Phasing Narrative.pdf

PDF 138 KB Posted

Attached to
Z2DA--549-21-700 EHRM Infrastructure Upgrades Construction Dallas VAMC
Solicitation number
36C77625R0093
Issued by

About this file

This is a Phasing Narrative for a federal construction project involving network infrastructure upgrades at a VA facility in Dallas, Texas (Project 549-21-700).

The project is organized into three sequential phases focused on installing fiber optic cabling with redundant A and B path ring topology across campus. Phase 1 establishes the backbone infrastructure by locating and extending a secondary Internet Service Provider (ISP) from Ann Arbor near building 9 to building 77, then extending through duct banks to building 2J Server Room. This phase includes installing fiber optic termination cabinets in the 2J Server Room and providing new fiber cabling to account for all critical and essential buildings (1, 2, 2J, 3, 8, 60, 72, 74, and 87), with fiber left reeled and ready for distribution in Phase 3. Phase 1 also completes the redundant fiber ring topology across campus through duct banks to all other buildings, with all Outside Plant (OSP) work finished by phase end. Phase 2 addresses ancillary and non-critical buildings (5, 6, 7, 8, 9, 11, 13, 44, 45, 68, 69, 71, 75, 77, 79, 80, 81, 82, and temporary buildings TT46-TT55 and Herzog buildings), working one building at a time until substantial completion, including demolition work, TR/TE construction or modification, connection to the fiber ring topology, and horizontal cabling from TRs to edge devices. Phase 3 completes fiber installation within critical and essential buildings, beginning with building 60, requiring TR construction or modification, demolition work as needed, connection to redundant fiber paths, and horizontal cabling, with strict requirements that no horizontal cabling demolition occurs until new edge devices are installed and cabled from the new TR infrastructure. The miscellaneous provisions allow schedule deviations for grouped off-hours work and require Electronic Security Systems work to be completed during TR construction.

View the file

Other files

File Type Posted
36C77625R0093 0005.pdf PDF
Technical Questions Spreadsheet - Dallas - 4-10-2026.docx DOCX document
36C77625R0093 0004.pdf PDF
Technical Questions Spreadsheet - Dallas - 4-7-2026.docx DOCX document
36C77625R0093 0003.pdf PDF
Technical Questions Spreadsheet - Dallas - 4-2-2026.docx DOCX document
C - 852.204-72 PERSONNEL VETTING AND CREDENTIALING MAR 2026.docx DOCX document
36C77625R0093 0002.pdf PDF
Technical Questions Spreadsheet - Dallas.docx DOCX document
P - 52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL - DEV NOV 2025.docx DOCX document
C - 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL - DEV MAR 2026.docx DOCX document
Electrical Narrative.pdf PDF
Environmental Narrative.pdf PDF
Security Design Narrative.pdf PDF
Sign-in Sheet - EHRM Dallas.pdf PDF
HVAC Narrative.pdf PDF
Structural Narrative.pdf PDF
36C77625R0093 0001.pdf PDF
Architecture Narrative.pdf PDF
Civil Narrative.pdf PDF
Fire Protection Narrative.pdf PDF
Telecommunications Design Narrative.pdf PDF
36C77625R0093.pdf PDF
Attachment 9 - Division Cost Breakdown.xlsx XLSX spreadsheet
Attachment 4 - 549-21-700 - Construction Bid Drawings_Volume 2.pdf PDF
Attachment 1 - V1_549-21-700_Final Bid Documents_Specifications.pdf PDF
Attachment 11 - Past Performance Questionnaire.docx DOCX document
Attachment 8 - Construction Wage Rates - Dallas - 01-02-26.pdf PDF
Attachment 6A - Addendum 01.pdf PDF
Attachment 5 - 549-21-700 - Construction Bid Drawings_Volume 3.pdf PDF
Attachment 2 - V2_549-21-700_Final Bid Documents_Specifications.pdf PDF
Attachment 10 - Site Visit Instructions.pdf PDF
Attachment 12 - Project Information Sheet for Contractors.docx DOCX document
Attachment 7 - PCRA and ICRA.zip ZIP file
Attachment 6B - Addendum 02.pdf PDF
Attachment 3 - 549-21-700 - Construction Bid Drawings_Volume 1.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA PROJECT NUMBER

PROJECT NAME

549-21-700 (2302) EHRM Upgrades Dallas, TX

SUBMITTAL Final Bid Documents SUBJECT Phasing Narrative

Phase 1

• Locate and extend secondary ISP that enters campus from Ann Arbor (near building 9) to building 77 new TR/ISP entrance facility.

o Extend ISP through duct banks from building 77 to building 2J Server Room to establish secondary ISP for campus.

• Install new fiber optic cabling termination cabinets in 2J Server Room for A and B fiber optic cabling pathways required for ring topology.

• Provide new fiber optic cabling from cabinets to account for all buildings, levels, and rooms within the critical and essential buildings (1, 2, 2J, 3, 8, 60, 72, 74, and 87).

o Leave fiber reeled and ready for distribution through the critical and essential buildings in phase 3.

• Install new fiber optic cabling redundant A and B path fiber ring topology across campus through duct banks (existing and new) to all other buildings.

o All OSP work to be completed under Phase 1.

Phase 2

• Complete all work on for ancillary buildings (non-critical or essential buildings) o Buildings 5, 6, 7, 8, 9, 11, 13, 44, 45, 68, 69, 71, 75, 77, 79 (fiber to existing rack only), 80, 81, 82, TT46, TT47, TT48, TT49, TT50, TT51, TT52, TT54, TT55, and all (3) Herzog buildings.

▪ Working in one building at a time until substantial completion (installed, tested, and approved).

• Complete all demolition work o Build new TRs/TEs or modify existing TRs in place as required o Connect TRs to redundant A and B path fiber ring topology.

o Complete all horizontal cabling work to edge devices from

TRs

VA PROJECT NUMBER

PROJECT NAME

549-21-700 (2302) EHRM Upgrades Dallas, TX

SUBMITTAL Final Bid Documents SUBJECT Phasing Narrative

Phase 3

• Install fiber optic cabling for redundant A and B path fiber ring topology each TR within the critical and essential buildings.

o 1, 2, 2J, 3, 8, 60, 70, 72, 74, and 87

▪ Build new TR/TE or modify existing TRs in place as required in each building.

• Complete demolition work as needed to install new.

o Working in one building at a time until substantial completion

(installed, tested, and approved).

o Connect TRs to redundant A and B path fiber ring topology.

o Complete all horizontal cabling work to edge devices from

TRs

▪ No horizontal cabling demolition work shall take place until new edge devices are installed and cabled from new TR supported from new backbone infrastructure.

• Contractor to start with building 60 and work their way in to the main grouping of buildings

Miscellaneous

• Deviations from schedule allowed for “off” hours work that can be reasonably grouped together

• All Electronic Security Systems (ESS) work associated with TRs shall be done during the construction of the TRs.