Fire Protection Narrative.pdf

PDF 581 KB Posted

Attached to
Z2DA--549-21-700 EHRM Infrastructure Upgrades Construction Dallas VAMC
Solicitation number
36C77625R0093
Issued by

About this file

This is a Fire Protection Design Narrative document for the VA EHRM Dallas, TX project (Project No. 549-21-700). The project, located at the VA North Texas Healthcare System Dallas Medical Campus, involves upgrading facility fiber, designing or remodeling 126 IT closets, and upgrading facility HVAC and electrical distribution. Dominique Noel, PE of Rated Engineering, serves as the Qualified Fire Protection Engineer.

The fire protection design maintains existing sprinkler and alarm system protection levels in compliance with applicable codes and standards. All sprinkler heads within TR (telecommunications) rooms will be replaced with standard response fusible link sprinklers per VA Fire Protection Design Manual requirements. TR rooms are classified as Light Hazard (0.10 gpm/1,500 sq.ft.) and will be protected with wet pipe sprinkler systems unless the existing facility lacks automatic fire sprinkler protection. Smoke detectors will be provided in existing TR spaces with power extender panels per NFPA 72. Modified sprinkler heads will have maximum spacing of one per 130 square feet; hydraulic calculations are not anticipated due to small numbers of modified heads. Clean agent fire extinguishers must be located within 75 feet of the most remote point in each TR but cannot be located within the TR itself. Fire alarm and sprinkler systems will be renovated as necessary to facilitate TR layout modifications while maintaining existing protection levels. The design complies with NFPA 13 (2022), NFPA 72 (2022), NFPA 75 (2020), NFPA 101 (2021), the VA Design Guide Infrastructure Standard for Telecommunications Spaces (Edition 3.1), and the VA Fire Protection Design Manual (Ninth Edition, November 2023). Pipe materials include steel Schedule 40 for 2-inch and smaller lines, and steel Schedule 10 may be used for 2½-inch and greater lines. The system will be commissioned per Section 0191 00 General Commissioning Requirements, with phasing outlined by the contractor to limit system outages.

View the file

Other files

File Type Posted
Technical Questions Spreadsheet - Dallas - 4-10-2026.docx DOCX document
36C77625R0093 0005.pdf PDF
36C77625R0093 0004.pdf PDF
Technical Questions Spreadsheet - Dallas - 4-7-2026.docx DOCX document
Technical Questions Spreadsheet - Dallas - 4-2-2026.docx DOCX document
36C77625R0093 0003.pdf PDF
Technical Questions Spreadsheet - Dallas.docx DOCX document
P - 52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL - DEV NOV 2025.docx DOCX document
C - 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL - DEV MAR 2026.docx DOCX document
C - 852.204-72 PERSONNEL VETTING AND CREDENTIALING MAR 2026.docx DOCX document
36C77625R0093 0002.pdf PDF
Electrical Narrative.pdf PDF
Environmental Narrative.pdf PDF
Phasing Narrative.pdf PDF
Sign-in Sheet - EHRM Dallas.pdf PDF
HVAC Narrative.pdf PDF
Structural Narrative.pdf PDF
36C77625R0093 0001.pdf PDF
Architecture Narrative.pdf PDF
Civil Narrative.pdf PDF
Telecommunications Design Narrative.pdf PDF
Security Design Narrative.pdf PDF
36C77625R0093.pdf PDF
Attachment 9 - Division Cost Breakdown.xlsx XLSX spreadsheet
Attachment 4 - 549-21-700 - Construction Bid Drawings_Volume 2.pdf PDF
Attachment 1 - V1_549-21-700_Final Bid Documents_Specifications.pdf PDF
Attachment 10 - Site Visit Instructions.pdf PDF
Attachment 12 - Project Information Sheet for Contractors.docx DOCX document
Attachment 7 - PCRA and ICRA.zip ZIP file
Attachment 6B - Addendum 02.pdf PDF
Attachment 3 - 549-21-700 - Construction Bid Drawings_Volume 1.pdf PDF
Attachment 11 - Past Performance Questionnaire.docx DOCX document
Attachment 8 - Construction Wage Rates - Dallas - 01-02-26.pdf PDF
Attachment 6A - Addendum 01.pdf PDF
Attachment 5 - 549-21-700 - Construction Bid Drawings_Volume 3.pdf PDF
Attachment 2 - V2_549-21-700_Final Bid Documents_Specifications.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA PROJECT NUMBER

PROJECT NAME

549-21-700 (2302) EHRM Dallas, TX

SUBMITTAL Final Bid Documents SUBJECT Fire Protection

Fire Protection Project Overview

The fire protection design narrative is intended to satisfy the requirements of the VA Fire Protection Design Manual, A/E Submission Instructions for Minor and NRM Construction Program, and SOW. The author of this fire protection narrative is Dominique Noel, PE of Rated Engineering. Dominique Noel is serving as the project Qualified Fire Protection Engineer as required by the Department of Veterans Affairs “Qualifications and Scope of Services - Project Fire Protection Engineer” document.

This project consists of upgrading facility fiber throughout the buildings to each IT closet, providing a redundant fiber run throughout the facility to each IT closet, provide redundant fiber mains to the demarcation room from the provider point, design or remodel one hundred twenty six IT closets throughout the facility, at specified locations adhering to the EHRM guidelines outlined in attachments, upgrade facility HVAC and electrical distribution as required, physical security assessment and upgrades and hazardous material abatement.

These telecommunication (TR) rooms (also known by deprecated terms such as IT closet, switch room, IDF, etc,) have a planned rating of 1 regardless of the rating of the supported computer room/data center.

The campus is the VA North Texas Healthcare System, Dallas (VHANTX) Medical Campus.

The building tenant/owner is the Department of Veterans Affairs.

Existing system description

Existing TRs are not required to have initiation devices or notification appliances by the VA fire protection design manual. Each existing TR spaces with a power extender panel will be provide with a smoke detector as required by NFPA 72 section 10.4.5 “early warning fire detection shall be at the location of each control unit(s), notification appliance circuit power extender(s), and supervising station transmitting equipment to provide notification of fire at that location…”

All the spaces within the SOW that have a TR room shall be protected with a wet pipe sprinkler system unless the existing facility is currently not protected with an automatic fire sprinkler system. TR rooms with exposed ceilings will be protected with upright standard response type sprinklers. Modified sprinkler heads will have a maximum spacing of one per 130 square feet.

Hydraulic calculations are not anticipated due to the small number of heads that may be modified in each building.

Selective Demolition

Fire alarm and sprinkler systems will be renovated as necessary to facilitate any modification to TR layout. Existing levels of fire protection will be maintained throughout any modified spaces. No major outages are anticipated for fire protection related work.

549-21-700 (2302) EHRM Dallas, TX

Proposed System Description

The base building fire protection system will consist of maintaining existing fire sprinkler and alarm system level of protection in accordance with the applicable codes and standards. 3.7(B) paragraph 3 from the VA fire protection design manual states “Standard response fusible link sprinklers will lessen the chance of a sprinkler being accidentally broken and will still provide structure protection since a standard response head is more robust and harder to break than a typical glass bulb quick response sprinkler.” To comply with the design guide requirements all sprinkler heads within the TR rooms will be replaced with standard response fusible link sprinklers. If TR room layout is modified the fire alarm and sprinkler systems will be adjusted to maintain the existing system coverage.

Phasing

Phasing will be outlined by contractor at time of construction so that system outages are limited.

Commissioning

The system will be commissioned subject to the requirement of Section 0191 00 General Commissioning Requirements

Seismic Requirements

• Seismic bracing is not provided on existing system components. Seismic bracing in renovated areas is not required for fire protection systems.

Applicable Codes and Standards

• NFPA 13 Standard for the Installation of Sprinkler Systems – 2022 Edition

• NFPA 72 National Fire Alarm and Signaling Code – 2022 Edition

• NFPA 75 Standard for the Fire Protection of Information Technology Equipment – 2020 Edition

• NFPA 101 Life Safety Code – 2021 Edition

• VA Design Guide Infrastructure Standard for Telecommunications Spaces – Edition 3.1 – July 1, 2021

• VA Fire Protection Design Manual – Ninth Edition – November 1, 2023

Tests Prior to design

• Any system modifications to fire alarm would require testing to ensure installation did not adversely affect overall system.

Fire suppression design

• Occupancy: See architectural narrative for life safety analysis.

549-21-700 (2302) EHRM Dallas, TX

• Classification:

o TR/TE and office spaces – Light Hazard (NFPA 13 Hazard Classification Table 5.0).

o Minor Electrical and Mechanical Spaces - Ordinary Hazard 1 (NFPA 13 Hazard Classification Table 5.0).

o Major Storage and Linen Spaces - Ordinary Hazard 1 (NFPA 13 Hazard Classification Table 5.0).

• Pipe Material: Per NFPA 13 requirements.

Wet-Pipe Sprinkler Systems

• Fire Service Entrance – Not in SOW.

• Space Occupancy Classifications:

• See Architectural narrative for occupancy classification, All TR rooms are classified as Light Hazard, 0.10 gpm/1,500 sq.ft.

• Pipe Material and Sizes

• 2-inches and smaller shall be steel, Schedule 40

• 2 ½-inches and greater may be steel, Schedule 10

Fire Extinguishers

• Fire extinguishers will be located on architectural floorplans. Existing fire extinguishers will not be impacted by the scope of this project. However, in accordance with the VA FP Design Manual Paragraph 3.7E(2), clean agent fire extinguishers shall be provided within 75 ft of the most remote point in each TR but cannot be located within the TR itself.

Manual Dry Standpipe Systems

• N/A - Not impacted by the SOW.

Dry-Pipe Sprinkler Systems

Clean Agent Fire Suppression Systems

Electric-Driven, Fire Pumps

• Not applicable to SOW.

Diesel-Driven, Fire Pumps

• Not applicable to SOW.

549-21-700 (2302) EHRM Dallas, TX

Special Electrical Systems

• The sprinkler system will be monitored by building fire alarm system.

• See Division 28 for Fire Detection and Alarm for related requirements.

End Fire Protection