring / credit system for Factor 2: SDVOSB/VOSB Commitment? This is being solicited as “Unrestricted” - please revising to offering full credit to those that can demonstrate at least 15-20% SDVOSB participation as subcontractors. Also please explain how the evaluation criteria will be measured here if possible. |
To receive credit, an offeror must be listed at the time of submission of offers and at time of award, as a certified SDVOSB/VOSB in the SBA certification database on the SBA Veteran Small Business Certification Program portal at https://veterans.certify.sba.gov/ (see 13 CFR 128) and be otherwise eligible in accordance with SBA size standards for the acquisition and limitations on subcontracting requirements set forth in SBA regulations (see 13 CFR 121, 125 and 128).
Non-Veteran offerors proposing to use certified SDVOSBs or VOSBs as subcontractors will receive some consideration under this evaluation factor.
| 9 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm if commissioning is required for this project. |
| Reference spec section 01 91 00 |
| 10 |
| 3/16/2026 |
| 3/27/2026 |
| The 730 Calendar Day POP appears to be unrealistic. Will the VA consider providing more time? |
| No. The EHR Deployment Scheduled implementation has North Texas Upgrading in Sept. 2029. Which means substantial completion of infrastructure has to be completed within 6 months of our deployment. |
| 11 |
| 3/16/2026 |
| 3/27/2026 |
| RFI: BAS Integration Clarification |
We understand the existing Building Automation System (BAS) is a Siemens system. The project narrative on page 5, paragraph 6 states that HVAC controls will be integrated into the existing ECC system. However, Specification Section 23 09 23, Part 1, paragraph 1.1(A)(1) references “JCI building controllers.”
Please confirm whether the VA Dallas intends for the new VRF system to be fully integrated into the existing Siemens BAS, as currently provided and installed by the Siemens Area Branch Office.
Confirmed, the system needs to integrate with existing Siemens Building Management not Johnson Controls.
| 12 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm that names of specific Small Business Subcontractors, as well as their description(s) of work are required as a part of the Subcontracting Plan submission. |
| 13 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm that “Self-Certified Small Businesses” registered in SAM.GOV count towards the overall Small Business Subcontracting goal, but not towards any subcategories of Small Business. |
| 14 |
| 3/16/2026 |
| 3/27/2026 |
| Please list the subcontracting percentage goals for Total Small Business (SB), Service-Disabled Veteran-Owned Small Business (SDVOSB), Veteran-Owned Small Business (VOSB), and any other Small Business subcategory percentage goals that need to be fulfilled for this contract. |
| 15 |
| 3/16/2026 |
| 3/27/2026 |
| ET/TY series drawings for CCTV camera. Bid spec documents do not specify what systems are currently in place for this project, please answer the following questions: |
a. What is the manufacturer of the current video management system?
b. What version/existing is the current video management system operating?
c. Are we expected to support version upgrades as part of this contract?
d. Are there sufficient existing licenses to support the new cameras?
e. Are the cameras to be 2MP pan/tilt/zoom or fixed dome?
f. Is there a current maintenance/vendor/installer of this system that we can contact? Please provide contact information.
a. Avigilon
b. ACC 7
c. No version upgrade for software required
d. No licenses must be provided
e. Reference PSRDM 10.6.3 for Camera requirements.
2 MP cameras are antiquated.
f. No. VA employees install and maintain current system
| 16 |
| 3/16/2026 |
| 3/27/2026 |
| ET/TY series drawings for card reader/pin pad. Bid spec documents do not specify what system are currently in place for this project, please answer the following questions: |
a. What is the manufacturer of the current access control system.
b. What version/existing software is the access control system operating.
c. Are we expected to support the version? updates as part of the contract?
d. Are the sufficient licenses to support the new doors?
e. Is there any existing integration between the access control and CCTV systems?
f. Is there a current maintenance/vendor/installer of this system that we can contact? Please provide contact information.
a. Hirsch Identiv
b. Velocity server is provided, readers must be FICAM compliant and integrate with current system.
c. No
d. No
e. No
f. No. VA employees install and maintain current system.
| 17 |
| 3/16/2026 |
| 3/27/2026 |
| Is there an allowance for Cat 6A cables that should be included within the Div.27 pricing? Some previous requirements on other projects requested 5-10% additional Cat 6A cables to cover what may have been missed during design. |
| Yes. Per General note on Telecommunication drawings |
1. DRAWING IS DIAGRAMMATIC IN NATURE AND IS NOT TO BE CONSTRUED
AS ALL INCLUSIVE; FIELD VERIFY EXISTING CONDITIONS AND ADJUST
WORK AS REQUIRED TO EXECUTE SPECIFIED WORK.
| 18 |
| 3/16/2026 |
| 3/27/2026 |
| Existing Fire Alarm System. |
a. Q- Is there current maintenance/vendor/installer of this system that we can contact? Please provide contact information.
No. Currently VA employees are maintaining the system. VA Currently uses Notifier.
| 19 |
| 3/16/2026 |
| 3/27/2026 |
| Existing Nurse Call System. |
a. Q- Is there current maintenance/vendor/installer of this system that we can contact? Please provide contact information.
Relocation of Nurse call is not within the scope of this project.
| 20 |
| 3/16/2026 |
| 3/27/2026 |
| Is conduit required for grounding conductors running/installed ceiling & risers? |
| Grounding conductors must be installed in raceway, unless noted otherwise. |
| 21 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits? |
| 22 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a location where site asphalt and concrete can be stored/separated? Can this material be removed from the site once per week? |
| Yes. Factor removal into construction cost. |
| 23 |
| 3/16/2026 |
| 3/27/2026 |
| Will soil testing be performed prior to construction, to determine if any soils are contaminated? |
| 24 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a location where spoil dirt can be stored? |
| Yes. Factor removal into construction cost. |
| 25 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a specific location that will be used as a laydown yard during construction? |
| 26 |
| 3/16/2026 |
| 3/27/2026 |
| Will erosion control plans be provided? |
| Yes. Reference plans. |
See pg. GS006 of Attachment 3 - 549-21-700 - Construction Bid Drawings_Volume 1.pdf
| 27 |
| 3/16/2026 |
| 3/27/2026 |
| Has there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition? |
| No. |
| 28 |
| 3/16/2026 |
| 3/27/2026 |
| WAO/WAP - Is this a 1 for 1 replacement for existing cables? |
| Yes, 1 for 1 for all active IT equipment and some designated biomedical systems. |
| 29 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a requirement for a full existing conditions data survey of every room/above ceiling to confirm cable count & WAO location? If so, who dictates the outlet location and quantity of cables per location? |
| 30 |
| 3/16/2026 |
| 3/27/2026 |
| Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided. |
| 31 |
| 3/16/2026 |
| 3/27/2026 |
| What is the drop count of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone? |
| Utilize Bid Drawings to determine drop count and existing conditions. |
| 32 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a requirement for a full/complete existing conditions data survey of every room/WAO pathway/above ceiling pathway, to determine if the existing pathway meet the VA/A&E plan T501 detail & spec.? |
| See Note H below from T501 |
Contractor may either coordinate field verification with the VA or provide full or partial adjustments to existing cable pathways and WAO locations.
H. EXISTING SPLINE-TYPE CABLE TRAY MAY BE REUSED, AT THE CONTRACTORS DISCRETION, WHEN ALL THE FOLLOWING ARE TRUE: 1) IT IS IN GOOD CONDITION; 2) THE FINISHED PROJECT FILL CAPACITIES DOES/WILL NOT EXCEED THAT SPECIFIED ON T-001, GENERAL NOTES, PARAGRAPH 7; AND 3) THE STRUCTURAL INTEGRITY OF THE EXISTING TRAY AND ITS SUPPORTS HAVE NOT FAILED, SAGGED, AND ARE NOT DAMAGED OR BROKEN. CONTRACTOR SHALL VERIFY QUESTIONABLE SITUATIONS OF REUSING EXISTING TRAY WITH THE COR FOR A FINAL DECISION OR DIRECTIVE PRIOR TO COMMENCING WORK
| 33 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a count and length for Cat6A patch cords? |
| GC to field verify count. Patch cords to be provided of varying lengths. |
| 34 |
| 3/16/2026 |
| 3/27/2026 |
| Is there a count and length for Fiber Patch cords? |
| No, VA will specify as pairs are activated. |
| 35 |
| 3/16/2026 |
| 3/27/2026 |
| Is armored fiber acceptable in leu of/or is Maxcell/innerduct required for ISP fiber? |
| Use innerduct per the documents. |
| 36 |
| 3/16/2026 |
| 3/27/2026 |
| Are we to provide one patch cord each end for every new CAT6A cable installed? Or will the VA specify a quantity for the Technology contractor to provide? |
| Provide a patch cord for every new CAT6A cable installed. Patch cords to be provided of varying lengths. |
| 37 |
| 3/16/2026 |
| 3/27/2026 |
| Are we to provide patch cables for each pair of strands at each end? |
| Provide patch cables only for fibers that are terminated to active equipment/ports. Do not provide patch cables for unused strands unless specifically indicated. |
| 38 |
| 3/16/2026 |
| 3/27/2026 |
| Are we to provide one fiber jumper on each end for every strand of new Fiber cable installed? Or will the VA specify a quantity for the Technology contractor to provide? |
| No, VA will specify as pairs are activated. |
| 39 |
| 3/16/2026 |
| 3/27/2026 |
| Is there any copper backbone (25-pair or larger) needed? |
| no |
| 40 |
| 3/16/2026 |
| 3/27/2026 |
| Are there specific lengths for the Fiber jumpers? |
| Varying lengths will be needed but standardized. |
| 41 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm if we will be allowed to keep locked storage containers or Conex boxes within the grounds. |
| 42 |
| 3/16/2026 |
| 3/27/2026 |
| Is there an allowance of 1” data rough-in that should be carried within the Div.26 & 27 pricing? Some previous requirements on other projects requested 5-10% additional 1” data rough-in to cover what may have missed during design. Please advise. |
| No additional allowance for data rough-in shall be included. Provide conduit and pathways as indicated on the Contract Documents and as required per codes/standards. Note that the minimum allowable conduit size for this project is 1-1/4”; 1” conduit is not permitted. |
| 43 |
| 3/16/2026 |
| 3/27/2026 |
| On TN series plans show pathway for A/B fiber run to be installed in conduit above ceiling & in wall. |
Q-Can EMT conduit above ceiling & in wall be used in leu of rigid/IMC as per spec. 27 05 33 3.1D.?
Utilize conduit as described in 27 05 33.
Rigid is required where harsh conditions/exposure can damage EMT. Contractor to verify that EMT is appropriate for locations in which it is being installed.
| 44 |
| 3/16/2026 |
| 3/27/2026 |
| On TN series plans show a 2D for the WAO indicating (2) CAT6a cable & the same location on TND plans shows a 2D/1V indicating (2) data & (1) voice cable. |
a. Q-Voice cable/system being removed/demo completely? Please advise Voice cabling shall be demoed as shown on the drawings.
Standard WAO density shall be 2D unless otherwise noted.
| 45 |
| 3/16/2026 |
| 3/27/2026 |
| TN504 Detail 3/4/5 calls for Voice cable to be BLUE & Data cable to be WHITE. VA standard/basis of design calls for Data BLUE & Voice to be WHITE. Please advise |
| No white cable will be installed on the new network. Because of the complexity of the facility options 3/4/5 all show different combinations of faceplate configurations. TN504 details the different combinations of cable colors and wall RJ45 connectors. |
| 46 |
| 3/16/2026 |
| 3/27/2026 |
| On “T” series Plan (Technology plans) Note G |
G. ALL WAO'S INDICATED ON PLANS ARE EXISTING UON; CONTRACTOR SHALL REUSE EXISTING BACKBOXES AND ASSOCIATED CONDUIT RISER/PATHWAY; CONTRACTOR SHALL PROVIDE THE FOLLOWING AT EACH LOCATION: A NEW 4-PORT FACEPLATE AND/WITH TWO (2) NEW CATEGORY-6A CABLES IN EXISTING BACKBOX USING EXISTING PATHWAY.
INSTALL NEW (4) PORT FACE PLATE; COMPLY WITH DETAIL 5/TN506
Please provide TN506 drawing.
Please refer to page TN504.
| 47 |
| 3/16/2026 |
| 3/27/2026 |
| 33. On “T” series Plan (Technology plans) Note H |
H. EXISTING SPLINE-TYPE CABLE TRAY MAY BE REUSED, AT THE CONTRACTORS DISCRETION, WHEN ALL THE FOLLOWING ARE TRUE: 1) IT IS IN GOOD CONDITION; 2) THE FINISHED PROJECT FILL CAPACITIES DOES/WILL NOT EXCEED THAT SPECIFIED ON T-001, GENERAL NOTES, PARAGRAPH 7; AND 3) THE STRUCTURAL INTEGRITY OF THE EXISTING TRAY AND ITS SUPPORTS HAVE NOT FAILED, SAGGED, AND ARE NOT DAMAGED OR BROKEN. CONTRACTOR SHALL VERIFY QUESTIONABLE SITUATIONS OF REUSING EXISTING TRAY WITH THE COR FOR A FINAL DECISION OR DIRECTIVE PRIOR TO COMMENCING WORK
a. This note indicates a full above ceiling audit to ensure that the above criteria is identified for the existing pathway. Please confirm this is the Design Intent and that offerors should include these existing conditions surveys for all above ceiling areas of the project.
b. This note indicates a complete CAT6 cable layout/quantity to determine that the existing pathway meets the above criteria. Please confirm this is the Design Intent.
c. This note does not identify the allowance of new cable tray that should be included in offerors pricing. Please identify how offerors should accurately and competitively provide pricing for this SOW.
a. Yes, during construction cable tray conditions should be inspected prior to pulling cable. The bid should include pricing of cable tray installation in the event that existing cable tray or sections of it do not meet requirements. If an area of cable tray needs to be installed/replaced the COR will be contacted for approval.
b. Cable type should be Cat 6A. Note H 2 references the “Finished Project Fill Capacities” after demo of the original cable.
c. This is up to the contractors’ means and methods. Possible solution would be to charge for needed cable tray by the foot.
| 48 |
| 3/16/2026 |
| 3/27/2026 |
| If there are discrepancies between the Bid Documents, please advise the order of precedence for the following – Design Narratives, Specifications, Drawings, Solicitation, PCRA/ICRA Requirements. |
| Refer to FAR 52.236-21 (DEV AUG 2026) and VAAR 852.236-71. If you find discrepancies that deviate from the Specifications or the TIL https://www.cfm.va.gov/til/telecom/OIT-ISTS.pdf an RFI should be submitted. |
| 49 |
| 3/16/2026 |
| 3/27/2026 |
| According to the PCRA/ICRA Documents, BLDGs – 1, 2, B2J, B3, B60, B72 & B74 all included “whole building” classifications of ICRA LEVEL IV. Level IV classifications implement all minimum infection prevention and control measures listed on Drawing GI003 including but not limited to barriers IAW NFPA 241, Digital Differential Pressure Sensing Devices, additional ANTE Room Entry, Specialized PPE to include Tyvek suits and/or shoe covers. |
a. Please advise if this ICRA Classification applies to the entire buildings or if it is intended only for TR/TE renovations and negative air exhaust directed OUTDOORS, unless VHA ICRA Appendix A (Alternative To Outdoor Exhaust Requirements) is accepted.
b. Please advise if the use of HEPA Containment Carts is permitted for all other work outside of the TR/TE & Demarc Room Renovations.
Please advise what “triggers” must be present to receive a Letter of Acceptance for VHA ICRA Appendix A for alternate interior exhaust procedures.
Please refer to the PCRA and ICRA Construction Safety Pin located inside the PCRA and ICRA.zip document. This form serves as a guide for requesting adjustments to the safety level based on the area you are working in. Initially, all work is designated as level 4.
| 50 |
| 3/16/2026 |
| 3/27/2026 |
| If VHA ICRA Appendix A is implemented, please advise how the following requirement will be achieved in BLDGs 1, 2, B2J, B3, B60, B72 & B74, given that the PCRA/ICRA for each of these buildings list the entire building as “HIGH or HIGHEST” Risk Category in TABLE 3. |
SEE FOLLOWING REFERENCE
REFERENCE - Appendix A – Subpart f. “Exhaust must be directed to Low-Risk areas as defined in Table 3 in this VHA ICRA template. Ideally this discharge must be located so as not to impinge on high traffic areas or create a nuisance with noise or excessive airflow.”
Please refer to the PCRA and ICRA Construction Safety Pin located inside the PCRA and ICRA.zip document. This form serves as a guide for requesting adjustments to the safety level based on the area you are working in. Initially, all work is designated as level 4.
| 51 |
| 3/16/2026 |
| 3/27/2026 |
| Spur Design Narrative “Fire Protection” states that New Fire Extinguishers will be shown on the Architectural Floor Plans. However, we don’t see these devices. Please identify locations for extinguishers/cabinets and associated signage. |
| In General Overall Plan Notes on Architectural drawings it states: |
3. WALL MOUNTED CARBON DIOXIDE OR CLEAN AGENT TYPE FIRE EXTINGUISHERS REQUIRED
WITHIN 75 FT OF NEW TR. CONTRACTOR TO COORDINATE FINAL LOCATIONS WITH COR AT TIME
OF CONSTRUCTION. EXTINGUISHERS MAY NOT BE LOCATED WITHIN THE TR.
| 52 |
| 3/16/2026 |
| 3/27/2026 |
| Please confirm that the following job does not need a project schedule? |